ID Date Authordown Category Type Module Target/Number Subject
  1344   Tuesday, September 06, 2016, 10:05 David WangITWStandard OperationTM2 5 Shielding blocks have been transferred from ITE to ITW.

5shielding blocks have been transferred from ITE to ITE. ITW is configured to take proton beam.

  1347   Thursday, September 08, 2016, 16:28 David WangConditioning StationRepairTM3 TM3 blue insulators have been replaced.

All TM3 blue insulators except Gas,EL, and 60 KV common  on top of the module have been replaced with new designed insulators. The new blue insulator for gas line need to be modified to fit for the bent on the gas  line.   EL, and 60KV common blue insulators were replaced during last time TM3 refurbishment so they are relative new, and  not replaced this time. All seals related to the blue insulators are changed to new seals. The o- r-ing surfaces  for o-ring 221 inside the  new insulators  are rougher than old parts. The module top need to be leak checked.

  1348   Thursday, September 08, 2016, 16:30 David WangConditioning StationRepairTM3 TM3 vacuum system have been connected at TCS.

start of roughing now.

 start of TCS and TM3 turbo-pumps. Everything is good so far.

  1349   Monday, September 12, 2016, 09:25 David WangConditioning StationRepairTM3 TM3 leak checked at TCS

After blue insulators replacement, TM3 service cap are leak checked. LD base leak rate 0.0xe-9 atm.cc/sec. I sprayed lots helium on all blue insulator seals. No leak has been found. Double checked them again, and got same result. All other seals on top of TM3 also have been checked. They are leak free. OVEN, TUBE, MSP, COIL, and EE water lines are pressurized with 70 psi helium for 3minutes each. They are good also.

  1351   Wednesday, September 14, 2016, 11:54 David WangConditioning StationRepairTM3 TM3 is disconnected at TCS.

 TM3 is disconnected at TCS and ready to be moved to silo.

  1354   Monday, September 19, 2016, 08:28 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 131(Sep-Dec, 2016)

Post new  target hall Excel sheet schedule for beam schedule 131. See attachment 1,2

Post new target hall  MS project schedule for beam schedule131. See attachment 3,4

Attachment 1: Target_Hall_shedule_131__Sep_to_Dec_2016.pdf
Target_Hall_shedule_131__Sep_to_Dec_2016.pdf
Attachment 2: Target_Hall_shedule_131__Sep_to_Dec_2016.xlsx
Attachment 3: Target_Hall_shedule_131_Sep_to_Dec.mpp
Attachment 4: Target_Hall_shedule_131_Sep_to_Dec.pdf
Target_Hall_shedule_131_Sep_to_Dec.pdf
  1356   Tuesday, September 20, 2016, 11:41 David WangITEStandard OperationTM4 TM4 has been disconnected in ITE.

TM4 has been disconnected in ITE. No water line purge on HS and 3 water circuits are looped after disconnection. The HALCW system resistivity is stable before and after this disconnection.

  1357   Tuesday, September 20, 2016, 11:48 David WangAssembly/Bench TestDevelopment  A silo and blue steel frame are removed out of TH

A silo and blue steel frame are removed out of TH this morning. They are transferred  through ante room, and moved to experimental hall TM assembly area for a long term storage. Swipes are done on the silo and frame before and during move. No contamination has been found .

  1358   Thursday, September 22, 2016, 13:04 David WangSouth Hot-CellStandard OperationTM4 SHC, TM4 leak check on HS line.

Chad and I leak checked the TM4 HS line after new target installation. base leak rate:0.0Xe-9 atm.cc/sec.  No response on LD during the leak check. The line is leak free so far. It will be helium pressurized at TCS  late.

  1359   Friday, September 23, 2016, 07:49 David WangConditioning StationStandard OperationTM4 TM4 has been moved and connected at TCS

All TCS and TM4 turbo-pumps were started yesterday. Overnight pumping down is good so far.

  1363   Tuesday, September 27, 2016, 07:30 David WangConditioning StationStandard OperationTM4 TM4 has been disconnected at TCS

TCS water system and vacuum system are turned  off this morning. The TCS and TM4 are vented.

  1365   Wednesday, September 28, 2016, 13:43 David WangITEStandard OperationTM4 TM4 has been connected at ITE

All ITE turbo pumps have been started since yesterday afternoon. The ITE and TM4 pumping down is good so far.

  1366   Wednesday, September 28, 2016, 13:47 David WangConditioning StationStandard Operation  TCS pumping down during mini-shut down.

A steel plate  is covered on TCS. TCS roughing pump  is started now. The TCS will be pumping down during mini-shut down.

  1367   Friday, September 30, 2016, 14:34 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 131(Sep-Dec, 2016)

Weekly update TH schedule for beam schedule 131. See attachments 1,2

Attachment 1: Target_Hall_shedule_131_Sep_to_Dec.mpp
Attachment 2: Target_Hall_shedule_131_Sep_to_Dec.pdf
Target_Hall_shedule_131_Sep_to_Dec.pdf
  1368   Tuesday, October 04, 2016, 09:18 David WangITEStandard OperationTM4 5 Shielding blocks have been transferred from ITW to ITE.

The ITE is configured to take proton beam.

  1370   Wednesday, October 12, 2016, 10:00 David WangITWStandard OperationTM2 TM2 was disconnected at ITW

TM2 was disconnected at ITW. 3 water circuits in ITW gave been looped to keep 75 GPM water flow to ITW. HS line was purged at HS. RPG got the water sample.

  1371   Wednesday, October 12, 2016, 10:01 David WangConditioning StationStandard Operation  TCS pumps are stopped

Argon venting is started

  1381   Monday, October 24, 2016, 14:54 David WangSouth Hot-CellStandard OperationTM2 SHC, TM2 leak check on HS line.

Chad and I did the leak check on TM2 heat shield line. LD base leak rate:0.0xE-9atm.cc/sec. Base pressure:0.0X E-9 torr. The line is leak free.

  1383   Tuesday, October 25, 2016, 15:10 David WangITWStandard OperationTM2 TM2 has been connected at ITW

All turbo pumps are started. Two gas valves for Febiad run are opened. Pumping down is good so far.

  1384   Wednesday, October 26, 2016, 12:33 David WangConditioning StationStandard OperationTM2 Target Hall schedule for beam schedule 131(Sep-Dec, 2016)

Update TH schedule after job delay on TM2 Febiad target. Everything should be back to schedule on last two targets. See attachments.

Attachment 1: Target_Hall_shedule_131__Sep_to_Dec_2016.pdf
Target_Hall_shedule_131__Sep_to_Dec_2016.pdf
Attachment 2: Target_Hall_shedule_131_Sep_to_Dec.mpp
Attachment 3: Target_Hall_shedule_131_Sep_to_Dec.pdf
Target_Hall_shedule_131_Sep_to_Dec.pdf