786
|
Thursday, November 13, 2014, 14:01 |
David Wang | ITW | Repair | TM1 | | I replaced flow wheel and coil on ITW MSP water flow sensor. | I replaced flow wheel and coil on ITW MSP
water flow sensor which is located in ITW
pit. Before replacement, I checked the signal |
|
856
|
Monday, March 09, 2015, 14:01 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | ThO#1 | ThO#1 removed | ThO#1 has been removed from TM1 and placed
into the plastic dissection box.
Containment box cover has been reinstalled |
|
857
|
Tuesday, March 10, 2015, 09:01 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | ThO#1 | Module move | TM#1 has been moved from the west station
to the south hot cell had the ThO#1 target
removed and then the modules was moved from |
|
860
|
Thursday, March 12, 2015, 13:33 |
Anders Mjos | South Hot-Cell | Standard Operation | TM1 | ThO#1 | Target inspection | Chad, Anders and Alex inspected the target
this morning. The target had no significant
visible damage to the container. Some material |
|
887
|
Friday, April 17, 2015, 09:09 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | No target | Module move | TM#1 with no target has been moved from
the south west silo to the south hot cell
for the installation of the UCx target. |
|
888
|
Friday, April 17, 2015, 11:56 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | UC#12 | Electrical check | Electrical check of TM#1 with UCx#12 attached.
See attached PDF for details. |
|
889
|
Friday, April 17, 2015, 14:04 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | UC#12 | Module move | TM#1 with UCx#12 has been moved from the
south hot cell to the conditioning station. |
|
891
|
Monday, April 20, 2015, 10:12 |
Anders Mjos | Conditioning Station | Standard Operation | TM1 | UC#12 | Conditioning UC#12 | Monday, April 20, 2015, 09:35: Started
cooling water circulation
HV cover did not fit due to interference |
|
892
|
Monday, April 20, 2015, 10:22 |
David Wang | Conditioning Station | Standard Operation | TM1 | UCx12 | TM1 with UCx12 has been connected to CS and ready for conditioing. | The TH will be locked during the TM1 conditioning
time due to an interference issue between
CS HV cover and a gas analysis valve on top |
|
894
|
Tuesday, April 21, 2015, 17:14 |
Isaac Earle | South Hot-Cell | Standard Operation | TM1 | UC#12 | UC#12 Installed in TM1 | On Friday April 17th, UC#12 target was
installed in TM1. One of the copper
water lines was bent slightly as the target |
 |
895
|
Wednesday, April 22, 2015, 11:05 |
David Wang | Conditioning Station | Standard Operation | TM1 | | electrical check on TM1 at CS under vacuum | I did an electrical check on TM1 at CS.
The resistance check:A-B 3.918m ohm, A-C
5.905m ohm,A-D 4.070m ohm,B-C5.462m ohm,B-D3.633m |
|
896
|
Thursday, April 23, 2015, 09:08 |
David Wang | Conditioning Station | Maintenance | TM1 | UCx12 | Huge Leak on TM1 contaiment box window. | There is a huge leak on TM1 containment
box window. I did a 70 psi helium pressure
test on all TM1 water circuits this morning. |
    |
897
|
Thursday, April 23, 2015, 12:56 |
Anders Mjos | Conditioning Station | Maintenance | TM1 | | IG1 Good Vacuum limit changed | Changed by Dave Morris.
New value is 1E-5 T (old value was
7.09E-5 T) |
|
898
|
Monday, April 27, 2015, 10:28 |
David Wang | Conditioning Station | Standard Operation | TM1 | UCx12 | TM4 has been partially disconnected at CS. | TM1 has been partially disconnected at
CS for tomorrow move. The CS TP1S is still
running and will be stopped and disconnected |
|
901
|
Tuesday, April 28, 2015, 10:21 |
David Wang | Conditioning Station | Standard Operation | TM1 | UCx12 | CS and TM1 was vented with Argon gas | Dan and I vented CS and TM1 with Argon
gas before it is moved this morning. |
|
902
|
Tuesday, April 28, 2015, 10:26 |
David Wang | ITW | Standard Operation | TM1 | UCx12 | ITW target pit o-ring seal replacement. | Dan and I replaced ITW target pit o-ring
seal(.275DIA X42"ID). It is an annual
job before first beam to ITW. The old o-ring |
|
904
|
Tuesday, April 28, 2015, 11:14 |
Travis Cave | ITW | Standard Operation | TM1 | UC#12 | Module move | TM#1 with UC#12 has been moved from the
conditioning station to the west target station. |
|
905
|
Tuesday, April 28, 2015, 17:17 |
David Wang | ITW | Standard Operation | TM1 | UCx12 | TM1 has been connected in ITW. | TM1 has been connected in ITW. Five turbo
pumps have been started. The TM1 containment
box window line is capped on the service |
|
916
|
Friday, May 22, 2015, 15:44 |
David Wang | ITW | Standard Operation | TM1 | UCx12 | 5 Shielding blocks have been transferred from ITE to ITW. | 5 shielding blocks have been transferred
from ITE to ITW. I checked all ITW
water signals, and they are good. ITW |
|
940
|
Wednesday, June 10, 2015, 13:17 |
David Wang | ITE | Standard Operation | TM1 | | Target Hall Scheduled Activities April 07 - July 26 2015 | Weekly update the schedule after some jobs
have been finished in this week. |
 |