ID Date Author Category Type Module Target/Number Subjectdown
  2248   Tuesday, September 21, 2021, 13:47 Travis CaveNorth Hot-CellStandard OperationTM2UC#34Module move

 TM#2 with UC#34 has been moved from ITW to the north hot cell had the target removed and then moved to the south west silo.

  2251   Monday, September 27, 2021, 14:29 Travis CaveITWStandard OperationTM2Graphite #3Module move

 TM#2 with C#3 has been moved from the north hot cell to ITW. Also for the up coming site wide power outage, the ISAC Target Hall crane has been turned off and powered down, also the remote crane console has also been power down as well so that mean no ISAC TV for a few days.

  2255   Monday, October 04, 2021, 10:52 Travis CaveNorth Hot-CellStandard OperationTM4SiC#41Module move

 TM#2 moved from ITE to NHC SiC#41 removed and then moved back to ITE.

  2793   Thursday, April 24, 2025, 11:33 Travis CaveConditioning StationStandard Operation UC#48Module move

 TM4 with UC48 went on a long trip from the north hot cell to the conditioning station.

  2043   Wednesday, January 08, 2020, 10:34 David WangAssembly/Bench TestDevelopment  Module lifting assembly ITA0490

The second module lifting assembly ITA0490 is moved into TH and installed onto TM3 . It will stay with TM3. I adjusted the  CofG on the assembly. It is same to the first lifting assembly we are using now. After adjustment, The installation of assembly on TM3 are smooth. 

  2443   Monday, May 22, 2023, 15:06 Carla BabcockITEStandard OperationTM4TiC#5Module conditioning

Yesterday and today module conditioning was done on Tm4 in ITE. This is the first ramp up after the shutdown and ITE is planned to run at high voltages for the first weeks. The module is behaving well - went up to 40kV yesterday, stayed there for an hour, and up to 46kV today. Current draw is 113uA at 46kV. No serious sparking.

 

Tuesday, May 23, 2023, 09:32 :  Ramping up again, easy to 45kV. Drawing 132uA at 49kV. Still behaving quite well.

  2453   Tuesday, June 06, 2023, 17:36 Carla BabcockITWStandard OperationTM2TiC#6Module conditioning

Conditioned TM2 up to 48kV in ITW. Some sparks and current is not very stable. Drawing about 178uA at 48kV.

  120   Thursday, June 07, 2012, 11:58 Bevan MossConditioning StationStandard OperationTM1Ta38Module Move from SHC to TCS

TM1 was moved from SHC to the TCS. The mode took roughly 1 hour. During the move the north east corner of the containment box caught slightly on the flange of the vacuum vessel and then slipped off. The contact was minimal but should none the less be noted. After sliding off of the flange the module did not crash into the other sides of the vacuum vessel, this is why I believe the contact was minimal. It should be noted that the corner of concern is the one that is most difficult to see.

  255   Friday, March 08, 2013, 15:50 Bevan MossITEStandard OperationTM4CS Test Target #1Module Move from ITE to SHC

 Today David and I moved the module from ITE to the SHC. Move went very smoothly, David operated the cameras and has had basic training in how to manually lock out the controls.

  193   Tuesday, October 09, 2012, 11:17 Bevan MossITEStandard OperationTM4NiO#1Module Move

 TM4 with NiO#1 was moved from ITE to the SHC today. The move went well with no issues.

  195   Tuesday, October 09, 2012, 14:53 Bevan MossConditioning StationDevelopmentTM4UCx#5Module Move

TM4 was remote moved from the SCH to the TCS today. This was the first time the module was moved with the framework for the cage in place. The ion gauge on the service cap is closer to the cage than anticipated and as a result the pins for the gauge were sheared off. Discussion as to how to repair the gauge (both short term and long term needs to be had). We will try and rough down the TM tonight, it is not believed the vacuum will be affected.

  260   Wednesday, March 13, 2013, 14:31 Bevan MossConditioning StationStandard OperationTM4CS Test Target #1Module Move

 TM4 with CS Test Target #1 was moved from the SHC to the Conditioning Station. All went well. The welding cables came a little close to the cage, David will bend them in more in the future.

  2164   Tuesday, November 17, 2020, 10:17 Adam NewsomeSouth Hot-CellStandard OperationTM2 Module Move

TM2 has been moved from ITW to the South Hot Cell.


Reading at ITW: 114 mSv/hr

Reading at SHC: 85 mSv/hr

  2168   Tuesday, November 24, 2020, 09:37 Adam NewsomeITWStandard OperationTM2 Module Move

TM2 has been moved from the Conditioning Station to ITW. 

  2170   Wednesday, November 25, 2020, 09:05 Adam NewsomeSouth Hot-CellStandard OperationTM3 Module Move

TM3 has been moved from the Silo to the South Hot Cell.

  2263   Tuesday, November 09, 2021, 14:35 Adam NewsomeSouth Hot-CellStandard OperationTM2UCX#36Module Move

TM#2 was moved from ITW to SHC, then moved back to ITW.

  2246   Friday, September 17, 2021, 12:34 Frank SongITEStandard OperationTM4Sic#41Module Connection

 TM4 with a new target was moved back from NHC to ITE and reconnected at pit. The 5 shielding blocks were installed as well. Copies of connection checklist are attached here.

  2252   Monday, October 04, 2021, 09:27 Frank SongITWStandard OperationTM2C#3Module Connection

 TM2 been connected with new target C#3 in ITW. 

  2258   Friday, October 08, 2021, 12:39 Frank SongITEStandard OperationTM4UCx#35Module Connection

 the module with target UC#35 was connected in ITE and being pumped down.

  2265   Wednesday, November 10, 2021, 08:32 Frank SongITWStandard OperationTM2UC#36Module Connection

 TM2 with target UC#36 was connected at ITW.