109
|
Tuesday, May 22, 2012, 10:00 |
David Wang | Conditioning Station | Standard Operation | TM4 | sic 27 | helium pressure test on heat shield circuit | I did a helium pressure test on heat shield
circuit. The leak detector is concected to
the TM4 primary vacuum system.The IG1 is |
|
111
|
Tuesday, May 22, 2012, 12:36 |
David Wang | ITE | Standard Operation | TM4 | sic 27 | TM4 connection in ITE | All TM4 connections in ITE is done. The
station and TM4 is under roughing now. |
|
112
|
Tuesday, May 22, 2012, 15:19 |
David Wang | ITE | Standard Operation | TM4 | sic 27 | TM4 in ITE under pumping |
Normal
0
|
|
2023
|
Tuesday, November 05, 2019, 12:46 |
chad fisher | South Hot-Cell | Standard Operation | TM2 | ta#59 | Ta#59 removed | Ta#59 has been removed from TM2 and it
is now ready for electrical check. |
|
1457
|
Wednesday, March 22, 2017, 14:05 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | test target | module moved | TM#2 has been moved from the east target
station to the south hot cell. |
|
1458
|
Thursday, March 23, 2017, 09:30 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | test target | Electrical Check | Electrical check of the Ta test target
on TM#2 |
|
139
|
Wednesday, July 04, 2012, 13:18 |
David Wang | Conditioning Station | Standard Operation | TM4 | uo#3 | leak check on heat shield circuit |
|
|