Entry  Friday, August 07, 2015, 10:01, David Wang, ITE, Standard Operation, , , Target Hall Scheduled Activities April 07 - August 19 2015 Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf
Weekly update target hall schedule and activities. See attachment 1,2
Update and extend Target Hall schedule to Sep 08.  See attachment 3,4
Entry  Monday, August 10, 2015, 14:07, Isaac Earle, South Hot-Cell, Repair, TM2, , TM2 Containment Box Removed 
The containment box was taken off TM2 in preparation for installation of a new coil line isolator.
ITA6272 and ITA6273 have been received from the Scintillator Shop.  ITA6274 should be ready by the end of today.
Entry  Thursday, August 13, 2015, 09:17, chad fisher, South Hot-Cell, Repair, TM2, , TM2 status 20150811_132709.jpg20150813_083255.jpg20150813_090814.jpg
Tuesday, August 11,  insulator ITA6272 was installed onto the "pin x" line (unused plasma electrode) and tested; it seems to have successfully
eliminated the shorts on that line.
Wednesday, August 12  "shunts" installed on tube heater and oven circuit and electrically  tested.
Entry  Thursday, August 13, 2015, 13:46, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Status 
As previously mentioned, dump target installed with new mounting and high current fasteners.
Leak Check complete and ready to move to CS at 1:30
Entry  Friday, August 14, 2015, 10:00, David Wang, Conditioning Station, Repair, TM2, , Started CS water package for TM2  
I finished the rest TM2 connections to CS, and started CS cooling package. Everything works fine so far.
Entry  Wednesday, August 19, 2015, 14:52, David Wang, Conditioning Station, Repair, TM2, , TM2 at CS 
During the TM2 HV test at CS, It failed. In order to confirm there is no any water leak inside the module after the heaters and beam extraction test,
I disconnected all the water lines on the TM2, and purged the water lines with pressure air. Leak detector was reconnected back to the TM2 service cap,
and all water lines are pressurized with 80psi helium again each for 2 minutes.No any leak had been found during the test. All the water lines are still
Entry  Thursday, August 20, 2015, 09:38, David Wang, Conditioning Station, Repair, TM2, , TM2 was disconnected at CS 
TM2 was disconnected at CS. Travis and I did  electrical check before the venting. After,The module was vented and moved to SHC. The moving is smooth.
Entry  Thursday, August 20, 2015, 13:48, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall Scheduled Activities April 07 - Sep 08 2015 Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf
 Weekly update target hall schedule.See attachment 1,2
Spring and summer run is close to the end. This will be the last update on this old schedule. See attachment3,4.    A new schedule
for TH activities after mini shut down will be posted next time.
Entry  Wednesday, August 26, 2015, 09:54, Anders Mjos, Conditioning Station, Maintenance, , , Topped up water in TCS:TK2 
 Filled to 24.9 in
Entry  Tuesday, September 01, 2015, 10:38, David Wang, ITW, Maintenance, TM2, , ITW top tank flange clean up and r-ring replacement. ITW_o-ring_replacement_2015-09-01_008.JPGITW_o-ring_replacement_2015-09-01_007.JPGITW_o-ring_replacement_2015-09-01_006.JPG
During last run, ITW dump circuit had a water leak on an adaptor below the pressure gauge. The top tank flange, slot, and O-ring were water contaminated
by the leak. I removed the old o- ring, cleaned up the flange and o-ring slot, and put a new o-ring into the flange. Some  pictures will be attached
in this mail later.
Entry  Tuesday, September 01, 2015, 14:54, David Wang, ITW, Standard Operation, TM2, , TM2 has been connectec in ITW. 
TM2 has been connected in ITW. During the connection, Anders and I  found the TM2  high current cables used in ITE and CS are short in ITW. 
Anders and Grant found the original TM2 ITE high current cables in target hall. We replaced them. They works fine. But, a little bit longer on cable length
would be easy to connect them. All other connections and HV cover in ITW work for the TM2 so far.
Entry  Tuesday, September 01, 2015, 16:55, Anders Mjos, Conditioning Station, Maintenance, , , TBHT power supply remvoed 
 The power supply is needed as a spare for the failed TGHT p/s in ITW
Entry  Wednesday, September 02, 2015, 09:26, David Wang, ITE, Standard Operation, , , Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 Target_Hall_shedule_129_Sep_to_Dec.xlsxTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
I attach new Target Hall schedules here for 2015 fall and winter runs (beam schedule 129). The TH excel sheet schedule for beam 129 is included also.
Weekly update of Target Hall Schedule.See Attachments 3,4
Entry  Thursday, September 10, 2015, 08:55, chad fisher, South Hot-Cell, Repair, TM1, , TM1 Window Leak Diag. P0000122.JPG
Vacuum leak check on the window line circuit of TM1 took place yesterday and again to confirm this morning. Both days the response to helium is in the
area of a soldered reduction fitting at the top of the containment box above and to the shutter side of the extraction column (see attached picture). To
verify this morning each joint in the system had a 1 second shot of helium and then timed for 1 minute to wait for a response. This area responded both
Entry  Thursday, September 10, 2015, 08:59, chad fisher, South Hot-Cell, Repair, , , Manipulator Mait. and field check Sept. 4 
Hot cell was entered for preventative mait. on left manip. field measurements around the cell were taken in prep. for window removal in January and left/south
light bulb changed.
Hottest item in the cell was the conductor block end of the TM4 febiad coil line. It was 70 mSv/H on contact and seemed to be the major source
Entry  Tuesday, September 15, 2015, 11:06, chad fisher, South Hot-Cell, Repair, TM1, , TM1 Window Gasket Replacement 
Replaced the custom silver gaskets on the entrance window panel of TM1 this morning...this has eliminated an sign of leak at this joint, however there
appears to still be a leak somewhere...a good distance from the vcr joints of the window as we are getting a drift response.
Chad sprayed helium to soldering stems in containment box which we suspected with leak last week. With 1second click  on helium, after 80
Entry  Thursday, September 17, 2015, 11:50, David Wang, Spent Target Vault, Repair, TM1, , TM1 window circuit leak check TM1_leak_soldering_stems_001.JPGTM1_leak_soldering_stems_003.JPG
 Leak check TM1 window circuit soldering stems inside service cap when module is located at NE silo. LD base LR 0.0xE-9atm.cc/sec.  Only 1
second tiny amount  helium sprayed on stems soldering joints . LD got a quick response to high E-7 atm.cc/sec.Test is repeated again with same result. 
See attachments
Entry  Friday, September 25, 2015, 07:56, David Wang, Conditioning Station, Standard Operation, , , Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
weekly update see attachment
Entry  Thursday, October 01, 2015, 09:18, Travis Cave, Spent Target Vault, Standard Operation, , , Targets transfered to mini storage. 
In preparation for shipping of the spent targets five have been moved to the mini storage. The following target were moved to the mini storage, SiC#26,
Ta#36, UC#9,10,11.
Entry  Monday, October 05, 2015, 10:19, Anders Mjos, Conditioning Station, Maintenance, , , Chiller maintenance 
 will be performed Tuesday October 6th
Tuesday, October 06, 2015: Maintenance re-schedlued for Wednesday October 7th