Friday, May 13, 2016, 10:12, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 water lines, heaters, EE, and EL are connected at TCS.
|
The HV cover is installed on to TM2 after the connections. The HV key is returned back to B2 level. The TCS Faraday cage is locked. |
Monday, May 16, 2016, 10:48, Anders Mjos, Conditioning Station, Maintenance, , , Topped up water in TCS:TK2
|
Filled from 15 to 25 in |
Monday, May 16, 2016, 11:16, David Wang, ITW, Standard Operation, TM1, , ITW, TM1 turbo-pumps are swithched off
|
I let isac opp switched off ITW turbo-pumps. The argon vent valve in electrical room is opened. The ITW argon venting will be started soon. |
Tuesday, May 24, 2016, 10:42, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall schedule for beam schedule 130 (Apr- Sep)
|
Weekly update the TH schedules. See attachments 1, 2,3. |
Thursday, June 02, 2016, 11:59, David Wang, South Hot-Cell, Repair, TM3, , 5K mega test on TM3
|
I did a 5KV mega test on TM3. Only5Mohm @5kV between coli line PQ and chassis(ground). It confirmed the close gap between P,Q and GE. Other lines
are ok. See attachment. |
Thursday, June 02, 2016, 18:04, Aurelia Laxdal, South Hot-Cell, Repair, TM3, , 5K mega test on TM3
|
David Wang wrote:
I did a 5KV mega test on TM3. Only5Mohm @5kV between coli line PQ and chassis(ground). It confirmed |
Friday, June 03, 2016, 16:04, Aurelia Laxdal, South Hot-Cell, Repair, TM3, , 5K mega test on TM3
|
Aurelia Laxdal wrote:
|
Thursday, June 09, 2016, 10:04, David Wang, Conditioning Station, Standard Operation, , , Target Hall schedule for beam schedule 130 (Apr- Sep)
|
Weekly update . |
Tuesday, June 14, 2016, 11:20, David Wang, ITE, Standard Operation, TM4, , TM4 has been connected in ITE
|
TM4 and ITE are under roughing now. |
Tuesday, June 21, 2016, 13:47, Travis Cave/ Dan McDonald, Spent Target Vault, Repair, , , Spent Target Vault Door
|
The spent target vault door does not open or close. The emergency door closing did have to be used to close the door as it was locked in an open position,
the door stopped just off the open override limit. The door was closed and the spent target that was being assayed was placed into the mini storage. The
problem with the door appears to be related to the motor itself, as all the controls to the motor appear to be in working order. Also it was noticed on |
Monday, June 27, 2016, 13:45, David Wang, ITE, Standard Operation, , , 5 Shielding blocks have been transferred from ITW to ITE.
|
ITE is configured to take proton beam. |
Thursday, June 30, 2016, 13:33, Dan McDonald, Spent Target Vault, Maintenance, , , F308's
|
The five spent target F308 flasks where gone through in accordance with Nordion guidelines, the sixth spare is remains in the Hot Cell area. All
flasks where in reasonable shape with two needing weld repairs on the pallets. I replaced all the 3/4" pallet to flask fasteners with new Grade 8
bolts nut and washer combo. Flasks have been moved into the Hot Cell area awaiting movement into the Target Hall. |
Wednesday, July 06, 2016, 07:03, David Wang, ITW, Standard Operation, TM2, , TM2 was connected in ITW.
|
TM2 was disconnected in ITW and moved to SHC. |
Wednesday, July 06, 2016, 07:06, David Wang, Conditioning Station, Standard Operation, , , venting TCS with argon.
|
I switched off the vacuum pumps and vented TCS with argon. The TCS will be ready to accept TM2 this afternoon. |
Wednesday, July 06, 2016, 14:25, David Wang, Conditioning Station, Standard Operation, TM2, , TCS and TM2 turbo-pumps have been started.
|
The TCS and TM2 are pumping down. |
Friday, July 08, 2016, 08:20, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 has been connected at TCS
|
I connected TM2 to TCS and started water system. |
Friday, July 08, 2016, 16:56, Anders Mjos, Conditioning Station, Repair, , , VFD21 OL1 fault on Chiller
|
Plant Services group (Tony) will contact a service tech on Monday.
Water system will be switched off over the weekend. |
Tuesday, July 12, 2016, 12:40, David Wang, ITW, Standard Operation, TM2, , TM2 has been connected in ITW
|
All turbo-pumps are started. Everything is good so far. |
Tuesday, July 12, 2016, 12:42, David Wang, Conditioning Station, Standard Operation, , , Target Hall schedule for beam schedule 130 (Apr- Sep)
|
Update schedule weekly.Attachment 1,2 |
Thursday, July 14, 2016, 10:54, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall schedule for beam schedule 130 (Apr- Oct, 2016)
|
Update TH schedule 130 according to mini-shut down change.See attachment 1,2,3,4 |
|