ID Date Author Category Type Moduledown Target/Number Subject Text Attachments
  786   Thursday, November 13, 2014, 14:01 David WangITWRepairTM1 I replaced flow wheel and coil on ITW MSP water flow sensor.I replaced flow wheel and coil on ITW MSP
water flow sensor which is located in ITW
pit. Before replacement, I checked the signal
  
  856   Monday, March 09, 2015, 14:01 chad fisherSouth Hot-CellStandard OperationTM1ThO#1ThO#1 removedThO#1 has been removed from TM1 and placed
into the plastic dissection box.
Containment box cover has been reinstalled
  
  857   Tuesday, March 10, 2015, 09:01 Travis CaveSouth Hot-CellStandard OperationTM1ThO#1Module moveTM#1 has been moved from the west station
to the south hot cell had the ThO#1 target
removed and then the modules was moved from
 TM1_THO_elec_chk_postbeamSHC.PDF 
  860   Thursday, March 12, 2015, 13:33 Anders MjosSouth Hot-CellStandard OperationTM1ThO#1Target inspectionChad, Anders and Alex inspected the target
this morning. The target had no significant
visible damage to the container. Some material
  
  887   Friday, April 17, 2015, 09:09 Travis CaveSouth Hot-CellStandard OperationTM1No targetModule moveTM#1 with no target has been moved from
the south west silo to the south hot cell
for the installation of the UCx target.
  
  888   Friday, April 17, 2015, 11:56 Travis CaveSouth Hot-CellStandard OperationTM1UC#12Electrical checkElectrical check of TM#1 with UCx#12 attached.
See attached PDF for details.
 TM1_UC#12_tgt_elec_chk_SHC.PDF 
  889   Friday, April 17, 2015, 14:04 Travis CaveSouth Hot-CellStandard OperationTM1UC#12Module moveTM#1 with UCx#12 has been moved from the
south hot cell to the conditioning station.
  
  891   Monday, April 20, 2015, 10:12 Anders MjosConditioning StationStandard OperationTM1UC#12Conditioning UC#12Monday, April 20, 2015, 09:35: Started
cooling water circulation
HV cover did not fit due to interference
  
  892   Monday, April 20, 2015, 10:22 David WangConditioning StationStandard OperationTM1UCx12TM1 with UCx12 has been connected to CS and ready for conditioing.The TH will be locked during the TM1 conditioning
time due to  an interference issue between
CS HV cover and a gas analysis valve on top
  
  894   Tuesday, April 21, 2015, 17:14 Isaac EarleSouth Hot-CellStandard OperationTM1UC#12UC#12 Installed in TM1On Friday April 17th, UC#12 target was
installed in TM1.  One of the copper
water lines was bent slightly as the target
 IMG_4836.JPGIMG_4833.JPG 
  895   Wednesday, April 22, 2015, 11:05 David WangConditioning StationStandard OperationTM1 electrical check on TM1 at CS under vacuumI did an electrical check on TM1 at CS.
The resistance check:A-B 3.918m ohm, A-C
5.905m ohm,A-D 4.070m ohm,B-C5.462m ohm,B-D3.633m
  
  896   Thursday, April 23, 2015, 09:08 David WangConditioning StationMaintenanceTM1UCx12Huge Leak on TM1 contaiment box window.There is a huge leak on TM1 containment
box window. I did a 70 psi helium pressure
test on all TM1 water circuits this morning.
 006.JPG008.JPG011.JPG009.JPGTM1_leak_check_at_CS_2015-04-23.pdf 
  897   Thursday, April 23, 2015, 12:56 Anders MjosConditioning StationMaintenanceTM1 IG1 Good Vacuum limit changedChanged by Dave Morris. 
New value is 1E-5 T (old value was
7.09E-5 T)
 IG1GoodVacuum.png 
  898   Monday, April 27, 2015, 10:28 David WangConditioning StationStandard OperationTM1UCx12TM4 has been partially disconnected at CS.TM1 has been partially disconnected at
CS for tomorrow move. The CS TP1S is still
running and will be stopped and disconnected
  
  901   Tuesday, April 28, 2015, 10:21 David WangConditioning StationStandard OperationTM1UCx12CS and TM1 was vented with Argon gas Dan and I vented CS and TM1 with Argon
gas before it is moved this morning.
  
  902   Tuesday, April 28, 2015, 10:26 David WangITWStandard OperationTM1UCx12ITW target pit o-ring seal replacement.Dan and I replaced ITW target pit o-ring
seal(.275DIA X42"ID). It is an annual
job before first beam to ITW. The old o-ring
  
  904   Tuesday, April 28, 2015, 11:14 Travis CaveITWStandard OperationTM1UC#12Module moveTM#1 with UC#12 has been moved from the
conditioning station to the west target station.
  
  905   Tuesday, April 28, 2015, 17:17 David WangITWStandard OperationTM1UCx12TM1 has been connected in ITW.TM1 has been connected in ITW. Five turbo
pumps have  been started. The TM1 containment
box window line is capped on the service
  
  916   Friday, May 22, 2015, 15:44 David WangITWStandard OperationTM1UCx125 Shielding blocks have been transferred from ITE to ITW.5 shielding blocks have been transferred
from ITE to ITW. I  checked all ITW
water signals, and they are good.  ITW
  
  940   Wednesday, June 10, 2015, 13:17 David WangITEStandard OperationTM1 Target Hall Scheduled Activities April 07 - July 26 2015Weekly update the schedule after some jobs
have been finished in this week.
 Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp 