ID Date Author Category Type Module Target/Numberdown Subject Text Attachments
  1007   Tuesday, July 21, 2015, 12:38 David WangITWRepair  ITW external water leak on dump circuit has been fixed.The leaking 1/8 NPT(M)-1/4NPT(F) adapter
on the ITW dump circuit is replaced.
  
  1009   Wednesday, July 22, 2015, 12:13 chad fisherSouth Hot-CellRepairTM2 TM2 Short FindingsPin X was unplugged, short remained, however
any slight pressure on the block towards
the source tray makes the short go away.
 TM2_Short_July_22.jpg 
  1010   Thursday, July 23, 2015, 10:23 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 019 2015Update Target Hall schedule after the changing
on TM2 process. See attachment 1,2
 Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp 
  1011   Friday, July 24, 2015, 10:04 David WangITEStandard Operation  5 Shielding blocks have been moved from ITE to block storage area.Dan and I moved 5 shielding blocks from
ITE to block storage area. The move is smooth.
  
  1016   Monday, July 27, 2015, 15:34 David WangITEStandard OperationTM4 Leak check on TM4 HS water line with new UCX target. at SHCChad and I leak checked the HS line at
SHC after UCX target installation. On first
round helium spray, one of VCR fitting has
  
  1017   Monday, July 27, 2015, 15:46 David WangSouth Hot-CellStandard Operation  The yellow steel plug is put on SHC in THThe yellow steel plug is put on SHC in
TH. The spent target is inside the SHC.The
field around the SHC area in TH is so high
  
  1020   Tuesday, July 28, 2015, 10:17 David WangITERepair  ITE TP4 has been replacedTony and I replaced the ITE TP4 turbo pump
today. The pumping time on controller has
been reset to 0. The replaced broken 
  
  1026   Wednesday, July 29, 2015, 10:14 David WangITEStandard OperationTM4 TM4 has been connected in ITEDan and I connected TM4 in ITE. We checked
all water signals on ITE cooling circuits.
Everything is good.
  
  1028   Friday, July 31, 2015, 09:47 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 019 2015Weekly update of Target Hall schedule after
so many jobs have been finished in this week. 
See attachment 1, 2
 Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp 
  1029   Thursday, August 06, 2015, 10:26 Travis CaveSpent Target VaultStandard Operation  Spent Target Measurments and AssaysAll targets but one ( SiC#31 went in last
week) have been measured or assayed. See
attached PDF for the details.
 Vault_Storage_August_6_2015.pdf 
  1031   Friday, August 07, 2015, 10:01 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 19 2015Weekly update target hall schedule and
activities. See attachment 1,2
Update and extend Target Hall schedule
 Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf 
  1032   Monday, August 10, 2015, 14:07 Isaac EarleSouth Hot-CellRepairTM2 TM2 Containment Box RemovedThe containment box was taken off TM2 in
preparation for installation of a new coil
line isolator.
  
  1033   Thursday, August 13, 2015, 09:17 chad fisherSouth Hot-CellRepairTM2 TM2 statusTuesday, August 11,  insulator ITA6272
was installed onto the "pin x"
line (unused plasma electrode) and tested;
 20150811_132709.jpg20150813_083255.jpg20150813_090814.jpg 
  1035   Thursday, August 13, 2015, 13:46 chad fisherSouth Hot-CellRepairTM2 TM2 StatusAs previously mentioned, dump target installed
with new mounting and high current fasteners.
Leak Check complete and ready to
  
  1038   Friday, August 14, 2015, 10:00 David WangConditioning StationRepairTM2 Started CS water package for TM2 I finished the rest TM2 connections to
CS, and started CS cooling package. Everything
works fine so far.
  
  1040   Wednesday, August 19, 2015, 14:52 David WangConditioning StationRepairTM2 TM2 at CSDuring the TM2 HV test at CS, It failed.
In order to confirm there is no any water
leak inside the module after the heaters
  
  1041   Thursday, August 20, 2015, 09:38 David WangConditioning StationRepairTM2 TM2 was disconnected at CSTM2 was disconnected at CS. Travis and
I did  electrical check before the venting.
After,The module was vented and moved to
  
  1044   Thursday, August 20, 2015, 13:48 David WangConditioning StationStandard OperationTM2 Target Hall Scheduled Activities April 07 - Sep 08 2015 Weekly update target hall schedule.See
attachment 1,2
Spring and summer run is close to
 Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf 
  1048   Wednesday, August 26, 2015, 09:54 Anders MjosConditioning StationMaintenance  Topped up water in TCS:TK2 Filled to 24.9 in   
  1058   Tuesday, September 01, 2015, 10:38 David WangITWMaintenanceTM2 ITW top tank flange clean up and r-ring replacement.During last run, ITW dump circuit
had a water leak on an adaptor below the
pressure gauge. The top tank flange, slot,
 ITW_o-ring_replacement_2015-09-01_008.JPGITW_o-ring_replacement_2015-09-01_007.JPGITW_o-ring_replacement_2015-09-01_006.JPG 