61
|
Wednesday, October 24, 2012, 17:38 |
Isaac Earle | Repair | Target 2 | Target | T1 & T2 Target Ladder Control System Status | During the recent shutdown for the
T2/M9 joint repair Graham Waters replaced
the corrupted application code on the controller |
|
62
|
Tuesday, November 13, 2012, 16:26 |
Isaac Earle | Repair | Target 1 | Target | Manipulator Repair Complete | Repair of the west side manipulator
in the west hot cell was completed today.
Part of the repair was done by entering |
|
64
|
Monday, December 10, 2012, 15:42 |
Isaac Earle | Maintenance | Target 1 | Target | T1-MK2 Target Maintenance | - T1-MK2 target moved from storage pit
to hot cell
- Removed unused proximity sensor |
|
65
|
Tuesday, January 08, 2013, 09:27 |
Isaac Earle | Standard Operation | Target 2 | Target | BL1A Air Amplifier turned off for duration of shutdown. | The BL1A air amplifier
has been shut down by closing the air supply |
|
66
|
Tuesday, January 08, 2013, 10:52 |
Isaac Earle | Maintenance | Target 2 | Target | T2-MK1 Target Maintenance | - T2-MK1 target transported from storage
pit to hot cell
- Proximity sensor removed |
|
67
|
Friday, January 11, 2013, 15:48 |
Isaac Earle | Standard Operation | Target 1 | Target | BL1A Tunnel Accessed | The BL1A tunnel was accessed to drain
and sample T2 cooling package water. A
puddle of water was noticed in the South |
|
68
|
Monday, January 14, 2013, 16:55 |
Isaac Earle | Standard Operation | Target 2 | Target | Target Move & Damaged Profile Monitor | The T2-MK1 target (spare T2 target) was
transported from the hot cell to the storage
pit today. |
|
69
|
Monday, January 21, 2013, 11:57 |
Isaac Earle | Repair | Target 2 | Target | Flask Repair | On January 15th, when attempting
to move the T2 target from the beam line
to the hot cell, the latch mechanism on the |
|
70
|
Monday, January 21, 2013, 16:18 |
Isaac Earle | Standard Operation | Target 2 | Target | T2 Cooling Package Water Released | The T2 cooling package water was drained
to the BL1A active sump, refilled, cycled,
and drained again. Samples of T2 cooling |
|
72
|
Tuesday, February 05, 2013, 09:50 |
Isaac Earle | Maintenance | Target 2 | Target | T2-MK2 target moved from beam line to hot cell | The T2-MK2 target was transported from
the beam line to the RH hot cell. The
profile monitor was secured in the 'in' position |
|
74
|
Monday, March 18, 2013, 15:17 |
Isaac Earle | Maintenance | Target 2 | Target | T2-MK2 Target Maintenance and Re-Wiring | - T2-MK2 target moved from beamline to
hot cell (Feb 4th)
- Steel target support shield installed |
|
75
|
Tuesday, March 26, 2013, 10:55 |
Isaac Earle | Maintenance | Target 1 | Target | T1-MK1 Re-wiring and MRO Complete | The following work was performed
on the T1-MK1 target:
- Unused proximity sensor removed |
|
76
|
Tuesday, April 09, 2013, 17:06 |
Isaac Earle | Repair | Target 1 | Target | T1 Target Electronics Check | The T1-MK1 target protect and profile monitor
electronics were 'blip' tested by Bill Rawnsley
on April 5, 2013. The response from |
|
79
|
Wednesday, April 17, 2013, 16:43 |
Isaac Earle | Standard Operation | Target 2 | Target | T2 target installed; Vacuum leak-tight; Monitors OK; T2 ready for beam | The T2-MK2 target was transferred from
the storage pit to the beam line yesterday
(April 16th). The field was measured |
|
80
|
Wednesday, April 17, 2013, 16:45 |
Isaac Earle | Standard Operation | Target 1 | Target | T1-MK1 Target Leak Checked | The T1-MK1 target was leak checked
on April 15th at the T1 monolith by Ron Kuramoto
and Edi Dalla Valle. No leaks were |
|
82
|
Tuesday, May 14, 2013, 13:26 |
Isaac Earle | Development | Target 1 | Target | T1 & T2 Profile Scan | The T1 and T2 profile monitors were used
during today's development shift. Target
ladder movement for T1 was done at the panel |
|
83
|
Friday, May 31, 2013, 16:07 |
Isaac Earle | Repair | Target 1 | Target | Power Supply Fan Failure | Today (May 31, 2013) I was contacted
regarding a burning smell and high temperatures
around the T1/T2 controls racks. Erwin |
|
84
|
Tuesday, June 04, 2013, 13:42 |
Isaac Earle | Repair | Target 1 | Target | T1 and T2 Power Supply Fans Replaced | Replacement of the power supply fans
for the T1 Power Supply, T2 Power Supply,
as well as an additional power supply in |
|
91
|
Tuesday, November 12, 2013, 11:49 |
Isaac Earle | Repair | Target 1 | Target | MH Hot Cell Lab Manipulator Overhaul | Complete overhaul of all manipulators
in the Remote Handling Hot Cell Lab in the
Meson Hall was performed by Peter Dudley |
|
93
|
Saturday, November 23, 2013, 18:37 |
Isaac Earle | Repair | Target 2 | Target | T2-MK1 Installation | - T2-MK1 target transported from the storage
area by Isaac and Grant and installed at
the T2 monolith. All services were |
|