  1540   Wednesday, May 17, 2017, 08:35 David WangConditioning StationStandard OperationTM4 TCS turbo pumps was started yesterday

Anders started TCS turbo-pumps yesterday. The TCS and TM4 pumping down is good so far. I started TCS water pumps this morning for TCS water flow check.

2017-05-17 morning:  Stopped the water pumps. The field around the TM4 is high because of spent target in SHC. The water flow measurement will be delayed to this Friday.

  1541   Thursday, May 18, 2017, 10:08 David WangConditioning StationStandard OperationTM4 TM4 TP1 at TCS

TM4 TP1 was found making some noise during operation this morning. The current draw was check then. It was 1.8 A which is higher than 1.0A normal range. The pump body temperature was higher by hand feeling. But,1.0 hour later when checking again, everything on the pump goes back to normal. It is still fine so far. I will watch on this pump closely.

 2017-05-19,morning.  The TM4 TP1 stopped running last night.  I tried to start it this morning. But, It can't pass 6KRMP even. I think we have to replace it.    E- fault will be issued as well.   

  1544   Friday, May 19, 2017, 12:25 David WangConditioning StationStandard OperationTM4 TCS and TM4 water flow measurement.

 

 

  TCS(LPM) Freq(HZ) TCS+TM4(LPM) Freq(HZ)
Ta 5.5 106 3.7 68
Tu 5.6 107 4.3 79
Coil(RU only) 5.8 112 4.6 92
HS 7.0 13 6.6 12
MSP 6.4 21 5.8 21
EE 5.6 112 3.8 77
Window 4.5 81 4.3 78

 

  1545   Friday, May 19, 2017, 13:49 David WangConditioning StationRepairTM4 TM4 TP1 at TCS

TM4 TP1 is replaced. TCS and TM4 was argon vented before the job.The job took about 30minutes.  I started the all turbo pumps after job. All pumps work fine. The TCS vacuum is good.     

  1547   Tuesday, May 23, 2017, 13:30 David WangITEStandard OperationTM4 TM4 has been connected in ITE

Yasmine and I connected TM4 in ITE . All turbo pumps are started.

  1548   Tuesday, May 23, 2017, 14:10 David WangITEStandard Operation  ITE water interlock check is done.

We do this check once a year now. Rene found a target oven reset issue during the check . He will consult with Friedhelm. The interlock check is good.

  1549   Wednesday, May 24, 2017, 08:11 David WangITWStandard OperationTM2 TH schedule 132 update weekly

See attachments.

Attachment 1: Target_Hall_shedule_132_Apr_to_Sep.mpp
Attachment 2: Target_Hall_shedule_132_Apr_to_Sep.pdf
Target_Hall_shedule_132_Apr_to_Sep.pdf
  1551   Wednesday, June 07, 2017, 13:33 David WangConditioning StationStandard OperationTM2 TM2 SiC#36 leakc check and electrical check.

The results  are good. See attachment.

Attachment 1: TM2_SiC_36#_leak_check_an_delectrical_check..pdf
TM2_SiC_36#_leak_check_an_delectrical_check..pdf
  1552   Wednesday, June 07, 2017, 13:34 David WangConditioning StationStandard OperationTM2 TM2 and TCS vacuum system has been connected.

I started all turbo pumps.

  1553   Thursday, June 08, 2017, 07:37 David WangConditioning StationStandard OperationTM2 Helium pressure test on TM2 water llines at TCS.
  The helium pressure test on HS line is done at TCS this morning. I got the same result as last time when we helium pressure it it with first target in April. The leak  rate on this line is 1.8 XE-7atm.cc/sec. So, we know this leak is mostly on the line, but not on the VCR joints connecting the target.  See attachment for last time(April) checking e-log. The leak could be from water block which is same as other lines. I do not think this leak rate will affect the operation.

The attachment can not be opened for some reasons. Please check TM2 leak check  2017-03-13 e- log for last time test result and comment.

Attachment 1: TM2_helium_pressure_test..png
TM2_helium_pressure_test..png
  1554   Thursday, June 08, 2017, 08:35 David WangConditioning StationDevelopmentTM2 TM2 gas line reconfiguration on the module top.

Reconfigured TM2 gas line on the module top. It matches with the febiad gas line we are using on service tray now. Facing the module, both of them should be that right side line of two SST lines on feed-through. The gas line on TM2 was leak checked with a blind cap installed on service tray side and LD connected on module top this Tuesday. It is leak free with helium spray on the top of module and service tray.

Attachment 1: TM2_gas_line_on_the_top_002.JPG
TM2_gas_line_on_the_top_002.JPG
  1559   Tuesday, June 13, 2017, 13:41 David WangITWStandard OperationTM2 TM2 has been connected in ITW.

Yasmine and I connected TM2 in ITW today. the control page is set to febiad mode. Both gas line in ITW are opened for febiad run. All connections are double checked. Module connection checklist is finished.  All turbo pumps are started now. Everything is good so far. The TM2 is ready for conditioning when the ITW vacuum is good enough.

  1561   Monday, June 19, 2017, 07:29 David WangConditioning StationStandard OperationTM2 Update TH MS project schedule.

Update TH MS project schedule. See attachment 1,2.

Attachment 1: Target_Hall_shedule_132_Apr_to_Sep.pdf
Target_Hall_shedule_132_Apr_to_Sep.pdf
Attachment 2: Target_Hall_shedule_132_Apr_to_Sep.mpp
  1563   Friday, June 23, 2017, 12:08 David WangCraneRepair  TH crane inspection and probem fixing by Gordon crane

Gordon crane technician Peter came in today and checked TH crane. Maico and I were there with him. What he found is that brake gap on both side of main hoist decreased after months of using.  The solution is to lock the automatic self adjustment system so the gap will be fixed there. Each year during annual inspection, they will adjust the gap manually. After he locked both side of device, I tested the crane up and down couple of times. The brakes work fine. 

  1568   Tuesday, June 27, 2017, 10:26 David WangSouth Hot-CellStandard OperationTM4Ta#52Leak check on TM4 HS line at SHC

LD base LR:0.0Xe-9 atm.cc/sec. No leak has been found during the check.  The HS line will be helium pressurized at TCS this week.

Helium pressurized the HS line at TCS. 70 psi 2 minutes, 0.0 x E-9 atm.cc/sec. No leak.

  1569   Tuesday, June 27, 2017, 14:34 David WangConditioning StationStandard OperationTM4 TM4 vacuum has been connected at TCS

Turbo -pumps are started . The vacuum looks good so far.

  1571   Wednesday, June 28, 2017, 10:00 David WangConditioning StationStandard OperationTM4Ta#52TM2 has been connected at TCS

I started TCS water system.

  1574   Thursday, June 29, 2017, 11:55 David WangConditioning StationRepair  TCS HV cable and feed through installation

John Chow and I installed new TCS HV cable and feed through with their mounting panel back to TCS Faraday cage this Tuesday. ECO-4269 has been issued for the new cable feed through and mounting panel.

  1580   Monday, July 10, 2017, 10:19 David WangConditioning StationStandard OperationTM4 Turned off TCS water system

Prepare for TM4 move tomorrow morning.

  1590   Wednesday, August 02, 2017, 15:09 David WangITWStandard OperationTM2 TM2 was disconnencted in ITW yesterday.

Tm2 was disconnected in ITW yesterday. ITW EL cable crimp ring was broken. John Chow replaced this ring this afternoon.