Entry  Friday, September 23, 2011, 15:38, Rick Maharaj, , , , , , , , test stand vented 

Test stand vented

Entry  Thursday, October 13, 2011, 12:33, Rick Maharaj, Training , , , , , , , Test stand vented 

test stand vented

Entry  Tuesday, May 15, 2012, 07:39, Rick Maharaj, Sic #27, HP-SIS, ITE, TM4, , , In progress, Water on at test stand 

The vacuum on TSGIG1 reads 2.85e-07. Turing on water on teststand and observing any changes in vacuum pressure.

Entry  Tuesday, May 15, 2012, 08:08, Rick Maharaj, sic#27, , , , , , , Turbos off 

Target needs to be removed form teststand to remove heatshielding around target oven. The chamber will be vented, water circuits flushed and target removed.

Entry  Tuesday, May 15, 2012, 08:15, Rick Maharaj, , , , , , , , Test Stand chamber venting 
 
Entry  Tuesday, May 15, 2012, 08:16, Rick Maharaj, , , , , , , , Water circuits flushed 
 
Entry  Tuesday, May 15, 2012, 08:42, Rick Maharaj, , , , , , , , target removed 
 
Entry  Tuesday, May 15, 2012, 09:46, Rick Maharaj, , , , , , , , target reinstalled pumping started 
 
Entry  Friday, August 10, 2012, 14:08, Rick Maharaj, , , , , , , , Gas line pump 

Gas line vacuum pump reinstalled after fitting was modified to receive a standard swagelok connector. The vacuum line was plumbed using 1/4" copper tube (not Stainless) for the the ability to flex and manipulate the line for pump removal and and insertion.

Entry  Tuesday, May 21, 2013, 10:09, Rick Maharaj, , , , , , , , Test stand Vented 

Turbos stopped, waterlines flushed, chamber vented

Entry  Tuesday, May 21, 2013, 14:58, Rick Maharaj, CTL Febiad, , , , , , , CTL Febiad Installed 

Ceramic coated coil development target removed. CTL Febiad target installed.

Roughing chamber.

Entry  Tuesday, May 21, 2013, 15:14, Rick Maharaj, CTL Febiad, , , , , , , Turbos Started 

Turbos started

Entry  Tuesday, May 21, 2013, 15:50, Rick Maharaj, CTL Febiad, , , , , , , Cooling Water Turned On 

Cooling water turned on when vacuum reading 5.54e-06 T. Vacuum steadily increasing. Ion gauge reading steadily decreasing now reading 4.48e-06 T.

Entry  Tuesday, October 22, 2013, 15:20, Rick Maharaj, , , , , , , Problems/Solutions, Target Heater Conductor Block Insulators Replaced Source_Tray_TGHT_and_COIL_insulators_replaced_2013-10.pdf

The Conductor insulating blocks - ITD053C and ITD054C - that secure the target heater and coil conductor blocks were replaced. The existing ones were cracked and fell apart upon removal.

Entry  Wednesday, March 12, 2014, 10:20, Rick Maharaj, , , , , , , Done, replace heatshield waterline loop 

A new Heatshield waterline loop was manufactured and installed to replace the old one which had a leak.

Chamber vacuum currently being roughed down.

Wednesday, March 12, 2014, 10:41: Started turbos.

Wednesday, March 12, 2014, 10:5:0 Turbos at speed. TP1A timed out once.

Wednesday, March 12, 2014, 10:51: Vacuum at 2.6E-5 T.  


By AM

Thursday, March 13, 2014, 10:20: Opened water. Vacuum stable at 9.3E-7 T.

Venting chamber to investigate slow pump down.

Thursday, March 13, 2014, 10:21: Stopped turbos.

Thursday, March 13, 2014, 11:15: Venting

 

By RM

HS loop wiped with methanol, door seals wiped.

Thursday, March 13, 2014, 11:47: Pump down Started

Thursday, March 13, 2014, 12:05: Turbos started

Thursday, March 13, 2014, 12:09: TP1B at speed

Thursday, March 13, 2014, 12:12: TP1A at speed

Thursday, March 13, 2014, 12:13: IG1 turned on Vacuum at 7.2E-06


By AM

Monday, March 17, 2014, 12:55 : Stopped turbos. Vacuum at 2.4E-7 T. 

Monday, March 17, 2014, 17:39: Venting

 

Entry  Friday, April 04, 2014, 17:01, Rick Maharaj, UC#9, LP-SIS, ITW, TM1, , 39230-3, Done, Conditioning Heatshield for UCx#9 

Friday, April 04, 2014, 16:26: Heatshield/Ionsource assembly for UC LP SIS  installed in test stand with Ta tube as heat load.

Friday, April 04, 2014, 16:29: Chamber roughing started

Friday, April 04, 2014, 16:51: Turbos started

Friday, April 04, 2014, 16:59: TP1B at speed

Friday, April 04, 2014, 17:00: TP1A at speed

Friday, April 04, 2014, 17:00: IG1 Turned on vacuum at 2.8e-05T

 


Tuesday, April 08, 2014, 10:37: Vacuum 1.8e-07 T - Heatshield water turned on

Tuesday, April 08, 2014, 10:40: No change in vacuum pressure.

 


Wednesday, April 09, 2014, 11:46: Started heating tght to 200 amps

Wednesday, April 09, 2014, 14:58: Heating increased to 400 amps

 


Thursday, April 10, 2014, 14:58: Heating increased to 580 amps


By AM

Friday, April 11, 2014, 14:57: Started cool down. Vacuum at 4.2E-7 T


By AM

Wednesday, April 23, 2014, 09:18: Turbos stopped. Vacuum at 1.2E-7 T

Wednesday, April 23, 2014, 13:50: Venting

Wednesday, April 23, 2014, 14:14: Heat Shield removed

Entry  Tuesday, February 28, 2012, 10:29, Pierre Bricault, , LP-FEBIAD, , , , , In progress, Test FEBIAD at ISAC test statnd 
 
Entry  Tuesday, February 28, 2012, 11:04, Pierre Bricault, , , , , , , ,  

 Calibrating the gas valve

Entry  Tuesday, March 06, 2012, 15:15, Pierre Bricault, , HP-SIS, , , , , , ISAC test stand two turbos replaced 

Vac group has replaced the two turbo pumps.

Entry  Tuesday, March 06, 2012, 15:17, Pierre Bricault, , , , , , , , ISAC test stand 

Start turbo pumps at 1514H