ID Date Authordown Category Type Module Target/Number Subject Text Attachments
  1249   Thursday, June 02, 2016, 11:59 David WangSouth Hot-CellRepairTM3 5K mega test on TM3I did a 5KV mega test on TM3.  Only5Mohm
@5kV between coli line PQ and chassis(ground).
It confirmed the close gap between P,Q and
 5K_mega_check_on_TM3.pdf 
  1253   Tuesday, June 07, 2016, 11:36 David WangITEStandard OperationTM4Ta#47TM4 has been disconnected in ITE.Dan and I disconnected TM4 in ITE. HS water
lines has been purged.
  
  1254   Tuesday, June 07, 2016, 11:37 David WangITEStandard OperationTM4Ta#47TM4 has been moved from ITE to SHCBill and Yasmine did the move. Everything
is good.
  
  1255   Tuesday, June 07, 2016, 11:42 David WangSouth Hot-CellStandard OperationTM4Ta#47electrical check on TM4 with old Ta target at SHC.I did an electrical check on TM4 with the
old target still installed. The number is
a little bit low on 500V mega check between
 electrical_check_2016-06-07._TM4_with_old_Lp_Ta_target..pdfelectrical_check_2016-06-07._TM4_with_old_Lp_Ta_target..pdf 
  1256   Tuesday, June 07, 2016, 17:11 David WangConditioning StationStandard OperationTM4UC#16TM4 UCx16 electrical check and leak check at SHCChad and I finished the TM4 UCx6 electrical
check and leak check at SHC. Leak check result
on HS line is good. There is a dead short
 UCX_16_electrical_test.pdfelectrical_check._TM4_UCx16_at_TCS..pdf 
  1257   Tuesday, June 07, 2016, 17:14 David WangConditioning StationStandard OperationTM4UC#16TM4 with UCx16 target has been moved from SHC to TCS.Bill and Yasmine did the move remotely
this afternoon. The move is successful.
  
  1258   Tuesday, June 07, 2016, 18:17 David WangConditioning StationStandard OperationTM4UC#16TM4 and TCS turbo pumps are started.TM4 and TCS vacuum system are connected.
  Turbo pumps are started.  Everything
is fine so far.
  
  1260   Thursday, June 09, 2016, 08:37 David WangConditioning StationStandard OperationTM4UC#16TM4 with UCx16 helium pressure test at TCSI did a helium pressure test on TM4 at
TCS with UCX16 target installed on the module.
No leak has been found on all using water
 TM4_withUCx16_helium_pressure_test_at_TCS.pdf 
  1261   Thursday, June 09, 2016, 09:44 David WangConditioning StationStandard OperationTM4UC#16TM4 has been connected at TCSIt is ready for HV conditioning/ heating.    
  1262   Thursday, June 09, 2016, 10:04 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 130 (Apr- Sep)Weekly update .  Target_Hall_shedule_130_Apr_to_Sep.mppTarget_Hall_shedule_130_Apr_to_Sep.pdf 
  1263   Tuesday, June 14, 2016, 08:04 David WangConditioning StationStandard OperationTM4UC#16TM4 has been disconnected at TCSThe TM4 and TCS are vented with argon.    
  1265   Tuesday, June 14, 2016, 11:20 David WangITEStandard OperationTM4 TM4 has been connected in ITETM4 and ITE are under roughing now.   
  1268   Monday, June 27, 2016, 13:45 David WangITEStandard Operation  5 Shielding blocks have been transferred from ITW to ITE.ITE is configured to take proton beam.   
  1271   Wednesday, July 06, 2016, 07:03 David WangITWStandard OperationTM2 TM2 was connected in ITW.TM2 was disconnected in ITW and moved to
SHC.
  
  1272   Wednesday, July 06, 2016, 07:06 David WangConditioning StationStandard Operation  venting TCS with argon.I switched off the vacuum pumps and vented
TCS with argon. The TCS will be ready to
accept TM2 this afternoon.
  
  1276   Wednesday, July 06, 2016, 14:25 David WangConditioning StationStandard OperationTM2 TCS and TM2 turbo-pumps have been started.The TCS and TM2 are pumping down.   
  1278   Friday, July 08, 2016, 08:20 David WangConditioning StationStandard OperationTM2 TM2 has been connected at TCSI connected TM2 to TCS and started water
system.
  
  1282   Tuesday, July 12, 2016, 12:40 David WangITWStandard OperationTM2 TM2 has been connected in ITWAll turbo-pumps are started. Everything
is good so far.
  
  1283   Tuesday, July 12, 2016, 12:42 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 130 (Apr- Sep)Update schedule weekly.Attachment 1,2  Target_Hall_shedule_130_Apr_to_Sep.pdfTarget_Hall_shedule_130_Apr_to_Sep.mpp 
  1285   Thursday, July 14, 2016, 10:54 David WangConditioning StationStandard OperationTM2 Target Hall schedule for beam schedule 130 (Apr- Oct, 2016)Update TH schedule 130 according to mini-shut
down change.See attachment 1,2,3,4
 Target_Hall_shedule_130_Apr_to_Sep.pdfTarget_Hall_shedule_130_Apr_to_Sep.mppTarget_Hall_shedule_130_Apr_to_Sep_2016.pdfTarget_Hall_shedule_129_Sep_to_Dec.xlsx 