  896   Thursday, April 23, 2015, 09:08 David WangConditioning StationMaintenanceTM1UCx12Huge Leak on TM1 contaiment box window.

There is a huge leak on TM1 containment box window. I did a 70 psi helium pressure test on all TM1 water circuits this morning. The LD base leak rate was 0.0XE-9 atm.cc/sec. When applying the 70 psi helium to containment box window circuit, the leak rate on LD jumped to 1XE-4 atm.cc/sec in 5 seconds.I released the helium source right away,t but the conditioning station is full of helium  molecules already, and the leak rate on LD stays at 1xE-5 atm.cc /sec.  The leak on this circuit is huge.    Other water lines are good.        

Attachment 1: 006.JPG
006.JPG
Attachment 2: 008.JPG
008.JPG
Attachment 3: 011.JPG
011.JPG
Attachment 4: 009.JPG
009.JPG
Attachment 5: TM1_leak_check_at_CS_2015-04-23.pdf
TM1_leak_check_at_CS_2015-04-23.pdf
  897   Thursday, April 23, 2015, 12:56 Anders MjosConditioning StationMaintenanceTM1 IG1 Good Vacuum limit changed

Changed by Dave Morris. 

New value is 1E-5 T (old value was 7.09E-5 T)

Attachment 1: IG1GoodVacuum.png
IG1GoodVacuum.png
  898   Monday, April 27, 2015, 10:28 David WangConditioning StationStandard OperationTM1UCx12TM4 has been partially disconnected at CS.

TM1 has been partially disconnected at CS for tomorrow move. The CS TP1S is still running and will be stopped and disconnected tomorrow morning.

  901   Tuesday, April 28, 2015, 10:21 David WangConditioning StationStandard OperationTM1UCx12CS and TM1 was vented with Argon gas

Dan and I vented CS and TM1 with Argon gas before it is moved this morning.

  902   Tuesday, April 28, 2015, 10:26 David WangITWStandard OperationTM1UCx12ITW target pit o-ring seal replacement.

Dan and I replaced ITW target pit o-ring seal(.275DIA X42"ID). It is an annual job before first beam to ITW. The old o-ring was moved and the groove was vacuum cleaned. The new o-ring has been installed properly.

  904   Tuesday, April 28, 2015, 11:14 Travis CaveITWStandard OperationTM1UC#12Module move

TM#1 with UC#12 has been moved from the conditioning station to the west target station.

  905   Tuesday, April 28, 2015, 17:17 David WangITWStandard OperationTM1UCx12TM1 has been connected in ITW.

TM1 has been connected in ITW. Five turbo pumps have  been started. The TM1 containment box window line is capped on the service cap and the line is pump town to E-4 torr range.

  916   Friday, May 22, 2015, 15:44 David WangITWStandard OperationTM1UCx125 Shielding blocks have been transferred from ITE to ITW.

5 shielding blocks have been transferred from ITE to ITW. I  checked all ITW water signals, and they are good.  ITW is configured to take proton beam.

  940   Wednesday, June 10, 2015, 13:17 David WangITEStandard OperationTM1 Target Hall Scheduled Activities April 07 - July 26 2015

Weekly update the schedule after some jobs have been finished in this week.

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp
  953   Friday, June 19, 2015, 11:43 David WangITWRepairTM1 ITW external water leak on dump circuit

There was an external water leak in ITW during the last beam running time. The leak started after the shielding blocks transfer(May 22). It cause a constantly water level drop on S-tank(0.5 "/day average). Today , after the blocks are moved , the leak source has been found. Water seeped through a fitting on ITW dump circuit pressure gauge. The leak water slowly flow around the TM1 on the tank flange. most of them are dried out, but left some stain on dump module and tank flange. By closing the supply and return water valves on the ITW dump circuit, the leak is stopped now. We will fix this problem after the module is moved out and the radioactive field is low.  See attachments.

Attachment 1: 2015-06-19_ITW_dump_water_external_leak_001.JPG
2015-06-19_ITW_dump_water_external_leak_001.JPG
Attachment 2: 2015-06-19_ITW_dump_water_external_leak_002.JPG
2015-06-19_ITW_dump_water_external_leak_002.JPG
Attachment 3: 2015-06-19_ITW_dump_water_external_leak_003.JPG
2015-06-19_ITW_dump_water_external_leak_003.JPG
Attachment 4: 2015-06-19_ITW_dump_water_external_leak_004.JPG
2015-06-19_ITW_dump_water_external_leak_004.JPG
Attachment 5: 2015-06-19_ITW_dump_water_external_leak_006.JPG
2015-06-19_ITW_dump_water_external_leak_006.JPG
Attachment 6: 2015-06-19_ITW_dump_water_external_leak_005.JPG
2015-06-19_ITW_dump_water_external_leak_005.JPG
  969   Tuesday, June 30, 2015, 11:27 Travis CaveITWStandard OperationTM1UC#12Module moved

TM#1 with UC#12 has been moved from the west station to the south hot cell.

  970   Tuesday, June 30, 2015, 12:37 chad fisherSouth Hot-CellStandard OperationTM1UCx#12UCx #12 Removal

UCx#12 has been removed from TM1 and placed in a pail with argon.

Right leg (B) of target is clearly broken.

Containment Box cover re-installed and module ready to move.

  971   Tuesday, June 30, 2015, 15:41 David WangITWStandard OperationTM1 TM1 was disconnected in ITW this morning.

TM1 was disconnected in ITW  this morning. The ITW was vented with argon last night.

  974   Thursday, July 02, 2015, 11:49 Travis CaveSouth Hot-CellStandard OperationTM1no targetModule moved

TM#1 has been moved from the south hot cell to the south west silo.

  988   Thursday, July 09, 2015, 13:17 Anders MjosConditioning StationStandard OperationTM1 TM1 in TCS for alpha contamination test

 Thursday, July 09, 2015, 13:17: Water package started.

Thursday, July 09, 2015, 15:20: Water package stopped.


Friday, July 10, 2015, 14:15: Roughing with new pump

  990   Thursday, July 09, 2015, 14:02 David WangConditioning StationDevelopmentTM1 TM1 is pumping down at CS

TM1 and CS  vacuum system are connected. All turbo-pumps are started. The new TP1S works fine also. The pumping down looks good so far. During the TM1 and CS roughing down time, Joe .M noticed a Rn-220 level surge up in TH . Then,the Rn220  level slowly dropped back. Anders suspected this Rn-220 surging is related to the TM1 roughing down at CS. We decided we will stop the pumps , vent the CS , and roughing  again tomorrow. During the same time Joe will monitor  Rn-220 level in TH to see if the surging is repeatable. We want to learn more on this TH Rn-220 issue.

  992   Friday, July 10, 2015, 14:41 Anders MjosConditioning StationMaintenanceTM1 Replaced roughing pump

 The roughing pump was replaced with a more leak tight pump due to the discovery of Rn-220 migration while roughing on TM1 in TCS

  993   Monday, July 13, 2015, 11:31 Travis CaveConditioning StationStandard OperationTM1no targetModule moved

TM#1 has been moved back to the south west silo from the conditioning station.

  1064   Wednesday, September 09, 2015, 09:59 Travis CaveSouth Hot-CellStandard OperationTM1no targetModule moved

TM#1 has been moved from the south west silo to the south hot cell.

  1065   Thursday, September 10, 2015, 08:55 chad fisherSouth Hot-CellRepairTM1 TM1 Window Leak Diag.

Vacuum leak check on the window line circuit of TM1 took place yesterday and again to confirm this morning. Both days the response to helium is in the area of a soldered reduction fitting at the top of the containment box above and to the shutter side of the extraction column (see attached picture). To verify this morning each joint in the system had a 1 second shot of helium and then timed for 1 minute to wait for a response. This area responded both times tested at about 40 seconds...no response at any of the other locations.

Attachment 1: P0000122.JPG
P0000122.JPG