ID |
Date |
Author |
Target/No.# |
Source |
Station |
Module |
Target Oven W.O# |
Heat Shield W.O# |
Status |
Subject |
Text |
 |
493
|
Friday, January 22, 2016, 13:35 |
Aurelia Laxdal | | | | | | | Problems/Solutions | TSG:RP1 nor performing |
|
|
974
|
Thursday, July 13, 2023, 18:29 |
Aurelia Laxdal | | LP-SIS | | | | | In progress | Spectrometer tests | Pumping down: TS loaded with a LP-SIS
container for spectrometer test.
Started heating up the target container: |
|
1015
|
Monday, July 29, 2024, 23:02 |
Aurelia Laxdal | Ta#67 Thin foils | LP-SIS | ITE | TM3 | 45447-14 | 45235-10 | | Cooldown for removing the V wires | 22:55 Cooldown completed to remove
the voltage wires from inside the vacuum
box. |
|
3
|
Wednesday, September 14, 2011, 15:40 |
Anders Mjos | TaC#1 | LP-SIS | ITE | TM1 | 38634-6 | 36833-6 | In progress | TaC#1 installed and pumping down. | Wednesday, September 14, 2011, 15:39: Vacuum
at 1.3e-5 torr
Thursday, September 15, 2011, 08:59: |
|
4
|
Thursday, September 15, 2011, 09:20 |
Anders Mjos | | | | | | | | ISAC TestStand old e-log | link
to old e-log |
|
5
|
Thursday, September 15, 2011, 13:46 |
Anders Mjos | FEBIAD Test | HP-FEBIAD | | | | | Failed | FEBIAD Broken Tube | See attached file for photos of the broken
tube |
|
10
|
Friday, September 23, 2011, 16:40 |
Anders Mjos | | | | | | | Problems/Solutions | 9-pin connectors swapped on source tray | Friday, September 23, 2011, 16:3: The connection
on the 9-pin connector for FEBIAD targets
showed burn marks from the previous FEBIAD |
|
11
|
Friday, September 23, 2011, 16:42 |
Anders Mjos | SiC#26 | HP-FEBIAD | ITE | TM4 | 38295-9 | 38307-8 | In progress | Target ready to be heated | Friday, September 23, 2011, 16:4: Target
installed and roughing started.
Friday, September 23, 2011, 17:12: |
|
13
|
Monday, September 26, 2011, 16:14 |
Anders Mjos | | | | | | | Problems/Solutions | Fixed leak on water line for HS, added Kapton insulation |
While testing SiC#26 a leak
was discovered on the water line to the heat
shield. The leak was in the right joint (see |
 |
19
|
Monday, October 03, 2011, 13:56 |
Anders Mjos | SiC#26 | HP-FEBIAD | ITE | TM4 | 38295-9 | 38307-8 | Done | Venting |
|
|
20
|
Monday, October 03, 2011, 14:46 |
Anders Mjos | SiC#26 | HP-FEBIAD | ITE | TM4 | 38295-9 | 38307-8 | Done | Target stored under vacuum |
|
|
21
|
Wednesday, October 12, 2011, 13:14 |
Anders Mjos | SiC#26 | HP-FEBIAD | ITE | TM4 | 38295-9 | 38307-8 | Done | Target removed |
|
|
23
|
Thursday, October 13, 2011, 15:42 |
Anders Mjos | Training | HP-FEBIAD | | | | | Problems/Solutions | Target ready to be heated |
|
|
24
|
Monday, October 17, 2011, 10:22 |
Anders Mjos | FEBIAD | | | | | | Problems/Solutions | Variable leak valve replaced | Variable leak valve with serial number
F3-592 has been replaced by F3-649 due
to regulating problems described previously |
|
25
|
Monday, November 14, 2011, 15:40 |
Anders Mjos | | | | | | | Problems/Solutions | Variable leak valve repaired |
|
|
28
|
Tuesday, December 20, 2011, 16:09 |
Anders Mjos | | | | | | | Problems/Solutions | Variable leak valve repaired |
|
|
33
|
Thursday, February 16, 2012, 15:59 |
Anders Mjos | | | | | | | Problems/Solutions | He and Ne installed and gas lines leak checked | New supply of He and Ne was installed yesterday
and gas lines leak checked. The He bottle
is currently closed. |
|
49
|
Friday, March 02, 2012, 08:53 |
Anders Mjos | FEBIAD test | | | | | | Problems/Solutions | Tube heater insulator glowing | The insulator for the tube
heater was observed to be glowing with a
blue shine when the target was on high voltage. |
|
50
|
Friday, March 02, 2012, 13:28 |
Anders Mjos | FEBIAD test | | | | | | | Venting test stand | Venting for target exchange |
|
72
|
Monday, April 16, 2012, 11:16 |
Anders Mjos | Nb#6 | LP-SIS | ITW | TM1 | | | In progress | Venting, purging cooling lines | Venting chamber and purging cooling lines
in preparation for target removal |
|