Tuesday, July 27, 2021, 12:57, Fernando Maldonado, , LP-FEBIAD, , , 41790-10, 44378-5, Failed, FEBIAD parameter scan - efficiency measurements
|
Assembly has new gas tube to the target for better fit and clearance to the HS.
Electric checks before closing shows no short between TIS and HS.
Tuesday, July 27, 2021, 12:57: Venting |
Wednesday, July 28, 2021, 08:48, Fernando Maldonado, , LP-FEBIAD, , , 41790-10, 44378-5, Failed, FEBIAD parameter scan - efficiency measurements
|
Modified spiral tube from VCR to counteract torque towards the HS. Now points towards TBHT.
Electric checks before closing shows no short between TIS and HS. |
Friday, July 30, 2021, 15:34, Carla Babcock, , , , , , , Failed, TSG:RP1 failure
|
TP1A tripped off on Fernando, seems the backing pressure got too high. Even with PV1 closed the RP1 pump could not get below 200mTorr. Derek from vacuum
group came and had a look, and is swapping RP1 out for one of the vacuum group pumps, then will see if they can repair ours. |
Wednesday, March 29, 2023, 12:22, Aaron Schmidt, TiC#5, LP-FEBIAD, ITE, TM4, 44692-7, 45235-20, Failed, Conditioning TiC#5
|
Wednesday, March 29, 2023, 09:15: Roughing.
Wednesday, March 29, 2023, 12:22: TP1B on.
Wednesday, March 29, 2023, 12:40: TP1A on. |
Tuesday, September 20, 2011, 19:00, Aurelia Laxdal, TaC#1, LP-SIS, ITE, TM1, 38634-6, 36833-6, Done, Finished testing TaC#1
|
Tuesday, September 20, 2011:
Did another mass scan today at 5:40. Saved as: plotdump-local-clean.txt Sept 20 11 11-51-20.txt
Started target cool-down. Tomorrow the target would be ready to be removed from the Test Stand. |
Friday, September 30, 2011, 18:03, Aurelia Laxdal, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, Done, Finished testing SiC#26 at the Test Stand
|
Today, did a did a mass scan: plotdump-local-clean.txt Sep30 11 12-20-08.txt
Optimized a bit the tune with Friedhelm, then started the Target Cooldown. |
Monday, October 03, 2011, 10:53, Aurelia Laxdal, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, Done, Target is ready to be removed.
|
Turned off the HV and locked up the transformer. Isolated the ion source box. The target is under vacuum and the water is still on. |
Monday, October 03, 2011, 13:56, Anders Mjos, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, Done, Venting
|
Aurelia Laxdal wrote:
Turned off the HV and locked up the transformer. Isolated the ion source box. The target is under vacuum |
Monday, October 03, 2011, 14:46, Anders Mjos, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, Done, Target stored under vacuum
|
Anders Mjos wrote:
|
Wednesday, October 12, 2011, 13:14, Anders Mjos, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, Done, Target removed
|
Anders Mjos wrote:
|
Friday, February 17, 2012, 10:27, Aurelia Laxdal, , , , , , , Done, Started the Archivers
|
Started both ISACT and SOURCES Archivers. |
Wednesday, March 07, 2012, 09:27, Friedhelm Ames, Nb#6, , , , , , Done, water cooling started
|
water cooling line valves opened. No response on vacuum TSG:IG1 3.5e-7 T |
Thursday, May 17, 2012, 08:36, Anders Mjos, SiC#27, HP-SIS, ITE, TM4, , , Done, Target removed
|
Thursday, May 17, 2012, 08:36: Turbo pumps switched off in preparation of target removal.
Thursday, May 17, 2012, 08:51: Purging cooling lines.
Thursday, May 17, 2012, 08:55: Venting. |
Monday, June 04, 2012, 10:51, Anders Mjos, Ta#38, LP-SIS, ITW, TM1, , , Done, Venting chamber
|
Aurelia Laxdal wrote:
Did the HV conditioning. |
Tuesday, June 26, 2012, 16:06, Anders Mjos, , , , , , , Done, Vented
|
Anders Mjos wrote:
HS water lines blanked. |
Friday, July 06, 2012, 15:36, Friedhelm Ames, , , , , , , Done, switched everything off
|
switched everything off to prepare for scheduled power outage on Monday |
Monday, July 09, 2012, 12:57, Anders Mjos, , , , , , , Done, Vented
|
|
Thursday, July 12, 2012, 12:23, Anders Mjos, , , , , , , Done, TSH:SV5 bypass on
|
Thursday, July 12, 2012, 15:48: bypass removed |
Thursday, July 12, 2012, 13:41, Anders Mjos, , , , , , , Done, purging gas lines with air
|
gas lines purged with air for 60 min (through TSHUHV1 and TSHSV4).
gas line allowed to fill with nitrogen to 300 torr and evacuated.
repeated 3 times.
|
Thursday, July 19, 2012, 09:35, Anders Mjos, , , , , , , Done, Venting to investigate leak on front door
|
Thursday, July 19, 2012, 09:35: Switched off both turbos.
Thursday, July 19, 2012, 10:23: Venting
|
|