  144   Thursday, July 12, 2012, 13:41 Anders Mjos      Donepurging gas lines with air
    gas lines purged with air for
60 min (through TSHUHV1 and TSHSV4).

   gas line allowed to fill with nitrogen
  
  151   Thursday, July 19, 2012, 09:35 Anders Mjos      DoneVenting to investigate leak on front doorThursday, July 19, 2012, 09:35: Switched
off both turbos.
Thursday, July 19, 2012, 10:23: Venting
  
  153   Thursday, July 19, 2012, 11:32 Anders Mjos      DonePumping downThursday, July 19, 2012, 11:29: roughing
Thursday, July 19, 2012, 11:49: starting
turbos
  
  177   Friday, August 17, 2012, 12:53 Pierre Bricault      Done Test completed.
exel file on My Documents in folder
FEBIAD Test Aout2012/TestFEBIAD
 TestFEBIAD.xlsx 
  182   Friday, August 24, 2012, 08:28 Anders MjosNiO#1HP-FEBIADITETM4  DoneNiO#1 installed

    

       
            
  
  190   Friday, August 31, 2012, 11:12 Aurelia Laxdal HP-FEBIADITETM4  DoneFinished testing NiO#1Turned off the HV and the optics in the
first section. Couldn't turn off the optics
in the second section: left a message for
  
  191   Friday, August 31, 2012, 11:39 Anders MjosNiO#1HP-FEBIADITETM4  DoneVenting vacuum chamber - source changeFriday, August 31, 2012, 11:39: Stopped
turbos.
Friday, August 31, 2012, 13:06: Venting.
  
  193   Tuesday, September 04, 2012, 08:11 Anders MjosNb#7LP-SISITWTM1  DoneNb#7 installed

    

       
            
  
  196   Friday, September 07, 2012, 13:10 Friedhelm AmesNb#7     Donemass scan finishedmass scan is finished saved as 
 
  Normal

 0
  
  
  199   Tuesday, September 11, 2012, 19:48 Friedhelm AmesNB#7HP-SIS    Donecool down finished, all source power supplies off.    
  204   Friday, September 14, 2012, 15:27 Anders MjosNb#7LP-SISITWTM1  DoneVentingTarget cooled down. Power supplies off.
Friday, September 14, 2012, 15:27:
Turbos off.
  
  212   Monday, September 24, 2012, 15:25 Anders Mjos      DoneTMS RP and TP started    
  214   Tuesday, September 25, 2012, 13:25 Anders Mjos      DoneStarted turbos after replaced roughing pump    
  224   Friday, October 26, 2012, 08:29 Anders MjosTiC#3LP-SISITWTM1  DoneTarget ready for conditioning

    

       
            
  
  228   Friday, November 02, 2012, 15:40 Aurelia Laxdal LP-SISITWTM1  DoneSiC#3 cooldown startedStarted the cooldown for SiC#3.   
  229   Monday, November 05, 2012, 09:47 Aurelia Laxdal LP-SISITWTM1  DoneTPS optics cannot be turned off. All TPS optics, with the exception of TPS:Q4
cannot be turned off. E-Fault#6395 for Controls.
Same for the TSG optics: CB1, VCB1
  
  230   Monday, November 05, 2012, 13:26 Aurelia Laxdal LP-SISITWTM1  DoneVenting the Test StandVenting the Test Stand.
TiC#3 will be ready to be removed
in few minutes. 
  
  231   Monday, November 05, 2012, 14:41 Anders MjosTiC#3LP-SISITWTM1  DoneTarget RemovedTarget looks OK. The right leg was a bit
much out of center and will be adjusted in
the lab.
  
  232   Monday, November 05, 2012, 14:42 Anders MjosTest SiCHP-FEBIAD    DonePumping downMonday, November 05, 2012, 14:41: Roughing
Monday, November 05, 2012, 14:58:
Started turbos
  
  245   Tuesday, December 11, 2012, 13:40 Sebastian RaederRFQ empty     DoneHeating test for Ion guide Laser ion sourcenew ion guide laser ion source installed.
Pure target container without targetmaterial
and without surface ion source.
 heatint_rfq_dec11_2012.PNGheatint_rfq_dec12_2012.PNG 