  1031   Friday, August 07, 2015, 10:01 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - August 19 2015

Weekly update target hall schedule and activities. See attachment 1,2

Update and extend Target Hall schedule to Sep 08.  See attachment 3,4

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mpp
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf
  1032   Monday, August 10, 2015, 14:07 Isaac EarleSouth Hot-CellRepairTM2 TM2 Containment Box Removed

The containment box was taken off TM2 in preparation for installation of a new coil line isolator.

ITA6272 and ITA6273 have been received from the Scintillator Shop.  ITA6274 should be ready by the end of today.

  1033   Thursday, August 13, 2015, 09:17 chad fisherSouth Hot-CellRepairTM2 TM2 status

Tuesday, August 11,  insulator ITA6272 was installed onto the "pin x" line (unused plasma electrode) and tested; it seems to have successfully eliminated the shorts on that line.

Wednesday, August 12  "shunts" installed on tube heater and oven circuit and electrically  tested.

Thursday , August 13, dummy target installed.

 

Attachment 1: 20150811_132709.jpg
20150811_132709.jpg
Attachment 2: 20150813_083255.jpg
20150813_083255.jpg
Attachment 3: 20150813_090814.jpg
20150813_090814.jpg
  1035   Thursday, August 13, 2015, 13:46 chad fisherSouth Hot-CellRepairTM2 TM2 Status

As previously mentioned, dump target installed with new mounting and high current fasteners.

Leak Check complete and ready to move to CS at 1:30

  1038   Friday, August 14, 2015, 10:00 David WangConditioning StationRepairTM2 Started CS water package for TM2

I finished the rest TM2 connections to CS, and started CS cooling package. Everything works fine so far.

  1040   Wednesday, August 19, 2015, 14:52 David WangConditioning StationRepairTM2 TM2 at CS

During the TM2 HV test at CS, It failed. In order to confirm there is no any water leak inside the module after the heaters and beam extraction test, I disconnected all the water lines on the TM2, and purged the water lines with pressure air. Leak detector was reconnected back to the TM2 service cap, and all water lines are pressurized with 80psi helium again each for 2 minutes.No any leak had been found during the test. All the water lines are still perfectly sealed. Also, I checked all the vacuum to air seals on the top of the module.They are good either.  Anders used the RGA  tracking the helium during the test. No leak.

  1041   Thursday, August 20, 2015, 09:38 David WangConditioning StationRepairTM2 TM2 was disconnected at CS

TM2 was disconnected at CS. Travis and I did  electrical check before the venting. After,The module was vented and moved to SHC. The moving is smooth.

  1044   Thursday, August 20, 2015, 13:48 David WangConditioning StationStandard OperationTM2 Target Hall Scheduled Activities April 07 - Sep 08 2015

 Weekly update target hall schedule.See attachment 1,2

Spring and summer run is close to the end. This will be the last update on this old schedule. See attachment3,4.    A new schedule for TH activities after mini shut down will be posted next time.

Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mpp
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf
Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf
  1048   Wednesday, August 26, 2015, 09:54 Anders MjosConditioning StationMaintenance  Topped up water in TCS:TK2

 Filled to 24.9 in

  1058   Tuesday, September 01, 2015, 10:38 David WangITWMaintenanceTM2 ITW top tank flange clean up and r-ring replacement.

During last run, ITW dump circuit had a water leak on an adaptor below the pressure gauge. The top tank flange, slot, and O-ring were water contaminated by the leak. I removed the old o- ring, cleaned up the flange and o-ring slot, and put a new o-ring into the flange. Some  pictures will be attached in this mail later.

Attachment 1: ITW_o-ring_replacement_2015-09-01_008.JPG
ITW_o-ring_replacement_2015-09-01_008.JPG
Attachment 2: ITW_o-ring_replacement_2015-09-01_007.JPG
ITW_o-ring_replacement_2015-09-01_007.JPG
Attachment 3: ITW_o-ring_replacement_2015-09-01_006.JPG
ITW_o-ring_replacement_2015-09-01_006.JPG
  1059   Tuesday, September 01, 2015, 14:54 David WangITWStandard OperationTM2 TM2 has been connectec in ITW.

TM2 has been connected in ITW. During the connection, Anders and I  found the TM2  high current cables used in ITE and CS are short in ITW.  Anders and Grant found the original TM2 ITE high current cables in target hall. We replaced them. They works fine. But, a little bit longer on cable length would be easy to connect them. All other connections and HV cover in ITW work for the TM2 so far.

  1061   Tuesday, September 01, 2015, 16:55 Anders MjosConditioning StationMaintenance  TBHT power supply remvoed

 The power supply is needed as a spare for the failed TGHT p/s in ITW

  1062   Wednesday, September 02, 2015, 09:26 David WangITEStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015

I attach new Target Hall schedules here for 2015 fall and winter runs (beam schedule 129). The TH excel sheet schedule for beam 129 is included also.

Weekly update of Target Hall Schedule.See Attachments 3,4

Attachment 1: Target_Hall_shedule_129_Sep_to_Dec.xlsx
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 3: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
Attachment 4: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 5: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
  1065   Thursday, September 10, 2015, 08:55 chad fisherSouth Hot-CellRepairTM1 TM1 Window Leak Diag.

Vacuum leak check on the window line circuit of TM1 took place yesterday and again to confirm this morning. Both days the response to helium is in the area of a soldered reduction fitting at the top of the containment box above and to the shutter side of the extraction column (see attached picture). To verify this morning each joint in the system had a 1 second shot of helium and then timed for 1 minute to wait for a response. This area responded both times tested at about 40 seconds...no response at any of the other locations.

Attachment 1: P0000122.JPG
P0000122.JPG
  1066   Thursday, September 10, 2015, 08:59 chad fisherSouth Hot-CellRepair  Manipulator Mait. and field check Sept. 4

Hot cell was entered for preventative mait. on left manip. field measurements around the cell were taken in prep. for window removal in January and left/south light bulb changed.

Hottest item in the cell was the conductor block end of the TM4 febiad coil line. It was 70 mSv/H on contact and seemed to be the major source of field in the hot cell. The waterblock end of this line did not apper to be hot.

  1069   Tuesday, September 15, 2015, 11:06 chad fisherSouth Hot-CellRepairTM1 TM1 Window Gasket Replacement

Replaced the custom silver gaskets on the entrance window panel of TM1 this morning...this has eliminated an sign of leak at this joint, however there appears to still be a leak somewhere...a good distance from the vcr joints of the window as we are getting a drift response.

Chad sprayed helium to soldering stems in containment box which we suspected with leak last week. With 1second click  on helium, after 80 seconds waiting time , the LD started to show leak up to 3xe-9atm.cc/sec.

Chad sprayed helium close to service tray and vacuum chase. with 1second click on helium , after 30 seconds waiting time, the LD started to show leak up to 2Xe-8 atm.cc/sec.

After this test, we knew the leak is somewhere in service tray or service cap, but not the soldering stems in containment box we suspected before.The further investigation is needed.

  1071   Thursday, September 17, 2015, 11:50 David WangSpent Target VaultRepairTM1 TM1 window circuit leak check

 Leak check TM1 window circuit soldering stems inside service cap when module is located at NE silo. LD base LR 0.0xE-9atm.cc/sec.  Only 1 second tiny amount  helium sprayed on stems soldering joints . LD got a quick response to high E-7 atm.cc/sec.Test is repeated again with same result.  See attachments

Attachment 1: TM1_leak_soldering_stems_001.JPG
TM1_leak_soldering_stems_001.JPG
Attachment 2: TM1_leak_soldering_stems_003.JPG
TM1_leak_soldering_stems_003.JPG
  1082   Friday, September 25, 2015, 07:56 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015

weekly update see attachment

Attachment 1: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
  1089   Thursday, October 01, 2015, 09:18 Travis CaveSpent Target VaultStandard Operation  Targets transfered to mini storage.

In preparation for shipping of the spent targets five have been moved to the mini storage. The following target were moved to the mini storage, SiC#26, Ta#36, UC#9,10,11.

  1090   Monday, October 05, 2015, 10:19 Anders MjosConditioning StationMaintenance  Chiller maintenance

 will be performed Tuesday October 6th

Tuesday, October 06, 2015: Maintenance re-schedlued for Wednesday October 7th