2448
|
Tuesday, May 30, 2023, 12:23 |
Frank Song | ITE | Standard Operation | TM4 | TiC#5 | gas lines pump out in ITE Faraday Cage | argon is being supplied at 6 psi to TM4. |
|
2455
|
Tuesday, June 13, 2023, 09:55 |
Frank Song | ITE | Standard Operation | TM4 | TiC#5 | module disconnection | TM4 with TiC#5 was disconnected in
ITE and moved to NHC. |
|
2458
|
Wednesday, June 14, 2023, 07:10 |
Frank Song | ITE | Standard Operation | TM4 | SiC#45 | TM4 with SiC#45 connection in ITE | TM4 with new target SiC#45 was connected
in ITE, all TPs are running at their full
speed. |
|
2459
|
Wednesday, June 14, 2023, 13:37 |
David Wang | ITE | Standard Operation | TM4 | | ITE water signal interlock check | ITE water signal interlock check including
HS,EE, TA, TU, MSP. Coil1 , C-window ,2a-window,
2A tank, 2A shielding plug , 2A dump, 2A |
|
2465
|
Wednesday, July 19, 2023, 08:04 |
Frank Song | ITE | Standard Operation | TM4 | UCx#42 | Module Connection | TM4 with new target UCx#42 was connected
in ITE. |
|
2483
|
Tuesday, August 29, 2023, 09:33 |
Frank Song | ITE | Standard Operation | TM4 | UCx#42 | module disconnection | TM4 with spent target UCx#42 was
disconnected in ITE and has been remote moved
to NHC this morning. |
|
2488
|
Wednesday, September 06, 2023, 08:07 |
Frank Song | ITE | Standard Operation | TM4 | Ta#65 | Module Connection | TM4 was connected in ITE with new
target Ta#65 installed. see attachment in
detail. |
|
2499
|
Tuesday, November 07, 2023, 13:55 |
Frank Song | ITE | Standard Operation | TM4 | Ta#65 | module disconnection | TM4 with spent target Ta#65 was disconnected
in ITE and moved to SHC. |
|
2508
|
Wednesday, November 29, 2023, 12:45 |
Carla Babcock | ITE | Standard Operation | | | gas lines pumped down | Pumped down the gas lines in ITE on Tuesday
Nov. 28 2023 and opened the CF4 bottle valves.
Missed the small section between the regulator |
|
2512
|
Thursday, December 21, 2023, 09:37 |
Ferran Boix Pamies | ITE | Development | | | Rewiring of TC multiping wires | Thursday, December 21, 2023, 09:36.
ITE multipin wires 12-13-14-15 were rewired
from the RF driver box to a TC datalogger |
|
2519
|
Wednesday, January 10, 2024, 16:51 |
Carla Babcock | ITE | Standard Operation | TM4 | UCx#43 | UCx#43 failure | To deliver stable beam to RadMol,
started heating UCx#43 up again. Target was
overheated during initial conditioning in |
|
2527
|
Monday, January 22, 2024, 10:16 |
David Wang | ITE | Standard Operation | TM4 | UCx# | Tm4 waterlines helium pressure test and TM service cap helium leak check. | Tm4 waterlines helium pressure test and
TM service cap helium leak check was done
last Friday. All water lines were pressurized |
|
2528
|
Monday, January 22, 2024, 14:12 |
Frank Song | ITE | Standard Operation | TM4 | UCx#43 | module disconnection | TM4 with spent target UCx#43 was
disconnected in ITE and is ready moved to
SHC. see attachment pls. |
|
2537
|
Friday, February 02, 2024, 07:48 |
David Wang | ITE | Standard Operation | TM4 | | ITE primary and secondary vacuum vessel leak check. | ITE primary and secondary vacuum vessel
leak check has been done. SST bellow for
2A3M19 wire scanner on entrance module |
|
2545
|
Thursday, February 15, 2024, 17:40 |
Carla Babcock | ITE | Standard Operation | | | ITE annual HV testing | ITE was set up for HV tests - this time
the module plug was not in so the BIAS and
EE had to be bypassed. NOTE: ITE:BIASPLC |
|
2548
|
Friday, February 23, 2024, 06:36 |
David Wang | ITE | Maintenance | | | ITE entrance module has been disconnected. | ITE entrance module has been disconnected
per document 190510. Its a preparation job
for next month module moving out to SHC. |
|
2550
|
Thursday, March 14, 2024, 14:54 |
David Wang | ITE | Maintenance | | | ITE entrance module has been moved from ITE pit to TCS. | ITE entrance module has been moved from
ITE pit to TCS. The move is smooth.ITE entrance
module top tank flange and o ring slot are |
|
2552
|
Thursday, March 21, 2024, 11:35 |
Ferran Boix Pamies | ITE | Development | | | Wiring of new thermocouple PLC module | Thursday, March 21, 2024, 11:33 Three
channels are available now for thermocouple
readouts from the Target multipin. Wiring |
|
2553
|
Monday, March 25, 2024, 10:53 |
David Wang | ITE | Repair | | | ITE entrance module has been moved from TCS to ITE. | ITE entrance module has been moved from
TCS to ITE. The move is smooth. |
|
2554
|
Monday, March 25, 2024, 10:55 |
David Wang | ITE | Standard Operation | | | ITE entrance module has been reconnected in ITE pit. | ITE entrance module has been reconnected
in ITE pit per document 190510. |
|