Monday, September 24, 2012, 15:25, Anders Mjos, , , , , , , Done, TMS RP and TP started
|
|
Tuesday, September 25, 2012, 13:05, Anders Mjos, , , , , , , Problems/Solutions, TSG:RP1 will not start without blowing the fuse
|
Anders Mjos wrote:
See e-fault 6329 |
Tuesday, September 25, 2012, 13:25, Anders Mjos, , , , , , , Done, Started turbos after replaced roughing pump
|
|
Tuesday, September 25, 2012, 16:10, Aurelia Laxdal, , , , , , , , Conditioning - SiC-HP-FEBIAD for operator training
|
Did the HV conditioning up to 30kV.
Started the heaters conditioning:
for TSH:TGHT up to 580A |
Thursday, September 27, 2012, 12:27, Aurelia Laxdal, , , , , , , In progress, SiC-HP-FEBIAD for operator training
|
The source was used yesterday for operator training.
Today, I found the source off: the ISAC PLC Status was stopped. Kazuya re-started the PLC. I will re-start the source. |
Friday, September 28, 2012, 09:59, Aurelia Laxdal, , , , , , , In progress, SiC-HP-FEBIAD for operator training - Source Off
|
Checked with ISAC Ops this morning and they are not available for FEBIAD training. Turned off the source until next week. |
Wednesday, October 10, 2012, 10:47, Friedhelm Ames, , , , , , , Failed, found teststand tripped off
|
turbo pumps in source section and all ion gauges off all optics and heaters tripped. Reason unknown. |
Wednesday, October 10, 2012, 17:35, Aurelia Laxdal, , , , , , , Failed, found teststand tripped off
|
Friedhelm Ames wrote:
turbo pumps in source section and all ion gauges off all optics and heaters tripped. Reason unknown. |
Thursday, November 29, 2012, 14:15, Anders Mjos, , , , , , , In progress, Venting in preparation for RFQ work
|
Thursday, November 29, 2012, 14:15: Stopping turbos
Thursday, November 29, 2012, 15:57: Venting |
Thursday, November 29, 2012, 16:21, Anders Mjos, , , , , , , , Pumping down
|
Thursday, November 29, 2012, 16:21: Roughing |
Friday, November 30, 2012, 10:42, Anders Mjos, , , , , , , , Venting
|
|
Friday, November 30, 2012, 12:04, Anders Mjos, , , , , , , In progress, 9-pin connector installation work in progress
|
in preparation for RFQ testing. By Sebastian and Anders
An insulated 9-pin D-sub connector was installed on the service cap in port Q (as labeled in ISK4523). The connector mating to the target
assembly was placed in the upper slot on the source tray. |
Monday, December 03, 2012, 15:33, Anders Mjos, , , , , , , In progress, Leak check of 9-pin feed through
|
Base leak rate 6 - 7 E-9 mbar-l/s
A leak was found around the 9-pin feed through. |
Tuesday, December 04, 2012, 11:05, Anders Mjos, , , , , , , , Vented
|
In preparation for RFQ target and leak troubleshooting.
Tuesday, December 04, 2012, 11:04: Turbos off (vacuum at 3.8E-7 T)
Water lines purged. |
Tuesday, December 04, 2012, 17:27, Anders Mjos, RFQ empty, , , , , , In progress, Pumping down
|
The RFQ heating test target was installed by Sebastian and Anders.
Tuesday, December 04, 2012, 17:26: roughing
Tuesday, December 04, 2012, 17:45: starting turbos |
Wednesday, December 05, 2012, 11:18, Anders Mjos, , , , , , , In progress, Leak checking 9-pin feed through
|
Vacuum at 4.4E-7T
Base leak rate 2 - 3 E-9 mbar-l/sec
No response above background. |
Thursday, December 06, 2012, 08:41, Anders Mjos, , , , , , , , Opened cooling water
|
Vacuum stable at 2.8E-7 T |
Tuesday, December 11, 2012, 13:27, Sebastian Raeder, , , , , , , , 9 PIN connector
|
A Sub D 9 Pin connector on a HV insulator was installed on Port Q of the target box at the teststand. The insulator is leak tested and OK, vacuum is
below 2E-7 T
The feed through is connected (1to1) to the upper 9 Pin connector of the target tray. Since the existing upper 9 Pin connector was damaged from |
Tuesday, December 11, 2012, 13:40, Sebastian Raeder, RFQ empty, , , , , , Done, Heating test for Ion guide Laser ion source
|
new ion guide laser ion source installed. Pure target container without targetmaterial and without surface ion source.
Heat up to 580A for heat test of all components. Distance between target and repeller < 1mm
|
Thursday, December 13, 2012, 08:40, Anders Mjos, RFQ empty, , , , , , In progress, Venting
|
Thursday, December 13, 2012, 08:38: TBHT and TGHT off
Thursday, December 13, 2012, 08:38 : Vacuum at 1.8E-7 T
Thursday, December 13, 2012, 08:38 : Turbos off |
|