  19   Wednesday, August 17, 2011, 13:09 Bevan MossITWStandard OperationTM1Ta #37TM1 move from ITW to Hot Cell TM1 with Ta #37 target was moved
from ITW to the south hot cell. The rotation
of TM1 may have been off slightly during
  
  20   Thursday, August 18, 2011, 13:12 chad fisherSouth Hot-CellStandard OperationTM1UCx #2UCx #2 InstallationUCx #2 has been installed onto TM1.
Installation went well except the
left leg got bent slightly sometime between
  
  21   Thursday, August 18, 2011, 14:09 Bevan MossSouth Hot-CellStandard OperationTM1UCx#2Leak and Electrical Check plus Remote Move to Conditioning Station TM1 with UC#2 had the target installed,
the heat shield line was pumped on and achieved
a vacuum of 0.0 x 10^-4 Torr and a  leak
  
  22   Thursday, August 18, 2011, 16:07 Bevan MossConditioning StationStandard OperationTM1UCx#2Pump Down Pump down in the conditioning station
started at ~2:40 for rough down. The turbo
pumps were turned on at ~3:30 and at 3:52
  
  23   Friday, August 19, 2011, 14:52 Bevan MossConditioning StationRepairTM1UCx#2Leak Check A
leak check was performed on the module when
it was in the conditioning station today.
  
  24   Wednesday, August 24, 2011, 16:35 Bevan MossSouth Hot-CellRepairTM1UCx#2Move, inspection and repair On August 22nd TM1 was vented with
Argon in the conditioning station. It had
been pumping with just the roughing pump
 2011-08-23-17-41-40.UCx_Leak_August_22_2011.jpg 
  25   Wednesday, August 24, 2011, 17:11 Bevan MossConditioning StationStandard OperationTM1UCx#2Leak Check, HV conditioning and Module MoveToday a leak check on TM1's external seals
and the heat shield line was completed by
David Wang. After 16 hours of the turbo pumps
  
  26   Thursday, September 01, 2011, 09:11 Don JacksonITWStandard OperationTM1UCx#2Argon Venting West StationWest target station is setup to use argon
for tank venting.  There is 1200 PSI
remaining on argon bottle in electrical room. 
  
  32   Monday, October 03, 2011, 11:00 Travis CaveITWStandard OperationTM1UCx#2Move from west station to south hot cellTM#1 with UCx#2 has been moved from the
west station to the south hot cell. Move
went well.
  
  33   Monday, October 03, 2011, 11:54 chad fisherSouth Hot-CellStandard OperationTM1UCx#2 - TaC#1Target change UCx#2-TaC#1UCx#2 has been removed from Tm1 and put
in a bucket with a slow argon feed and a
lid placed lossely on top.
  
  34   Monday, October 03, 2011, 14:52 Travis CaveSouth Hot-CellStandard OperationTM1TaC#1Electrical checkTM#1 with TaC#1 installed passed the electrical
test. With a value of 882MOhms that was meggered
from the heat shield to the chassis, all
  
  35   Tuesday, October 04, 2011, 14:13 Travis CaveITWStandard OperationTM1TaC#1Move ot TM#1Move of TM#1 with the TaC#1 target has
been moved from the south hot cell to the
west target station.
  
  50   Monday, November 14, 2011, 14:07 Travis CaveITWStandard OperationTM1TaC#1Module moveTM#1 with TaC#1 from the west target station
to the south hot cell. Move went well.
  
  51   Tuesday, November 15, 2011, 13:08 Travis CaveConditioning StationStandard OperationTM1 Move ot TM#1TM#1 has been moved from the south hot
cell to the conditioning station. Move went
well.
  
  52   Wednesday, November 16, 2011, 07:44 chad fisherSouth Hot-CellStandard OperationTM1TaC#1TaC#1 Removal and inspectionNovember 15, 2011 removed TaC#1 from TM1
and inspected TM1 for any obivous signs of
trouble (Problems with EE at end of run).
  
  53   Wednesday, November 16, 2011, 07:46 chad fisherSouth Hot-CellStandard OperationTM1TaC#1Inspection of TaC#1Inspection of TaC#1 showed that the oven
was indeed broken on the A+ (left oven leg)
side of the central block.
  
  55   Thursday, November 17, 2011, 11:52 Travis CaveConditioning StationStandard OperationTM1no targetModule moveTM#1 moved from the conditioning station
to the south hot cell. Move went well.
  
  56   Friday, November 18, 2011, 09:44 Travis CaveSouth Hot-CellStandard OperationTM1UCx#3Electrical checkElectrical checks of TM#1 with UCx#3 have
been completed. They all appear to be with
in operational range. All megger checks were
 ITW_UC#3_Elec_check.PDF 
  57   Friday, November 18, 2011, 09:56 chad fisherSouth Hot-CellStandard OperationTM1UCx#3UCx#3 InstallationUCx#3 has been installed on TM1.
Leak check also complete.
Base Leak Rate 0.0 x 10-9
  
  58   Friday, November 18, 2011, 11:09 Travis CaveConditioning StationStandard OperationTM1UCx#3Module moveTM#1 with UCx#3 has been moved from the
south hot cell to the conditioning station.
Move went well.
  