Entry  Tuesday, October 21, 2014, 08:55, chad fisher, South Hot-Cell, Repair, , , Manipulator repair 
Entry  Wednesday, October 22, 2014, 09:41, David Wang, Conditioning Station, Development, TM3, , TM3 has been disconnected at CS. 
Entry  Wednesday, October 22, 2014, 13:05, Anders Mjos, Conditioning Station, Maintenance, , , Controls upgrade on TCS 
Entry  Wednesday, November 05, 2014, 14:21, Anders Mjos, Conditioning Station, Development, , , Jumper installed on TGHT, TBHT and COIL Jumper1.jpgJumper2.jpg
Entry  Thursday, November 06, 2014, 13:43, David Wang, Conditioning Station, Development, TM3, , CS vacuum system has been connected to TM3. 
Entry  Thursday, November 13, 2014, 14:01, David Wang, ITW, Repair, TM1, , I replaced flow wheel and coil on ITW MSP water flow sensor. 
Entry  Thursday, November 13, 2014, 14:05, David Wang, ITE, Repair, TM4, , Dan and I replaced flow wheel on ITE HVC2 water flow sensor. 
Entry  Monday, November 17, 2014, 13:45, chad fisher, South Hot-Cell, Repair, , , Jig for roof install of target Target_roof_install_20141117_01.jpgTarget_Roof_install_Jig_20141117_02.jpgTarget_roof_install_20141117_03.jpgTarget_roof_install_20141117_04.jpg
Entry  Wednesday, November 19, 2014, 11:12, David Wang, Conditioning Station, Standard Operation, TM4, , CS roughing pump is started.  
Entry  Tuesday, November 25, 2014, 11:33, David Wang, South Hot-Cell, Development, , , Remove UCX 11 target transfer stand from SHC back to TH. 
Entry  Monday, December 01, 2014, 12:05, maicodallavalle, Spent Target Vault, Maintenance, , , F-308 Maintenance 
Entry  Monday, December 01, 2014, 14:06, chad fisher, South Hot-Cell, Repair, TM2, , TM2 REFURB. WATER LOOP TEST TM2_20141201_01.JPGTM2_20141201_02.JPGTM2_20141201_03.JPGTM2_20141201_04.JPGTM2_20141201_05AC.jpg
Entry  Monday, December 01, 2014, 14:48, Travis Cave, Spent Target Vault, Standard Operation, , , F-308s moved 
Entry  Tuesday, December 02, 2014, 10:15, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Reburb. Loop Install TM2_20141202_01.jpg20141203_142215.jpg20141203_143530.jpg
Entry  Tuesday, December 02, 2014, 13:33, David Wang, South Hot-Cell, Development, TM2, , Leak check on TM2 tube heater +(D) at SHC 2014-12-02_003.JPG2014-12-02_001.JPG2014-12-02_004.JPG
Entry  Thursday, December 04, 2014, 09:57, Travis Cave, Spent Target Vault, Standard Operation, , , Spent target placed in F-308. 
Entry  Thursday, December 04, 2014, 16:37, David Wang, Conditioning Station, Development, TM2, , connected TM2 and CS vacuum system . 
Entry  Friday, December 05, 2014, 07:47, David Wang, Conditioning Station, Development, TM2, , TM2 at CS 
Entry  Friday, December 05, 2014, 11:58, David Wang, Conditioning Station, Development, TM2, , helium pressure test on TM2 tube heater +(D) water lines. 6x
Entry  Friday, December 05, 2014, 13:46, Anders Mjos, Conditioning Station, Development, TM2, , Not able to start water system 