  698   Wednesday, July 02, 2014, 14:29 David WangITEStandard Operation  Reconnected TM3 in ITE.

I reconnected TM3 in ITE. All turbo pumps have been started. The water supply to TM3 only in ITE. The HV keys are back to electrical room.

  700   Tuesday, July 08, 2014, 09:57 David WangITEStandard OperationTM3 5 Shielding blocks have been transferred from ITW to ITE.

5 Shielding blocks have been transferred from ITW to ITE. The ITE is configured to take proton beam.

  702   Wednesday, July 16, 2014, 11:28 David WangITWStandard OperationTM1 TM1 had been dsiconnected in ITW.

The TM1 and ITW  were vented with argon gas last night. TM1 had been disconnected in ITW this morning.

  708   Thursday, July 17, 2014, 10:13 David WangConditioning StationStandard OperationTM1 Leak check on TM1 HS water line with new target installed

Chad and I leak checked TM1 HS waterline with new target installed at SHC. The LD base LR:0.0xE-9atm.cc/sec, base pressure: 0.0xE-4 torr. Chad sprayed helium on both VCR fittings and flushed helium around the target. No response has been found on leak detector. The target HS line is leak tight so far. I will do helium pressure test on this line at CS on next Monday.

  709   Thursday, July 17, 2014, 11:49 David WangConditioning StationStandard OperationTM1 TM1 and CS turbo pumps have been started

I connected TM1 at CS. All turbo pumps have been started. The pumping down is  good so far.

  710   Monday, July 21, 2014, 13:11 David WangConditioning StationStandard OperationTM1 helium pressure test on TM1 HS water line at CS.

The TM1 HS line is  pressure tested this morning with 70 psi helium  at CS. No response has been found on leak detector.

  711   Tuesday, July 22, 2014, 07:32 David WangConditioning StationStandard OperationTM1 Stop TM1 and CS turbo pumps and ruff pump.

Stop TM1 and CS turbo pumps and ruff pump. TM1 is disconnect at CS. It will be vented tomorrow morning and moved to ITW.

  712   Wednesday, July 23, 2014, 13:36 David WangITWStandard OperationTM1 TM1 in ITW.

  TM1 has been connected in ITW . The new roughing pump replaced on last Friday works good. I started all turbo pumps in ITW. The ITW TP1 controller was broken during the starting time. Dimo and I changed a new controller for ITW TP1 in electrical room. The pumping down is good so far. ITW water supplies to TM1 only.      

  716   Monday, July 28, 2014, 14:37 David WangConditioning StationDevelopmentTM2 helium pressure test on TM2 tube heater +(D)and -(C)water lines.
  • TM2 installed in Conditioning Station
  • Varian Leak detector connected directly to Target Module 2 Service cap.
  • Vacuum draw in Target Station with both module turbo pumps
  • Leak detector baseline normal (10^-4 Torr, 10^-9 Std cc/s He)
  • Since no Source tray is installed, and tube heater supply conductor is blanked off in target enclosure, it was necessary to test both supply and return points.
  • For each line tested, 80 psi He was connected, and waited ~2 min to for a response on the leak detector.
  • Lines tested:
    • conductor D (tube heater), Supply -> no He response
    • conductor D (tube heater), Return -> no He response
    • conductor C (tube heater), Supply -> no He response
    • conductor C (tube heater), Return -> no He response
  • Based on this leak testing, both supply and return lines of conductors C & D are leak tight under 95 psi He (80 psig He supply to vacuum)

 

Attachment 1: 011.JPG
011.JPG
Attachment 2: 012.JPG
012.JPG
Attachment 3: 013.JPG
013.JPG
Attachment 4: 014.JPG
014.JPG
Attachment 5: 015.JPG
015.JPG
Attachment 6: 017.JPG
017.JPG
Attachment 7: 018.JPG
018.JPG
  717   Monday, July 28, 2014, 14:45 David WangConditioning StationDevelopmentTM2 turned off TM2 and CS turbo pumps.

I turned off TM2 and CS turbo-pumps. TM2 will be moved from CS to silo tomorrow morning.

  718   Monday, July 28, 2014, 17:26 Ron KuramotoITWRepair  ITW:IV5 Air leak repair

Air leak was found at the Solenoid control valve located in the Pre-Separator & DB0 room.  The gasket between the solenoid body and its manifold block was broken, see attached photos. The gasket and solenoid body were replaced. Air was turned back on to IV5 (B/L gate valve) with no apparent air leaks. The gate valve was actuated open & closed from the control room seeing both limits successfully.

Repair was done by Dimo Y. who received 0.01 mSv, and assisted by Anthony I. & Ron K. who both received zero dose.
Rad fields measured by RPG were; 1300 uSv/hr above B/L and 350 uSv/hr @ the Solenoid valves at knee height.
 
 

DSCN0087.JPG

 

20140728_142855_-_small.jpg

 

20140728_143202_-_small.jpg

  719   Wednesday, July 30, 2014, 11:51 Travis CaveConditioning StationMaintenance  entrance module move

ITE Entrance module has been moved from the east station to the conditioning station.

  721   Tuesday, August 05, 2014, 10:40 Travis CaveITEStandard Operation  module move

ITE Entrance module has been moved back to the east station.

  722   Tuesday, August 05, 2014, 11:53 David WangITERepair  Reconnected ITE entrance module

ITE entrance module is reconnected in ITE.

  731   Monday, August 11, 2014, 14:27 David WangConditioning StationStandard OperationTM4 TM4 are vented with argon and disconnected at CS.

TM4 are vented with argon and disconnected at CS this morning.

  734   Wednesday, August 20, 2014, 10:25 David WangITEStandard OperationTM4 5 Shielding blocks have been transferred from ITW to ITE.

5 Shielding blocks have been transferred from ITW to ITE. ITE  is configured to take proton beam.
 

  735   Wednesday, September 03, 2014, 10:50 David WangITWStandard OperationTM1  TM1 has been disconnected in ITW.

  TM1 has been disconnected in ITW.

  739   Thursday, September 04, 2014, 09:47 David WangSouth Hot-CellStandard OperationTM1 Leak check on TM1 HS water line with new target installed

Chad and I  leak checked the TM1 HS line with new target installed. Base leak rate 0.0xe-9 atm.cc/sec. No any response has been found on LD. The line will be pressurized at CS with helium tomorrow.

  740   Thursday, September 04, 2014, 11:19 David WangConditioning StationStandard OperationTM1 TM1 is connected in CS.

TM1 is connected in CS. All turbo pumps are started.

  741   Friday, September 05, 2014, 07:15 David WangConditioning StationStandard OperationTM1 helium pressure test on TM1 HS water line at CS.

Helium pressure test on TM1 HS water line at CS is done. 80psi helium with LD 0.0xE-9 atm.cc/sec. 3 minutes test and no response on LD. The line is leak tight.