ID |
Date |
Author |
Category |
Type |
Module |
Target/Number |
Subject |
1249
|
Thursday, June 02, 2016, 11:59 |
David Wang | South Hot-Cell | Repair | TM3 | | 5K mega test on TM3 |
I did a 5KV mega test on TM3. Only5Mohm @5kV between coli line PQ and chassis(ground). It confirmed the close gap between P,Q and GE. Other lines are ok. See attachment. |
Attachment 1: 5K_mega_check_on_TM3.pdf
|
|
1253
|
Tuesday, June 07, 2016, 11:36 |
David Wang | ITE | Standard Operation | TM4 | Ta#47 | TM4 has been disconnected in ITE. |
Dan and I disconnected TM4 in ITE. HS water lines has been purged. |
1254
|
Tuesday, June 07, 2016, 11:37 |
David Wang | ITE | Standard Operation | TM4 | Ta#47 | TM4 has been moved from ITE to SHC |
Bill and Yasmine did the move. Everything is good. |
1255
|
Tuesday, June 07, 2016, 11:42 |
David Wang | South Hot-Cell | Standard Operation | TM4 | Ta#47 | electrical check on TM4 with old Ta target at SHC. |
I did an electrical check on TM4 with the old target still installed. The number is a little bit low on 500V mega check between chassis and 60KVbias which is 146Mohm. Others are good. See attachment
I wrote all OL to 0 in attachment 1 ohmmeter check. Please See attachment 2 for correction. |
Attachment 1: electrical_check_2016-06-07._TM4_with_old_Lp_Ta_target..pdf
|
|
Attachment 2: electrical_check_2016-06-07._TM4_with_old_Lp_Ta_target..pdf
|
|
1256
|
Tuesday, June 07, 2016, 17:11 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#16 | TM4 UCx16 electrical check and leak check at SHC |
Chad and I finished the TM4 UCx6 electrical check and leak check at SHC. Leak check result on HS line is good. There is a dead short between "Z" repellor and HS during the first time electrical check. The dead short disappeared after re- installation of UCx 14 target onto TM4. See attachment
Anders and I did another electrical check on TM4 at TCS under vacuum. See attachment 2 |
Attachment 1: UCX_16_electrical_test.pdf
|
|
Attachment 2: electrical_check._TM4_UCx16_at_TCS..pdf
|
|
1257
|
Tuesday, June 07, 2016, 17:14 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#16 | TM4 with UCx16 target has been moved from SHC to TCS. |
Bill and Yasmine did the move remotely this afternoon. The move is successful. |
1258
|
Tuesday, June 07, 2016, 18:17 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#16 | TM4 and TCS turbo pumps are started. |
TM4 and TCS vacuum system are connected. Turbo pumps are started. Everything is fine so far. |
1260
|
Thursday, June 09, 2016, 08:37 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#16 | TM4 with UCx16 helium pressure test at TCS |
I did a helium pressure test on TM4 at TCS with UCX16 target installed on the module. No leak has been found on all using water lines in TM4. See attachment for detail. |
Attachment 1: TM4_withUCx16_helium_pressure_test_at_TCS.pdf
|
|
1261
|
Thursday, June 09, 2016, 09:44 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#16 | TM4 has been connected at TCS |
It is ready for HV conditioning/ heating. |
1262
|
Thursday, June 09, 2016, 10:04 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule for beam schedule 130 (Apr- Sep) |
Weekly update . |
Attachment 1: Target_Hall_shedule_130_Apr_to_Sep.mpp
|
Attachment 2: Target_Hall_shedule_130_Apr_to_Sep.pdf
|
|
1263
|
Tuesday, June 14, 2016, 08:04 |
David Wang | Conditioning Station | Standard Operation | TM4 | UC#16 | TM4 has been disconnected at TCS |
The TM4 and TCS are vented with argon. |
1265
|
Tuesday, June 14, 2016, 11:20 |
David Wang | ITE | Standard Operation | TM4 | | TM4 has been connected in ITE |
TM4 and ITE are under roughing now. |
1268
|
Monday, June 27, 2016, 13:45 |
David Wang | ITE | Standard Operation | | | 5 Shielding blocks have been transferred from ITW to ITE. |
ITE is configured to take proton beam. |
1271
|
Wednesday, July 06, 2016, 07:03 |
David Wang | ITW | Standard Operation | TM2 | | TM2 was connected in ITW. |
TM2 was disconnected in ITW and moved to SHC. |
1272
|
Wednesday, July 06, 2016, 07:06 |
David Wang | Conditioning Station | Standard Operation | | | venting TCS with argon. |
I switched off the vacuum pumps and vented TCS with argon. The TCS will be ready to accept TM2 this afternoon. |
1276
|
Wednesday, July 06, 2016, 14:25 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TCS and TM2 turbo-pumps have been started. |
The TCS and TM2 are pumping down. |
1278
|
Friday, July 08, 2016, 08:20 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 has been connected at TCS |
I connected TM2 to TCS and started water system. |
1282
|
Tuesday, July 12, 2016, 12:40 |
David Wang | ITW | Standard Operation | TM2 | | TM2 has been connected in ITW |
All turbo-pumps are started. Everything is good so far. |
1283
|
Tuesday, July 12, 2016, 12:42 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule for beam schedule 130 (Apr- Sep) |
Update schedule weekly.Attachment 1,2 |
Attachment 1: Target_Hall_shedule_130_Apr_to_Sep.pdf
|
|
Attachment 2: Target_Hall_shedule_130_Apr_to_Sep.mpp
|
1285
|
Thursday, July 14, 2016, 10:54 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Target Hall schedule for beam schedule 130 (Apr- Oct, 2016) |
Update TH schedule 130 according to mini-shut down change.See attachment 1,2,3,4 |
Attachment 1: Target_Hall_shedule_130_Apr_to_Sep.pdf
|
|
Attachment 2: Target_Hall_shedule_130_Apr_to_Sep.mpp
|
Attachment 3: Target_Hall_shedule_130_Apr_to_Sep_2016.pdf
|
|
Attachment 4: Target_Hall_shedule_129_Sep_to_Dec.xlsx
|