ID Date Author Category Type Module Target/Numberdown Subject Text Attachments
  1031   Friday, August 07, 2015, 10:01 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 19 2015Weekly update target hall schedule and
activities. See attachment 1,2
Update and extend Target Hall schedule
 Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf 
  1032   Monday, August 10, 2015, 14:07 Isaac EarleSouth Hot-CellRepairTM2 TM2 Containment Box RemovedThe containment box was taken off TM2 in
preparation for installation of a new coil
line isolator.
  
  1033   Thursday, August 13, 2015, 09:17 chad fisherSouth Hot-CellRepairTM2 TM2 statusTuesday, August 11,  insulator ITA6272
was installed onto the "pin x"
line (unused plasma electrode) and tested;
 20150811_132709.jpg20150813_083255.jpg20150813_090814.jpg 
  1035   Thursday, August 13, 2015, 13:46 chad fisherSouth Hot-CellRepairTM2 TM2 StatusAs previously mentioned, dump target installed
with new mounting and high current fasteners.
Leak Check complete and ready to
  
  1038   Friday, August 14, 2015, 10:00 David WangConditioning StationRepairTM2 Started CS water package for TM2 I finished the rest TM2 connections to
CS, and started CS cooling package. Everything
works fine so far.
  
  1040   Wednesday, August 19, 2015, 14:52 David WangConditioning StationRepairTM2 TM2 at CSDuring the TM2 HV test at CS, It failed.
In order to confirm there is no any water
leak inside the module after the heaters
  
  1041   Thursday, August 20, 2015, 09:38 David WangConditioning StationRepairTM2 TM2 was disconnected at CSTM2 was disconnected at CS. Travis and
I did  electrical check before the venting.
After,The module was vented and moved to
  
  1044   Thursday, August 20, 2015, 13:48 David WangConditioning StationStandard OperationTM2 Target Hall Scheduled Activities April 07 - Sep 08 2015 Weekly update target hall schedule.See
attachment 1,2
Spring and summer run is close to
 Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf 
  1048   Wednesday, August 26, 2015, 09:54 Anders MjosConditioning StationMaintenance  Topped up water in TCS:TK2 Filled to 24.9 in   
  1058   Tuesday, September 01, 2015, 10:38 David WangITWMaintenanceTM2 ITW top tank flange clean up and r-ring replacement.During last run, ITW dump circuit
had a water leak on an adaptor below the
pressure gauge. The top tank flange, slot,
 ITW_o-ring_replacement_2015-09-01_008.JPGITW_o-ring_replacement_2015-09-01_007.JPGITW_o-ring_replacement_2015-09-01_006.JPG 
  1059   Tuesday, September 01, 2015, 14:54 David WangITWStandard OperationTM2 TM2 has been connectec in ITW.TM2 has been connected in ITW. During the
connection, Anders and I  found the
TM2  high current cables used in ITE
  
  1061   Tuesday, September 01, 2015, 16:55 Anders MjosConditioning StationMaintenance  TBHT power supply remvoed The power supply is needed as a spare
for the failed TGHT p/s in ITW
  
  1062   Wednesday, September 02, 2015, 09:26 David WangITEStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015I attach new Target Hall schedules here
for 2015 fall and winter runs (beam schedule
129). The TH excel sheet schedule for beam
 Target_Hall_shedule_129_Sep_to_Dec.xlsxTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp 
  1065   Thursday, September 10, 2015, 08:55 chad fisherSouth Hot-CellRepairTM1 TM1 Window Leak Diag.Vacuum leak check on the window line circuit
of TM1 took place yesterday and again to
confirm this morning. Both days the response
 P0000122.JPG 
  1066   Thursday, September 10, 2015, 08:59 chad fisherSouth Hot-CellRepair  Manipulator Mait. and field check Sept. 4Hot cell was entered for preventative mait.
on left manip. field measurements around
the cell were taken in prep. for window removal
  
  1069   Tuesday, September 15, 2015, 11:06 chad fisherSouth Hot-CellRepairTM1 TM1 Window Gasket ReplacementReplaced the custom silver gaskets on the
entrance window panel of TM1 this morning...this
has eliminated an sign of leak at this joint,
  
  1071   Thursday, September 17, 2015, 11:50 David WangSpent Target VaultRepairTM1 TM1 window circuit leak check Leak check TM1 window circuit soldering
stems inside service cap when module is located
at NE silo. LD base LR 0.0xE-9atm.cc/sec. 
 TM1_leak_soldering_stems_001.JPGTM1_leak_soldering_stems_003.JPG 
  1082   Friday, September 25, 2015, 07:56 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015weekly update see attachment  Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp 
  1089   Thursday, October 01, 2015, 09:18 Travis CaveSpent Target VaultStandard Operation  Targets transfered to mini storage.In preparation for shipping of the spent
targets five have been moved to the mini
storage. The following target were moved
  
  1090   Monday, October 05, 2015, 10:19 Anders MjosConditioning StationMaintenance  Chiller maintenance will be performed Tuesday October
6th
Tuesday, October 06, 2015: Maintenance
  