  ID Date Author Categorydown Type Specific Subject Text Attachments
  147   Thursday, April 09, 2015, 13:56 Isaac EarleDevelopmentTarget 2TargetT2-MK2 target wired for version identification, cable ties replaced, ready for useThe "POT/CAM" MS connector on
the T2-MK2 has been wired to allow automatic
target version number identification by the
  
  151   Wednesday, April 22, 2015, 09:46 Isaac EarleDevelopmentTarget 1TargetWater Sensors Installed on T1 Monolith Four water sensors have been installed
on top of the T1 monolith.  These water
sensors were wired and brought to the area
 T1_Water_Sensors.jpgIMG_4859.JPGIMG_4860.JPG 
  153   Wednesday, April 22, 2015, 15:17 Isaac EarleDevelopmentTarget 1TargetT1-MK2 wired for version identification The T1-MK2 target was wired for automatic
target version detection by the new PLC control
system (A to C jumper  in POT/CAM MS
  
  154   Thursday, April 23, 2015, 13:40 Isaac EarleDevelopmentTarget 2OtherT2 Protect Monitor Elevation Adjustment- T2 Protect Monitor moved from the beam
line to the hot cell on Monday April 20th
- Elevation of the plate center measured
 Old_T2_Protect_Monitor_(removed_Apr_22_2015)_-_Entry_Side.jpgOld_T2_Protect_Monitor_(removed_Apr_22_2015)_-_Exit_Side.jpg 
  157   Tuesday, April 28, 2015, 15:55 Isaac EarleDevelopmentTarget 1TargetTarget Version Jumper Wires Installed for T1-MK1 and T2-MK1 The T1-MK1 and T2-MK1 targets have
been re-wired to allow version identification.
 Work was performed in the target storage
  
  162   Thursday, June 11, 2015, 16:59 Isaac EarleDevelopmentOtherControlsLab Test of New T1/T2 Level SensorsThe new T1/T2 level sensors (Omega LVCN414)
were tested in the RH HC lab today using
the Omega software on a laptop and positioning
  
  163   Friday, June 19, 2015, 17:11 Isaac EarleDevelopmentOtherControlsPLC Test of Ultrasonic Level SensorThe new T1/T2 level sensors
(Omega LVCN414) were hooked up to the PLC
 Overnight_Level_Sensor_PLC_Test.jpg 
  165   Wednesday, July 08, 2015, 16:21 Isaac EarleDevelopmentTarget 1Target0.003" 347 SS Sheet for T1/T2 Targets Received A 5lb roll of 347SS sheet was received
today.  This alloy is to be used for
the target windows of the new T1 and T2 beryllium
 347SS_Mill_Spec_Test_Report_-_July_8_2015.pdf 
  166   Thursday, July 09, 2015, 13:51 Isaac EarleDevelopmentOtherTargetNew T1 and T2 Beryllium Targets OrderedAn order for new T1 and T2  beryllium
targets was submitted to the TRIUMF machine
shop today.  A total of seven T2 targets
  
  168   Friday, July 17, 2015, 10:14 Isaac EarleDevelopmentTarget 1TargetT1/T2 Be Target Failure History & Replacement PlanT1 and T2 beryllium target failure history
was investigated back to 2000 (as far as
XSTRIP records were readily available).  For
 T1_and_T2_Be_Target_History_-_July_17_2015.pdf 
  169   Thursday, August 13, 2015, 09:47 Isaac EarleDevelopmentOtherOther"Clamp A" disassembled and used to build clamp "TRH1257-#01"The 4" Marman flange clamp (IRH0001)
labeled "Clamp A",  as used
in the testing detailed in Document-114623
  
  184   Thursday, December 17, 2015, 13:31 Grant MinorDevelopmentOtherTargetT1/T2 Target Cassette - window / end cap manufacturing change (WO 41527)Isaac Earle has recently been managing
the fabrication of some new Be  target cassettes
for the T1 / T2 Meson Hall target ladders
 Left_new_right_old_ref_TBP1683_16Dec2015.JPGTBP1690_left_new_right_old_16Dec2015.JPGTBP1683_forming_tool_16Dec2015.JPGNew_Frame_Ref_TBP1696_16Dec2015.pdf 
  189   Monday, March 07, 2016, 18:22 Isaac EarleDevelopmentTarget 1ControlsPreliminary Testing of T1 Control System Complete Preliminary testing of the new PLC
control system and EPICS interface was completed
today for the T1 target, T1 cooling package,
 T1_Testing_Checklist_-_Complete_-_March_7_2016.pdf 
  190   Wednesday, March 16, 2016, 16:50 Isaac EarleDevelopmentTarget 2ControlsPreliminary Testing of T2 Control System CompletePreliminary testing of the new
PLC control system and EPICS interface was
 T2_Testing_Checklist_-_Complete_-_March_16_2016.pdf 
  192   Thursday, March 24, 2016, 15:38 Isaac EarleDevelopmentTarget 1TargetT1/T2 Beryllium Target Test Jig Fabrication CompleteFabrication of the T1/T2 beryllium target
testing jig (TBP1721) was completed today
by Dan MacDonald.  With a target installed
 IMG_6904.JPG 
  194   Thursday, April 07, 2016, 16:44 Isaac EarleDevelopmentOtherControlsT1/T2 Controls "Assembly Tests" CompletedThe T1/T2 Control System "Assembly
Tests"  (Document 118467 Release
#1, Section 5) have been completed.  The
  
  195   Monday, April 11, 2016, 13:51 Isaac EarleDevelopmentOtherOtherTarget Transfer Flask Hoist Hook Lower Limit Adjusted The lower limit of the flask hoist
hook has been adjusted.  The travelling
nut for the lower limit was rotated 3 notches
  
  202   Tuesday, June 21, 2016, 09:25 Isaac EarleDevelopmentOtherControlsT1/T2 EPICS System With-Beam Testing With-beam commissioning tests were
completed today by Tony Tateyama and Isaac
Earle.  The test results are attached
 T1T2_EPICS_Section_7_Commissioning_Results.pdf 
  206   Tuesday, August 30, 2016, 14:09 Isaac EarleDevelopmentOtherControlsT1/T2 PLC Code Update A new version of the T1/T2 PLC code
has been uploaded to the PLC CPU.  The
main change in the new version is a fix to
  
  207   Thursday, September 08, 2016, 17:26 Isaac EarleDevelopmentOtherActive SumpNew Active Sump High Level Switch and Electronics InstalledTo address the deficiencies identified
in E-Logs #204 and #205 the old active sump
high level switch was replaced with Omega
 IMG_7381.JPGIMG_7386.JPGRH_HC_Lab_Active_Sump_High_Level_Sensor_-_Electrical_Schematic.pdf 