380
|
Tuesday, June 18, 2013, 14:00 |
chad fisher | South Hot-Cell | Development | TM3 | | Mock-up testing / water block connections | The testing of the mock-up and tooling
has commenced.
Source tray mock-up has been driven |
|
334
|
Thursday, May 09, 2013, 10:13 |
chad fisher | South Hot-Cell | Development | | | Mock-up Progress | The source tray for the mock-up has been
setup for waterline bending and soldering/brazing.
Thanks to Travis for finding the |
|
383
|
Friday, June 21, 2013, 09:26 |
chad fisher | South Hot-Cell | Development | TM3 | | Mock-up Leak Check Results | The Mock-up has been leak tested after
the remote connection of the water blocks
and is leak tight! |
|
381
|
Wednesday, June 19, 2013, 08:15 |
chad fisher | South Hot-Cell | Development | TM3 | | Mock up water block connections | All water block connections on the mock-up
have bben achieved. It is now ready for leak
checking. |
|
2250
|
Thursday, September 23, 2021, 19:04 |
Adam Newsome | Spent Target Vault | Development | | | Mini-Storage: Remote Capability | Remote capability was added for the mini-storage
door control. The control signals originate
from the Opto 22 Module box that is used |
|
2241
|
Wednesday, August 11, 2021, 11:15 |
Adam Newsome | Spent Target Vault | Development | | | Mini-Storage: Cable track for e-chain installed | A cable track was installed between the
mini-storage vault and the silos, for the
purpose of implementing a retractable cable |
|
1528
|
Monday, May 08, 2017, 14:46 |
Travis Cave | Spent Target Vault | Maintenance | | | Mini Vault Door | Mini Vault Door as some difficulty
over coming a small hump on its track. To
open the door one needs to give the door |
|
2469
|
Friday, July 28, 2023, 10:21 |
Adam Newsome | Spent Target Vault | Maintenance | | | Mini Storage Vault: Bearing Lubrication | The bearings on the mini storage vault
were lubricated. It is suspected that this
has never been done. It is suggested that |
|
2470
|
Tuesday, August 01, 2023, 09:06 |
Adam Newsome | Crane | Development | | | Measuring Tape and Camera Removed from Target Hall Crane | In an effort to clean up the camera installation
on top of the ISAC target hall crane to resolve
a fault, the position measuring tape and |
|
942
|
Thursday, June 11, 2015, 13:11 |
chad fisher | Assembly/Bench Test | Repair | TM2 | | Measurements beyween ground Plane and HV TM2 Source tary | I've taken measurements between HV and
ground circuit on TM2 source tray as instructed.
At their closest points: |
|
354
|
Tuesday, May 21, 2013, 11:52 |
Bevan Moss | Conditioning Station | Standard Operation | TM3 | No Source Tray | May 16th Long HV conditioning | On May 16th 2013 the module was HV conditioned
all day. As a result the maximum stable voltage
has been increased to about 47kV (~4kV more |
|
2506
|
Monday, November 27, 2023, 12:01 |
chad fisher | South Hot-Cell | Maintenance | | | Manipulator tong cable and wrist replacement | Broken tong cable on SW manipulator (serial
#8106) of SHC was replaced today.
Following ISAC Hot Cell entry procedure, |
|
771
|
Tuesday, October 21, 2014, 08:55 |
chad fisher | South Hot-Cell | Repair | | | Manipulator repair | The east manipulator handle has been adjusted
and is ready for use. |
|
1907
|
Wednesday, April 17, 2019, 12:03 |
chad fisher | South Hot-Cell | Repair | | | Manipulator repair | Broken handle cable of east manipulator
has been replaced and manipulator is operational
again. |
|
1324
|
Thursday, August 18, 2016, 13:57 |
chad fisher | South Hot-Cell | Maintenance | | | Manipulator maitenance | South hot cell was entered to check to
replace cable if needed. Wrist cable showed
no signs of fraying or broken strands. |
|
1110
|
Wednesday, October 21, 2015, 09:49 |
chad fisher | South Hot-Cell | Repair | | | Manipulator handle repair | Rebuild handle of manipulator serial 7986
(currently in the east position) and replaced
broken snap ring 5555-18h on west side of |
|
1744
|
Friday, June 29, 2018, 10:12 |
chad fisher | South Hot-Cell | Maintenance | | | Manipulator Tong Cable Replacement | Tuesday, June 26 the broken tong cable
was replaced on the west manipulator in the
south hot cell. Wednesday the tong cable |
|
1377
|
Monday, October 24, 2016, 10:10 |
chad fisher | South Hot-Cell | Repair | | | Manipulator Repair Complete | Maico entered the hot cell and re-strung
the skipped cable back onto the pulleys this
morning. Manipulator is now operational. |
|
351
|
Friday, May 17, 2013, 10:04 |
chad fisher | South Hot-Cell | Repair | | | Manipulator Repair | Manipulator has been sucessfully repaired.
Recieved 0.19 mSv. Took Approx. 10-20 minutes |
|
770
|
Monday, October 20, 2014, 14:18 |
chad fisher | South Hot-Cell | Repair | | | Manipulator Repair | The broken cable on the east manipulator
has been replaced.
The handle will need some adjustments |
|