Tuesday, July 07, 2015, 10:50, Anders Mjos, Conditioning Station, Development, , , EPICS migration update - archiver
|
The archiver is now merged with ISAC - data available under Utilities - Archiver Retrieval
Old archiver data is
available under Utilities -> Archiver Retrieval - old
Strip tool save/load and export files under /data/tcsdata
Login via isacepics1.triumf.ca. TCS button on ISAC menu
|
Friday, July 03, 2015, 13:29, chad fisher, South Hot-Cell, Repair, TM2, , Hot Cell/ Module Fields
|
Field measured at block "R" through tool port with pole monitor is 6.65 mSv/H.
There are three air hoods and two air lines currently available. |
Friday, July 03, 2015, 11:33, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Coil Leak Progress 
|
First thing this morning the hot cell was "cleaned up" in preparation for the return of TM2 for attempted verification and locating of leak
on R/U coil circuit.
Containment box has been removed and front cover reinstalled to provide some modicum of shielding form the entrance and exit windows. Box was placed |
Friday, July 03, 2015, 09:41, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall Scheduled Activities April 07 - July 24 2015   
|
Updated the schedule before the weekend 2015-07-03. See attachment 1,2
Updated the schedule according to present TM2 refurbishment process. See attachment 3,4 |
Friday, July 03, 2015, 09:27, Anders Mjos, Conditioning Station, Development, , , Controls working on access control in EPICS
|
Some reboots will be done. |
Friday, July 03, 2015, 09:11, Travis Cave, South Hot-Cell, Standard Operation, TM2, no target, Module moved
|
TM#2 has been moved from the conditioning station to the south hot cell. |
Thursday, July 02, 2015, 11:51, Travis Cave, Spent Target Vault, Standard Operation, , UC#12, Spent target moved
|
UC#12 has been moved from the south hot cell and placed into storage. It is in pail #125 and in spot 1C of the vault it had a reading of 25.1mSv/hr upon
removal from the south hot cell. See PDF for vault details. |
Thursday, July 02, 2015, 11:49, Travis Cave, South Hot-Cell, Standard Operation, TM1, no target, Module moved
|
TM#1 has been moved from the south hot cell to the south west silo. |
Thursday, July 02, 2015, 10:22, Anders Mjos, Conditioning Station, Maintenance, TM2, , TP1S failed
|
See e-fault 8233. Edi assisted in diagnosing the problem. The pump will have to be replaced. |
Tuesday, June 30, 2015, 15:53, David Wang, Conditioning Station, Development, TM2, , leak on TM2 at CS  
|
I leak checked TM2 at CS this afternoon which including air to vacuum check on service cap and helium pressure test on water lines. There is a
small leak on water line R ,U (COIL1) during the helium pressure test.. Below 20 psi helium, there is no leak on it. But , once the helium pressure is
increased over 20 psi, it showed up on Leak Detector. At 60 psi helium, the leak rate is 9.4xE-9 atm.cc/sec. For detail information, See attachment. |
Tuesday, June 30, 2015, 15:41, David Wang, ITW, Standard Operation, TM1, , TM1 was disconnected in ITW this morning.
|
TM1 was disconnected in ITW this morning. The ITW was vented with argon last night. |
Tuesday, June 30, 2015, 12:37, chad fisher, South Hot-Cell, Standard Operation, TM1, UCx#12, UCx #12 Removal
|
UCx#12 has been removed from TM1 and placed in a pail with argon.
Right leg (B) of target is clearly broken.
Containment Box cover re-installed and module ready to move. |
Tuesday, June 30, 2015, 11:27, Travis Cave, ITW, Standard Operation, TM1, UC#12, Module moved
|
TM#1 with UC#12 has been moved from the west station to the south hot cell. |
Tuesday, June 30, 2015, 09:47, chad fisher, South Hot-Cell, Repair, , , manipulator repair
|
The right hand manipulator has been repaired. It took 43 minutes and I received ~ 0.56 mSv |
Monday, June 29, 2015, 10:51, David Wang, Conditioning Station, Repair, TM2, , leak on TM2 side panel
|
There is an air to vacuum leak on TM2 service cap side panel which we moved out during the TM2 wiring job. The CS pumps are stopped now. The CS will
be vented soon. The seal on this panel has to been changed.
2016-06-30. The o-ring seal on this panel(PNG1 and steerers) is replaced and leak checked. No leak now. |
Friday, June 26, 2015, 15:38, Anders Mjos, Conditioning Station, Development, TM2, , Leak check and HV test
|
Roughing started by David.
Friday, June 26, 2015, 15:31: Started TP1S
Friday, June 26, 2015, 15:38: Started TP1 & TP2 |
Friday, June 26, 2015, 14:33, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 have been moved from SHC to CS
|
Bill and I mover TM2 from SHC to CS. The move is smooth. I connected the CS vacuum system after the move, and started the roughing. |
Friday, June 26, 2015, 09:45, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Status
|
Containment box window waterlines have been connected and leak checked and new containment box cover installed.
Module ready for transport just before 9am. |
Friday, June 26, 2015, 09:44, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Retrofit Status   
|
On June 25th the following work was completed:
Optics tray was installed into TM2. The lower fastener on the vertical cable tray (IRH1585) needed to be removed and vertical cable tray rotated
upwards as optics tray would not clear cable tray. Optics tray was intstaled, cable tray repositioned and screw re-inserted. |
Friday, June 26, 2015, 08:27, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall Scheduled Activities April 07 - July 24 2015   
|
Update the Target hall Schedule after some changes on TM2 refurbishment. See attachment 1,2
2015-06-30, updated the schedule after some jobs have been finished before Canada day. See attachment 3,4. |
|