Entry  Friday, August 17, 2012, 10:09, Pierre Bricault, , , , , , , In progress, FEBIAD test cathode bias 
Backing pressure on the bender section is quite large. TMSIG6 reads 5.09E-7 T and TMS:CG2B reads 0.249 T!
Entry  Thursday, August 23, 2012, 10:11, Anders Mjos, , , , , , , In progress, Venting - installation of NiO#1 
Thursday, August 23, 2012, 10:10: Vacuum 2.1E-7
Thursday, August 23, 2012, 10:10: Stopped both turbos.
Thursday, August 23, 2012, 10:20: Water purged.
Entry  Thursday, August 23, 2012, 11:39, Anders Mjos, NiO#1, HP-FEBIAD, ITE, TM4, , , In progress, NiO#1 installed 
Thursday, August 23, 2012, 11:38: NiO#1 installed.
Thursday, August 23, 2012, 11:38: Started roughing. Both roughing pumps timed out.
Thursday, August 23, 2012, 11:54: Roughing.
Entry  Monday, August 27, 2012, 13:21, Aurelia Laxdal, NiO#1, HP-FEBIAD, ITE, TM4, , , In progress, HV conditioning at Test Stand  
Did HV conditioning up to TSG:BIAS=30kV, TSH=EE=-600V
Turned off the HV for Kazuya to check the connection/output of the TSG:TGHT Xantrex power supply.
Entry  Monday, August 27, 2012, 15:21, Aurelia Laxdal, , , , , , , In progress, Xantrex PS 10-600 for TSH:TGHT is not working  
When turned ON it was not going higher than 3.6A (EPICS/front panel).  Kazuya checked the connections at the back and also the EPICS/PLC/PS  input/output
signals. He compared these values with the similar once of  the TSH:TBHT PS  (which is also a Xantrex PS 10-600). E-Fault 6275
It turned out to be the connections on the top of the ion source box: the target heater was not connected and the power supply was not seeing the
Entry  Tuesday, August 28, 2012, 16:57, Aurelia Laxdal, , HP-FEBIAD, ITE, TM4, , , In progress, Updates for NiO#1 at Test Stand 
Tested the power supplies and locked up the HV cage.
Turned on the HV: 30kV.
Tomorrow we'll start up the heaters: 580A for the target and 280-300A for the tube.
Entry  Wednesday, August 29, 2012, 11:34, Aurelia Laxdal, , HP-FEBIAD, ITE, TM4, , , In progress, NiO#1 heating startup & few checks 
Friedhelm checked the voltage across R4 from ISK4563D-rev2.pdf. It shows 50 kOhms with the power supplies off and everything connected according to the
drawing. With the Anode PS On and set at 20V, we could see the same readback on EPICS and on the meter.
Then started the heater ramping: auto ramp 2A/min.
Entry  Thursday, August 30, 2012, 14:34, Aurelia Laxdal, , HP-FEBIAD, ITE, TM4, , , In progress, NiO#1 updates 


Normal
0




false
false
false

EN-US
X-NONE
X-NONE

Entry  Thursday, August 30, 2012, 16:51, Aurelia Laxdal, , HP-FEBIAD, ITE, TM4, , , In progress, NiO#1 cooldown started 
Started the cooldown.
Entry  Friday, August 31, 2012, 13:59, Anders Mjos, Nb#7, LP-SIS, ITW, TM1, , , In progress, Nb#7 installed 
Friday, August 31, 2012, 15:19: roughing
Friday, August 31, 2012, 15:39 : starting turbos
Friday, August 31, 2012, 15:44 : TP1B at speed
Entry  Friday, September 07, 2012, 12:11, Friedhelm Ames, NB#7, LP-SIS, , , , , In progress, mass scan started 
mass scan has been started after optimization on 23Na
Entry  Tuesday, September 11, 2012, 13:13, Friedhelm Ames, Nb#7, LP-SIS, , , , , In progress, start cool down 
start cooldown. Found computer at teststand off. Somebody tried to login with username ARIEL.
Entry  Wednesday, September 12, 2012, 08:02, Anders Mjos, Nb#7, LP-SIS, ITW, TM1, , , In progress, Venting 
Wednesday, September 12, 2012, 08:01: Turbos off
Wednesday, September 12, 2012, 13:35: Venting, water off and purged.
Wednesday, September 12, 2012, 13:55: Vented
Entry  Wednesday, September 12, 2012, 17:04, Anders Mjos, Nb#7, LP-SIS, ITW, TM1, , , In progress, Pumping down - w/replaced insulators 
Replaced swollen insulator and added Ta heat shield on insulator.
 
Wednesday, September 12, 2012, 17:03: Roughing
Entry  Thursday, September 13, 2012, 08:24, Anders Mjos, Nb#7, LP-SIS, ITW, TM1, , , In progress, Water on 
Thursday, September 13, 2012, 08:16: Opened up cooling water. Vacuum (IG1) increased from 5.9E-7 to 6.2E-7 before returning to 5.9E-7. Similar response
on IG6 (valve closed). Response is however similar to previous (short time ~5 min) vacuum fluctuations.
Entry  Friday, September 14, 2012, 16:33, Anders Mjos, , , , , , , In progress, Pumping down empty chamber 
Friday, September 14, 2012, 16:33: Roughing
Friday, September 14, 2012, 16:57: Starting turbos
Friday, September 14, 2012, 17:05 : Turbos at speed
Entry  Thursday, September 20, 2012, 14:24, Anders Mjos, , , , , , , In progress, Venting - installation of FEBIAD test target for operator training 
Thursday, September 20, 2012, 14:24: Turbos off
Thursday, September 20, 2012, 15:20: Venting
Entry  Thursday, September 20, 2012, 15:52, Anders Mjos, TEST SiC, HP-FEBIAD, , , , , In progress, Installilng SiC-HP-FEBIAD target for operator training 
Thursday, September 20, 2012, 15:50: Roughing
Thursday, September 20, 2012, 15:54: Aborting. VCR for gas line not connected.
Thursday, September 20, 2012, 16:09: Roughing
    Reply  Friday, September 21, 2012, 08:20, Anders Mjos, TEST SiC, HP-FEBIAD, , , , , In progress, Installilng SiC-HP-FEBIAD target for operator training 


    
        
            Anders Mjos wrote:
        
        
            
            Thursday, September 20, 2012, 15:50: Roughing
Entry  Thursday, September 27, 2012, 12:27, Aurelia Laxdal, , , , , , , In progress, SiC-HP-FEBIAD for operator training 
The source was used yesterday for operator training.
Today, I found the source off: the ISAC PLC Status was stopped. Kazuya re-started the PLC. I will re-start the source.