ID Date Author Category Type Moduledown Target/Number Subject Text Attachments
  5   Tuesday, July 19, 2011, 11:17 Travis CaveSouth Hot-CellStandard OperationTM4Ta#35Move of TM#4 from East target station to south hot cell.Move went well no problems readings at
East Target Station were very high at 500mSv/hr.
  
  6   Tuesday, July 19, 2011, 11:52 chad fisherSouth Hot-CellStandard OperationTM4Ta#36New target Ta#36 Installed on TM4Ta#36 has been installed on TM4 and is
awaiting leak and electrical check.
A small piece of the standard top
 DSC_0897.JPGDSC_0899.JPGDSC_0901.JPGDSC_0905.JPG 
  7   Tuesday, July 19, 2011, 12:02 Travis CaveSouth Hot-CellStandard OperationTM4Ta#36Electrical checkSee attached PDF for the details.  TM#4_SIS_Elec_Check2.pdf 
  8   Tuesday, July 19, 2011, 12:25 maicodallavalleSouth Hot-CellStandard OperationTM4Ta36TM4 Ta36 Target was put into the south hot cell.Ta36 was check by Maico and Chad.It was
then carried into the anteroom.From the anteroom
it was transferred into the south hot cell.
  
  9   Tuesday, July 19, 2011, 13:51 chad fisherSouth Hot-CellStandard OperationTM4Ta#36TM4 Ta#36 Leak Check ResultsTm4 w/ Ta#36 has been vacuum leak checked
using the standard leak check procedure.
At 1:45pm RH was contacted to notify
 DOC.PDF 
  10   Wednesday, July 20, 2011, 09:55 Travis CaveITEStandard OperationTM4Ta#36Move of TM#4 from South Hot Cell to East Target Station.Move completed, move went well.   
  28   Wednesday, September 28, 2011, 09:07 Travis CaveITEStandard OperationTM4Ta#36Move of TM#4 from East target station to south hot cell.Move of TM#4 with Ta#36 from East target
station to south hot cell, move went well.
  
  29   Wednesday, September 28, 2011, 10:06 chad fisherSouth Hot-CellStandard OperationTM4Ta#36Ta#36 RemovalTa#36 was removed from target module 4.
The standard, unexplained, un-investegated,
un-resolved "arc" were again present
  
  30   Wednesday, September 28, 2011, 11:59 Travis CaveSouth Hot-CellStandard OperationTM4no targetTM#4 moved from South Hot Cell to to North East Silo.TM#4 moved from South Hot Cell to to North
East Silo, move went well.
  
  37   Tuesday, October 25, 2011, 08:47 Travis CaveSouth Hot-CellStandard OperationTM4SiC#26 High PoweredElectrical checkTM#4 with SiC#26 HP has been checked electrically
it has passed. It was noted that the Megger
check of the Oven to Chassis (earth ground)
  
  38   Tuesday, October 25, 2011, 11:58 Travis CaveSouth Hot-CellStandard OperationTM4SiC#26 High PoweredModule moveTM#4 with SiC#26 HP has been moved from
the south hot cell to the conditioning station.
  
  39   Tuesday, October 25, 2011, 16:57 Bevan MossConditioning StationStandard OperationTM4 Turbo Pump 1 issuesRoughing on TM1 started at ~15:00 today
by ~16:30 the module had reached a pressure
of ~200 mTorr and the turbo pumps were turned
  
  40   Friday, October 28, 2011, 08:24 Travis CaveConditioning StationStandard OperationTM4SiC#26 High PoweredModule moveTM#4 moved from conditioning station to
south hot cell. For further leak checking.
  
  41   Friday, October 28, 2011, 09:30 chad fisherSouth Hot-CellRepairTM4 Tube Heater + Leak Check C.B.Base Pressure: 0.0x10-4
Stable Leak Rate: 0.0x10-9
Leak check of tube heater circuit,
  
  42   Friday, October 28, 2011, 09:37 chad fisherSouth Hot-CellStandard OperationTM4SiC#26 HP FebiadSiC#26 installed on TM4HP febiad target SiC#26 was installed onto
Tm4 on Monday morning.
"JP's" connector required
  
  43   Friday, October 28, 2011, 14:29 Bevan MossConditioning StationStandard OperationTM4 Leak Check on October 27/10/2011A leak check was performed on the module
on October 27/10/2011 by David Wang and was
reported to Bevan Moss but it never made
  
  44   Friday, October 28, 2011, 14:42 Bevan MossSouth Hot-CellMaintenanceTM4 Leak check on service cap feed through After Chad and Davids leak check
results from the containment box it was decided
to perform a leak check on the feed through
 IMG_1906.JPGIMG_1905.JPGIMG_1908.JPG 
  45   Monday, October 31, 2011, 08:51 Travis CaveSouth Hot-CellStandard OperationTM4SiC#26 High PoweredModule moveTM#4 with SiC#26 HP moved from the south
hot cell to the conditioning station.
  
  46   Tuesday, November 01, 2011, 11:50 David WangConditioning StationStandard OperationTM4 TM4 leak test on conditioning station I did a leak check again on TM4 today.
This time, the leak detector pump to the
bottom on both base pressure(0.0xE-4 torr)
  
  47   Wednesday, November 02, 2011, 13:12 Bevan MossConditioning StationStandard OperationTM4SiC#26 High PoweredHigh Voltage (HV) testing The silicon carbide targets voltage
was raised to 42 kV today before continuous
current draw was observed. It took roughly
  