Thursday, June 02, 2016, 11:59, David Wang, South Hot-Cell, Repair, TM3, , 5K mega test on TM3
|
I did a 5KV mega test on TM3. Only5Mohm @5kV between coli line PQ and chassis(ground). It confirmed the close gap between P,Q and GE. Other lines are ok. See attachment. |
Tuesday, June 07, 2016, 11:36, David Wang, ITE, Standard Operation, TM4, Ta#47, TM4 has been disconnected in ITE.
|
Dan and I disconnected TM4 in ITE. HS water lines has been purged. |
Tuesday, June 07, 2016, 11:37, David Wang, ITE, Standard Operation, TM4, Ta#47, TM4 has been moved from ITE to SHC
|
Bill and Yasmine did the move. Everything is good. |
Tuesday, June 07, 2016, 11:42, David Wang, South Hot-Cell, Standard Operation, TM4, Ta#47, electrical check on TM4 with old Ta target at SHC. 
|
I did an electrical check on TM4 with the old target still installed. The number is a little bit low on 500V mega check between chassis and 60KVbias which is 146Mohm. Others are good. See attachment
I wrote all OL to 0 in attachment 1 ohmmeter check. Please See attachment 2 for correction. |
Tuesday, June 07, 2016, 17:11, David Wang, Conditioning Station, Standard Operation, TM4, UC#16, TM4 UCx16 electrical check and leak check at SHC 
|
Chad and I finished the TM4 UCx6 electrical check and leak check at SHC. Leak check result on HS line is good. There is a dead short between "Z" repellor and HS during the first time electrical check. The dead short disappeared after re- installation of UCx 14 target onto TM4. See attachment
Anders and I did another electrical check on TM4 at TCS under vacuum. See attachment 2 |
Tuesday, June 07, 2016, 17:14, David Wang, Conditioning Station, Standard Operation, TM4, UC#16, TM4 with UCx16 target has been moved from SHC to TCS.
|
Bill and Yasmine did the move remotely this afternoon. The move is successful. |
Tuesday, June 07, 2016, 18:17, David Wang, Conditioning Station, Standard Operation, TM4, UC#16, TM4 and TCS turbo pumps are started.
|
TM4 and TCS vacuum system are connected. Turbo pumps are started. Everything is fine so far. |
Thursday, June 09, 2016, 08:37, David Wang, Conditioning Station, Standard Operation, TM4, UC#16, TM4 with UCx16 helium pressure test at TCS
|
I did a helium pressure test on TM4 at TCS with UCX16 target installed on the module. No leak has been found on all using water lines in TM4. See attachment for detail. |
Thursday, June 09, 2016, 09:44, David Wang, Conditioning Station, Standard Operation, TM4, UC#16, TM4 has been connected at TCS
|
It is ready for HV conditioning/ heating. |
Thursday, June 09, 2016, 10:04, David Wang, Conditioning Station, Standard Operation, , , Target Hall schedule for beam schedule 130 (Apr- Sep) 
|
Weekly update . |
Tuesday, June 14, 2016, 08:04, David Wang, Conditioning Station, Standard Operation, TM4, UC#16, TM4 has been disconnected at TCS
|
The TM4 and TCS are vented with argon. |
Tuesday, June 14, 2016, 11:20, David Wang, ITE, Standard Operation, TM4, , TM4 has been connected in ITE
|
TM4 and ITE are under roughing now. |
Monday, June 27, 2016, 13:45, David Wang, ITE, Standard Operation, , , 5 Shielding blocks have been transferred from ITW to ITE.
|
ITE is configured to take proton beam. |
Wednesday, July 06, 2016, 07:03, David Wang, ITW, Standard Operation, TM2, , TM2 was connected in ITW.
|
TM2 was disconnected in ITW and moved to SHC. |
Wednesday, July 06, 2016, 07:06, David Wang, Conditioning Station, Standard Operation, , , venting TCS with argon.
|
I switched off the vacuum pumps and vented TCS with argon. The TCS will be ready to accept TM2 this afternoon. |
Wednesday, July 06, 2016, 14:25, David Wang, Conditioning Station, Standard Operation, TM2, , TCS and TM2 turbo-pumps have been started.
|
The TCS and TM2 are pumping down. |
Friday, July 08, 2016, 08:20, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 has been connected at TCS
|
I connected TM2 to TCS and started water system. |
Tuesday, July 12, 2016, 12:40, David Wang, ITW, Standard Operation, TM2, , TM2 has been connected in ITW
|
All turbo-pumps are started. Everything is good so far. |
Tuesday, July 12, 2016, 12:42, David Wang, Conditioning Station, Standard Operation, , , Target Hall schedule for beam schedule 130 (Apr- Sep) 
|
Update schedule weekly.Attachment 1,2 |
Thursday, July 14, 2016, 10:54, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall schedule for beam schedule 130 (Apr- Oct, 2016)   
|
Update TH schedule 130 according to mini-shut down change.See attachment 1,2,3,4 |
|