744
|
Wednesday, September 10, 2014, 07:12 |
David Wang | ITW | Repair | TM1 | | Removed ITW HS and COIL flow rate monitors. | Removed ITW HS and COIL flow rate monitors
installed at the beginning of this year.
They were installed on these two circuits |
|
746
|
Wednesday, September 10, 2014, 11:47 |
David Wang | ITW | Standard Operation | TM1 | | TM1 has been connected in ITW. | TM1 has been connected in ITW. ITW
and TM1 turbo pumps have been started. Water
is supplied to TM1 only. Everything is good |
|
747
|
Friday, September 12, 2014, 14:21 |
Travis Cave | Spent Target Vault | Standard Operation | | | Spent target field measurements | Five of the ten target we want to measure
the fields on were done today. We will finish
up on Monday, and the spent target storage |
|
748
|
Monday, September 15, 2014, 11:23 |
Travis Cave | Spent Target Vault | Standard Operation | | | Spent target field measurements | Field measurements on the spent target
has finished see the attached PDF for details. |
|
759
|
Friday, October 10, 2014, 10:47 |
David Wang | Conditioning Station | Development | TM3 | | TM3 has been connected in CS | TM3 has been connected in CS. All water
supplies are bypassed theTM3 on the top of
the service cap. TM3 TP2 was difficult to |
|
762
|
Tuesday, October 14, 2014, 12:19 |
David Wang | ITW | Standard Operation | TM1 | | TM1 was disconnected in ITW. | TM1 was disconnected in ITW this morning.
Heat shield circuit is purged. |
|
766
|
Thursday, October 16, 2014, 15:40 |
Anders Mjos | Conditioning Station | Maintenance | | | Chiller unit | NOTE: If there is a problem with
the chiller unit (ie Fault 1 or Fault 2),
a power cycle may reset the VFDs for the |
|
767
|
Friday, October 17, 2014, 13:36 |
Anders Mjos | Conditioning Station | Maintenance | | | TCS:Chil staging not operational | NOTE: If cooling is required, the
compressors will have to be run manually.
Make sure to switch it off again when the |
|
768
|
Monday, October 20, 2014, 08:59 |
David Wang | Conditioning Station | Development | TM3 | | Started TCS water system. | I started TCS water system this morning
to check if the chillers work properly. |
|
769
|
Monday, October 20, 2014, 09:13 |
David Wang | Conditioning Station | Development | TM3 | | TM3 TP2 failed | TM3 TP2 stopped working this morning at
4:00 AM. I tried to start it but failed.
On normal start mode , It could not pass |
|
770
|
Monday, October 20, 2014, 14:18 |
chad fisher | South Hot-Cell | Repair | | | Manipulator Repair | The broken cable on the east manipulator
has been replaced.
The handle will need some adjustments |
|
771
|
Tuesday, October 21, 2014, 08:55 |
chad fisher | South Hot-Cell | Repair | | | Manipulator repair | The east manipulator handle has been adjusted
and is ready for use. |
|
773
|
Wednesday, October 22, 2014, 09:41 |
David Wang | Conditioning Station | Development | TM3 | | TM3 has been disconnected at CS. | TM3 has been disconnected at CS. It is
vented and ready to move. |
|
774
|
Wednesday, October 22, 2014, 13:05 |
Anders Mjos | Conditioning Station | Maintenance | | | Controls upgrade on TCS | See work
permit for details |
|
781
|
Wednesday, November 05, 2014, 14:21 |
Anders Mjos | Conditioning Station | Development | | | Jumper installed on TGHT, TBHT and COIL | A copper bar jumper (ITD0488) was
installed on the TGHT, TBHT and COIL conductors
on the taregt hall side for TCS testing. |
 |
784
|
Thursday, November 06, 2014, 13:43 |
David Wang | Conditioning Station | Development | TM3 | | CS vacuum system has been connected to TM3. | CS vacuum system has been connected
to TM3 for control system test(Dave.Morris). |
|
786
|
Thursday, November 13, 2014, 14:01 |
David Wang | ITW | Repair | TM1 | | I replaced flow wheel and coil on ITW MSP water flow sensor. | I replaced flow wheel and coil on ITW MSP
water flow sensor which is located in ITW
pit. Before replacement, I checked the signal |
|
787
|
Thursday, November 13, 2014, 14:05 |
David Wang | ITE | Repair | TM4 | | Dan and I replaced flow wheel on ITE HVC2 water flow sensor. | Dan and I replaced flow wheel on ITE HVC2
water flow sensor. The old wheel did rotate
smoothly inside its SST case. The new wheel |
|
789
|
Monday, November 17, 2014, 13:45 |
chad fisher | South Hot-Cell | Repair | | | Jig for roof install of target | Jig for installation of target through
hot cell roof has been assembled and placed
in the target hall. |
   |
795
|
Wednesday, November 19, 2014, 11:12 |
David Wang | Conditioning Station | Standard Operation | TM4 | | CS roughing pump is started. | CS roughing pump is started for TM4 and
UCX 11 target. |
|