  RH-ISAC, Page 96 of 140  Not logged in ELOG logo
ID Date Author Category Type Module Target/Numberdown Subject Text Attachments
  1118   Friday, November 06, 2015, 14:44 Anders MjosConditioning StationRepairTM3 O-rings replaced on service capO-rings were replaced on the service cap
by Anders, Maico, Aurelia and Keith under
work permit  I2015-11-05-5
  
  1120   Tuesday, November 10, 2015, 10:23 Anders MjosConditioning StationMaintenanceTM3 Air to vacuum leak on service capConducted a more thorough leak check this
morning with Edi. He found a leak on the
base of the  blue F/T insulator for
 TM3_Service_Cap_Leak.pdf 
  1122   Thursday, November 12, 2015, 10:18 Anders MjosConditioning StationMaintenanceTM3 Air to vacuum leak on service cap

    

       
            
  
  1124   Monday, November 16, 2015, 08:04 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015Update TH schedule according to changes.
See attachment 1,2 .
update TH schedule weekly. See attachments
 Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp 
  1127   Monday, November 16, 2015, 10:37 David WangConditioning StationRepairTM3 TM3 has been disconnected at TCS.I stopped the TM3 and TCS vacuum pumps
and water system. The TM3 is disconnected
and vented. It will be moved to silo this
  
  1129   Tuesday, November 24, 2015, 13:54 chad fisherSouth Hot-CellRepair  Cell DeconDecon/removal of large solid waste was
performed on Wednesday November 18th."Hot"
activated items included containment box
  
  1130   Tuesday, November 24, 2015, 14:00 chad fisherSouth Hot-CellRepair  Compressible waste sorting.Residual fields from the remaining compressible
waste were still too high (as far as I'm
concerned) so I have unpacked all compressible
 20151124_101547.jpg 
  1131   Tuesday, November 24, 2015, 14:02 chad fisherSouth Hot-CellRepair  Left Manip repairelectronics package on left manip died
completely yesterday (it has been going for
a while).
  
  1132   Tuesday, November 24, 2015, 14:03 chad fisherSouth Hot-CellStandard OperationTM4 Ta#46Ta#46 has been removed from TM4.   
  1136   Wednesday, November 25, 2015, 14:16 chad fisherSouth Hot-CellRepair  Cell DeconCell (table) was systematically cleaned
with a swiffer and resulting piles of contaminated
waste placed in pail with spent Ta target.
 20151125_100512.jpg20151125_101620.jpg 
  1142   Monday, November 30, 2015, 11:46 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015Weekly update TH schedule according to
changes. see attachment 1,2 .
Update TH schedule before the weekend.
 Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp 
  1147   Wednesday, December 02, 2015, 10:41 chad fisherSouth Hot-CellRepair  Drum Clean-up #2Another drum of waste was removed from
the south hot cell this morning. This drum
contained one 5 gal steel pail (damaged),
  
  1148   Thursday, December 10, 2015, 13:17 Anders MjosConditioning StationStandard Operation  Blank off flangeThursday, December 10, 2015, 13:17: Roughing
Thursday, December 10, 2015, 14:56:
Started TP1S
 TCS_Blank_Off.png 
  1149   Friday, December 18, 2015, 11:42 Anders MjosConditioning StationRepair  Vacuum gauges not reading correctly It was found that the conversion
from voltage to vacuum (Torr) in EPICS is
not correct for the XGS-600 controllers in
  
  1150   Monday, December 21, 2015, 13:27 Anders MjosConditioning StationRepair  Vacuum gauges not reading correctly

    

       
            
  
  1151   Friday, January 08, 2016, 09:29 chad fisherSouth Hot-CellRepair  Window DeconEntered the hot cell to perform final decon
on the window. Initial swipes this morning
were 11000 c.p.m. on 44-2. After decon approximately
  
  1153   Friday, January 22, 2016, 14:24 David WangSouth Hot-CellStandard Operation  2016 Winter Shut Down Target Hall Schedule (sketch)Post a sketch of 2016 winter shut down
target hall schedule. see attachment 1,2
 UPDATE THE SCHEDULE ACCORDING
 2016_winter_shut_down__target_hall_schedule.pdf2016_winter_shut_down__target_hall_schedule.mpp2016_winter_shut_down__target_hall_schedule.pdf2016_winter_shut_down__target_hall_schedule.mpp 
  1154   Friday, February 12, 2016, 13:00 David WangConditioning StationStandard Operation  2016 Winter Shut Down Target Hall Schedule 2016 Winter shut down target hall schedule.
See attachments1,2.
 update the schedule weekly.
 6x 
  1155   Friday, February 19, 2016, 06:58 maicodallavalleSpent Target VaultMaintenance  F-308's serviced/loaded/ bolts torquedFive F-308's were loaded with spent ISAC
targets. All five F-308's were serviced two
weeks ago. All bolts were torqued and security 
  
  1156   Thursday, February 25, 2016, 06:48 David WangITEStandard Operation  4 Shielding blocks have been transferred from ITE to block storage area.Dan and I transferred 4 shielding blocks
from ITE to block storage area. The ITE pit
is opened now.
  