Entry  Friday, November 06, 2015, 14:44, Anders Mjos, Conditioning Station, Repair, TM3, , O-rings replaced on service cap 
O-rings were replaced on the service cap by Anders, Maico, Aurelia and Keith under work permit  I2015-11-05-5
   

 
Entry  Tuesday, November 10, 2015, 10:23, Anders Mjos, Conditioning Station, Maintenance, TM3, , Air to vacuum leak on service cap TM3_Service_Cap_Leak.pdf
Conducted a more thorough leak check this morning with Edi. He found a leak on the base of the  blue F/T insulator for the multi-pin connector (see
attachment). I discovered that all the bolts could rotate freely in the threads as they were too small. The bolts were replaced. The leak rate was reduced
but still significant. The o-ring will likely need to be replaced.
    Reply  Thursday, November 12, 2015, 10:18, Anders Mjos, Conditioning Station, Maintenance, TM3, , Air to vacuum leak on service cap 


    
        
            Anders Mjos wrote:
        
        
            
            Conducted a more thorough leak check this morning with Edi. He found a leak on the base of the  blue
Entry  Monday, November 16, 2015, 08:04, David Wang, Conditioning Station, Standard Operation, , , Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
Update TH schedule according to changes. See attachment 1,2 .
update TH schedule weekly. See attachments 3,4
Entry  Monday, November 16, 2015, 10:37, David Wang, Conditioning Station, Repair, TM3, , TM3 has been disconnected at TCS. 
I stopped the TM3 and TCS vacuum pumps and water system. The TM3 is disconnected and vented. It will be moved to silo this afternoon.
Entry  Tuesday, November 24, 2015, 13:54, chad fisher, South Hot-Cell, Repair, , , Cell Decon 
Decon/removal of large solid waste was performed on Wednesday November 18th."Hot" activated items included containment box cover from TM2,
Febiad coil line remnants from TM4 (the hottest ends were previously cut off and disposed of), some target conductor bolts, steerer plugs from TM2, target
material remn.
Entry  Tuesday, November 24, 2015, 14:00, chad fisher, South Hot-Cell, Repair, , , Compressible waste sorting. 20151124_101547.jpg
Residual fields from the remaining compressible waste were still too high (as far as I'm concerned) so I have unpacked all compressible waste looking
for a "hot" item that has snuck into these items.
I have a hand full of small bolts (possible target components), a hand full of target material/dust (including an entire target disc), and some
Entry  Tuesday, November 24, 2015, 14:02, chad fisher, South Hot-Cell, Repair, , , Left Manip repair 
electronics package on left manip died completely yesterday (it has been going for a while).
Disconnected entire package and replaced with package from "spare" manipulator.
everything is back up and working.
Entry  Tuesday, November 24, 2015, 14:03, chad fisher, South Hot-Cell, Standard Operation, TM4, , Ta#46 
Ta#46 has been removed from TM4.
Entry  Wednesday, November 25, 2015, 14:16, chad fisher, South Hot-Cell, Repair, , , Cell Decon 20151125_100512.jpg20151125_101620.jpg
Cell (table) was systematically cleaned with a swiffer and resulting piles of contaminated waste placed in pail with spent Ta target.
Entry  Monday, November 30, 2015, 11:46, David Wang, Conditioning Station, Standard Operation, , , Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
Weekly update TH schedule according to changes. see attachment 1,2 .
Update TH schedule before the weekend. see attachment 3,4
Entry  Wednesday, December 02, 2015, 10:41, chad fisher, South Hot-Cell, Repair, , , Drum Clean-up #2 
Another drum of waste was removed from the south hot cell this morning. This drum contained one 5 gal steel pail (damaged), two sodium light bulbs, airlines,
and tank suits. Upon removal the drum was/is 1.5 mSv/h on contact. there was 200 counts of contamination found on the lid...easily removed. It will be
moved to the north hot cell at 11am.
Entry  Thursday, December 10, 2015, 13:17, Anders Mjos, Conditioning Station, Standard Operation, , , Blank off flange TCS_Blank_Off.png
Thursday, December 10, 2015, 13:17: Roughing
Thursday, December 10, 2015, 14:56: Started TP1S
Thursday, December 10, 2015, 15:59: Bypass applied on IG2
Entry  Friday, December 18, 2015, 11:42, Anders Mjos, Conditioning Station, Repair, , , Vacuum gauges not reading correctly 
 It was found that the conversion from voltage to vacuum (Torr) in EPICS is not correct for the XGS-600 controllers in use at the TCS. EPICS did
not correspond to local values displayed on the controller. An e-fault has been submitted.
    Reply  Monday, December 21, 2015, 13:27, Anders Mjos, Conditioning Station, Repair, , , Vacuum gauges not reading correctly 


    
        
            Anders Mjos wrote:
        
        
            
             It was found that the conversion from voltage to vacuum (Torr) in EPICS is not correct for the
Entry  Friday, January 08, 2016, 09:29, chad fisher, South Hot-Cell, Repair, , , Window Decon 
Entered the hot cell to perform final decon on the window. Initial swipes this morning were 11000 c.p.m. on 44-2. After decon approximately 100 counts.
Entry  Friday, January 22, 2016, 14:24, David Wang, South Hot-Cell, Standard Operation, , , 2016 Winter Shut Down Target Hall Schedule (sketch) 2016_winter_shut_down__target_hall_schedule.pdf2016_winter_shut_down__target_hall_schedule.mpp2016_winter_shut_down__target_hall_schedule.pdf2016_winter_shut_down__target_hall_schedule.mpp
Post a sketch of 2016 winter shut down target hall schedule. see attachment 1,2
 UPDATE THE SCHEDULE ACCORDING TO CYCLOTRON SIDE JOB. SEE ATTACHMENTS 3,4
Entry  Friday, February 12, 2016, 13:00, David Wang, Conditioning Station, Standard Operation, , , 2016 Winter Shut Down Target Hall Schedule  6x
2016 Winter shut down target hall schedule. See attachments1,2.
 update the schedule weekly. Everything is on time so far. see attachment 3,4.
Update the schedule according to beam new beam schedule and target process. see attachment 5,6
Entry  Friday, February 19, 2016, 06:58, maicodallavalle, Spent Target Vault, Maintenance, , , F-308's serviced/loaded/ bolts torqued 
Five F-308's were loaded with spent ISAC targets. All five F-308's were serviced two weeks ago. All bolts were torqued and security  cables were
installed  for shipment.
Entry  Thursday, February 25, 2016, 06:48, David Wang, ITE, Standard Operation, , , 4 Shielding blocks have been transferred from ITE to block storage area. 
Dan and I transferred 4 shielding blocks from ITE to block storage area. The ITE pit is opened now.