Wednesday, February 15, 2017, 13:42, Aaron Schmidt, , , , , 42218-11, 41751-6, Problems/Solutions, Vacuum Check (Water leak)
|
*Vacuum from previous test still active, minus turbo pumps. Same target, & heat shield as well.*
Wednesday, February 15, 2017, 13:38: Both Turbo pumps started.
Wednesday, February 15, 2017, 13:43: Ion gauge on. TP1B @ speed 42 KRPM. |
Tuesday, February 21, 2017, 10:35, Aaron Schmidt, , , , , 42218-11, 41751-6, Problems/Solutions, Water leak (E)(G)
|
Water leak found on water block lines (E) & (G) on FS #3.
Both lines were removed at the water blocks and the coil connection at the heat shield. They ends were blanked off.
Tuesday, February 21, 2017, 10:32: Roughing |
Monday, April 10, 2017, 15:12, Anders Mjos, , , , , , , Problems/Solutions, Vacuum leak on front door
|
The vacuum behaved erratic over night with excursion up into the mid 10^-6 Torr range. To investigate the chamber was vented. With the doors open, the
o-rings and sealing surfaces were cleaned. When pumping down again a vacuum leak could be heard at the front door by the lock. The chamber was vented again
twice, finally the two o-rings were swapped. This removed the large leak. The door is prevented from contacting the box at the lock, which is likely the |
Wednesday, April 12, 2017, 16:04, Anders Mjos, , , , , , , Problems/Solutions, Leak on FS#3 COIL and EE
|
A water to vacuum leak has been found on FS#3. The leak is not detected on the leak detector, but can be seen as an increase in vacuum and on partial
water pressure on the RGA
Wednesday, April 12, 2017, 17:11: The leak is on circuit EG (Coil +). Confirmed with water pressure |
Tuesday, April 18, 2017, 07:46, Aaron Schmidt, , , , , , , Problems/Solutions, TSG:TP1B & TSG:BV1B tripped
|
Tuesday, April 18, 2017, 07:30: TSG : TP1B Tripped on Saturday.
Tuesday, April 18, 2017, 07:40: TSG : BV1B opened. TSG : TP1B restarted.
Tuesday, April 18, 2017, 07:48: TSG : TP1B failed to restart.Turn off. |
Wednesday, May 17, 2017, 10:17, Anders Mjos, , HP-FEBIAD-CTL, , , , , Problems/Solutions, Sparking between new coil line and ground electrode
|
Wednesday, May 17, 2017, 10:17: Sparking around 20 kV. Will need to vent to increase gap between water lines.
Turbos stopped.
Wednesday, May 17, 2017, 10:50: Reset IV4. |
Wednesday, May 24, 2017, 11:12, Anders Mjos, , , , , , , Problems/Solutions, FEBIAD Anode bias configuration
|
The Test Stand has been configured for Anode bias. John Chow changed the power supply and the electrical connections have been wired according
to ISK4523D REV 6.
|
Saturday, June 03, 2017, 09:34, Anders Mjos, , , , , , , Problems/Solutions, FEBIAD Cathode bias configuration
|
Anders Mjos wrote:
The Test Stand has been configured for Anode bias. John Chow changed the power supply and the |
Thursday, August 03, 2017, 17:00, Anders Mjos, , , , , , , Problems/Solutions, Vacuum system tripped on power interruption
|
Thursday, August 03, 2017, 17:00: Restarted TPs |
Thursday, August 17, 2017, 12:45, Anders Mjos, , , , , , , Problems/Solutions, TBHT power supply removed
|
The Xantrex 10V 600 A power supply for the TBHT has been moved to ITE to replace the failed TGHT power supply |
Monday, August 21, 2017, 16:20, Anders Mjos, , , , , , , Problems/Solutions, TBHT power supply removed
|
Anders Mjos wrote:
The Xantrex 10V 600 A power supply for the TBHT has been moved to ITE to replace the failed TGHT |
Monday, October 30, 2017, 08:54, Anders Mjos, , , , , , , Problems/Solutions, TMS:TP6 shut down due to high noise
|
The turbo pump will need replacement. |
Wednesday, November 15, 2017, 10:56, Aaron Schmidt, , , , , , , Problems/Solutions, TMS:TP6 replacement
|
Turbo pump TP6 requires replacement.
Wednesday, November 15, 2017, 09:55: Turbo (TP2) off. Ion gauge off.
Wednesday, November 15, 2017, 10:55: Venting |
Monday, December 04, 2017, 08:29, Aaron Schmidt, , , , , , , Problems/Solutions, Power outage
|
Power outage over the weekend. Reboot PLC and systems.
Monday, December 04, 2017, 08:22: Turbo pumps TMS:TP6 & TP2 Restarted.
Monday, December 04, 2017, 08:28: Time out on turbo pump TP1B. |
Tuesday, January 02, 2018, 09:18, Anders Mjos, , , , , , , Problems/Solutions, Starting system
|
Tuesday, January 02, 2018
Cycled power for TCSIOC and PLCIOC
TP2 and TP6 started |
Monday, February 05, 2018, 09:17, Aaron Schmidt, , , , , , , Problems/Solutions, Epics loss
|
Monday, February 05, 2018, 09:10: the epics program was in 'White-out'. Turbo pumps tripped.
Unplug, re-plug PLC.
Monday, February 05, 2018, 09:16: Restart Turbo pumps on chamber & beamline. |
Tuesday, March 20, 2018, 09:14, Aaron Schmidt, , , , , , , Problems/Solutions, Optics issue
|
Tuesday, March 20, 2018, 09:11: TMS:Q5 & TMS:Q2 controllers require repair. Unable to hold a negative voltage.
+ @ 680V
- @ 0V (Should be 680V as well) |
Tuesday, May 22, 2018, 08:48, Anders Mjos, , , , , , , Problems/Solutions, TSG:TP1A not running
|
Pump found off on Tuesday morning.
Tuesday, May 22, 2018, 08:40: Starting TP1A
Tuesday, May 22, 2018, 08:47: TP1A at speed |
Thursday, May 24, 2018, 08:38, Anders Mjos, , , , , , , Problems/Solutions, Venting beamline for IG6 replacement
|
Thursday, May 24, 2018, 08:38: TPs stopped
Thursday, May 24, 2018, 09:18: Venting
Thursday, May 24, 2018, 14:30: IG6 replaced (second attempt) by Anthony. System pumping down |
Thursday, May 24, 2018, 15:28, Anders Mjos, , , , , , , Problems/Solutions, Reconfigured FEBIAD coil for testing new source tray
|
Thursday, May 24, 2018: Configured coil to be (-) E&F, (+) G&H. Water should be supplied to both terminals in either configuration. |
|