  1218   Friday, April 29, 2016, 08:01 David WangConditioning StationMaintenanceTM2 TM2 leak check at TCS, helium pressure test

Anders and I finished the most part of TM2 water lines helium pressure test yesterday.I list the system parameters and test result as below:

TCS  IG1: 9.8XE-8 torr,  TCS IG2: 9.6Xe-7 torr, TCS IG1S: 3.5XE-9 torr, TCS CG1A: 10 m torr

Helium pressure: 70 psi. Test time: 5 minutes for each individual circuit.  1 hour for all  lines together test.

 Leak detector base leak rate:0.0 X E -9 atm.cc/sec, base pressure 0.0X E-4 torr. LD was always restored or closely restored to the bottom  scale after each individual test.

 

Circuit Result (atm.cc/sec)
EE 0.0X E-9
Target Oven + 0.0X E-9
Coil 1   P-Q 0.0X E-9
Target Oven - 1.0X E-9
Tube Heater- 4.1X E-9
Tube heater+ 1.6X E-8
Coil 2    R-U 6.6X E-9
MSP 1.4X E-7
All above together (1 hour) 2.3X E-7
HS Open circuit . No test
Window Open circuit.  No test.
GE  7.2X E-7

The HS and Window lines will be tested later with new target installed and  window line gaskets restored.

  1217   Thursday, April 28, 2016, 06:28 David WangConditioning StationMaintenanceTM2 TCS water system are turned off.

 TCS water system worked fine overnight. I turned off TCS water system at 6:16 AM this morning. Start of purging TM2 water lines for helium pressure test again this morning.

2016-4-28 7:58AM. Disconnected TM2 water lines at TCS. Purged them with compression air each for 5 minutes. 

  1216   Tuesday, April 26, 2016, 10:47 David WangConditioning StationRepairTM2 TM2 leak check at TCS, water test.

The following water circuits in TM2 are connected at TCS and running with water now : target oven+ - ( one circuit), tube heater+ -( one circuit), coil1 and 2(one circuit), MSP, and EE. The HS and window are open circuits now so they can not be supplied with water.  During the check before we knew HS and window circuit were close to perfectly sealed. So, The test result should not be affected without them

The TCS water pumps are started at 8:28 AM. All TCS high vacuum gauge readings are getting slight better after that.

  1215   Monday, April 25, 2016, 12:18 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 130 (Apr- Sep)

Post MS project and Excel    target hall schedule for beam schedule 130 see attachments 1,2

Update TH schedule 130 with TM3 jobs involved in.see attachments 4,5.

2016-04-29.  Weekly update schedule according to changes. See attachments 6,7.

Attachment 1: Target_Hall_shedule_130_Apr_to_Sep.pdf
Target_Hall_shedule_130_Apr_to_Sep.pdf
Attachment 2: Target_Hall_shedule_130_Apr_to_Sep_2016.pdf
Target_Hall_shedule_130_Apr_to_Sep_2016.pdf
Attachment 3: Target_Hall_shedule_130_Apr_to_Sep.mpp
Attachment 4: Target_Hall_shedule_130_Apr_to_Sep.pdf
Target_Hall_shedule_130_Apr_to_Sep.pdf
Attachment 5: Target_Hall_shedule_130_Apr_to_Sep.mpp
Attachment 6: Target_Hall_shedule_130_Apr_to_Sep.mpp
Attachment 7: Target_Hall_shedule_130_Apr_to_Sep.pdf
Target_Hall_shedule_130_Apr_to_Sep.pdf
  1214   Friday, April 22, 2016, 14:07 David WangConditioning StationStandard OperationTM2 2016 Winter Shut Down Target Hall Schedule

Weekly update.This is the last update on 2016 winter shut down schedule. The new TH schedule for beam130  will be posted weekly after this. All jobs in winter shut down schedule were finished on time.

 

Attachment 1: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf
Attachment 2: 2016_winter_shut_down__target_hall_schedule.mpp
  1213   Monday, April 18, 2016, 09:07 David WangConditioning StationRepairTM2 venting TCS with argon.

Anders reported a possible air leak on TM2 and TCS by watching RGA  this morning. I found the quick connector on F terminal on the top of the module is leaking air. It is only used as "X" terminal for Febiad without  water. So, it should be blind capped instead of installing a quick connector. It was installed with a  blind cap before. I borrowed it for leak check on coil lines at SHC, but forgot to put it back right away. Instead, I put a quick connector on it later. This caused the problem. Anyway The TCS need to be vented , and a blind cap  will be installed on the F terminal.

2014-04-18, 9:24AM, I changed the quick connector with a blind cap on F terminal. the rough pump is started now.

  1212   Thursday, April 14, 2016, 12:56 David WangITWStandard OperationTM1 5 shielding blocks have been moved to ITW.

The ITW is configured to take proton beam.

  1211   Thursday, April 14, 2016, 09:46 Anders MjosConditioning StationStandard OperationTM2 TM2 water leak test

 Thursday, April 14, 2016, 07:50: RGA on


Friday, April 15, 2016, 08:09 : Ratio between water and air is higher than normal (indicating possible air leak). See attachment. 3.5 more H2O than N2.  (Ratio in TM3 Nov 2015 was 82:1)


 

A leak was found on the o-ring between the module flange and TCS. This could be fixed by cleaning the o-ring and sealing surface. The Window line is not closed and was accidentally pressurized with He on April 25


Tuesday, April 26, 2016, 08:47: David started the water package.


Wednesday, April 27, 2016, 08:15: Switched off chiller / water cooling.

Wednesday, April 27, 2016, 14:41: Switched chiller / water cooling back on.

Attachment 1: 2016-04-15_RGA.png
2016-04-15_RGA.png
  1210   Wednesday, April 13, 2016, 10:46 David WangConditioning StationStandard OperationTM2 TM2 and TCS vacuum system has been connected.

TCS is under roughing now.

2016-04-14, Started TCS and TM2 turbo-pumps yesterday afternoon. Overnight pumping down is fine.

  1209   Wednesday, April 13, 2016, 10:46 David WangConditioning StationStandard OperationTM2 TM2 and TCS vacuum system has been connected.

TCS is under roughing now.

  1208   Wednesday, April 13, 2016, 10:14 Travis CaveConditioning StationStandard OperationTM2no targetmodule moved

TM#2 has been moved from the south west silo to the conditioning station.

  1207   Tuesday, April 12, 2016, 11:41 David WangITEStandard OperationTM4 TM4 has been connected in ITE.

Tm4 has been connected in ITE. The ITE and TM4 is under roughing now. ITE

Turbo-pumps have been started. Everything is fine.

  1206   Tuesday, April 12, 2016, 09:08 Travis CaveITEStandard OperationTM4Ta#47module moved

TM#4 with Ta#47 has been moved from the conditioning station to the east target station.

  1205   Monday, April 11, 2016, 13:44 David WangConditioning StationStandard OperationTM4 I stopped TCS and TM4 vacuum pumps.

The TM4 is still under vacuum at TCS. It will be vented tomorrow morning.

I disconnected TM4 vacuum system at TCS.

  1204   Monday, April 11, 2016, 10:07 Travis CaveSpent Target VaultStandard Operation UC#14Spent Target move

The spent UC#14 target has been moved into the ISAC spent target vault. See the attached PDF for the details.

Attachment 1: Vault_Storage_April_11_2016.pdf
Vault_Storage_April_11_2016.pdf Vault_Storage_April_11_2016.pdf Vault_Storage_April_11_2016.pdf Vault_Storage_April_11_2016.pdf
  1203   Monday, April 11, 2016, 09:42 David WangConditioning StationStandard OperationTM4 Helium pressure test on TM4 HS line at CS with new Lp Ta target

70 psi helium , 2 minutes. Base leak rate 0.0x E-9 atm.cc/sec. base pressure 0.0XE-4 torr. no response on LD.The line is good.

  1202   Friday, April 08, 2016, 13:16 David WangConditioning StationStandard Operation  2016 Winter Shut Down Target Hall Schedule

Update schedule weekly .see attachment 1,2

Attachment 1: 2016_winter_shut_down__target_hall_schedule.mpp
Attachment 2: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf
  1201   Friday, April 08, 2016, 08:48 David WangITWStandard Operation  ITW water signal interlock check.

I did a ITW water signals interlock check with ISAC opp. They are checked once a year before first beam on.

2016-04-13 Same test is done on ITE also. Everything is good.

  1200   Friday, April 08, 2016, 08:13 Anders MjosITE/ITW CoolingMaintenance  High Active Water Resistivity

The high active water resistivity took a long time to recover after the upgrade to the water cooling circuit. The system needed about a month (from end February to end March) to recover to nominal values. See attached plot of archiver data.

TM1 has now been connected in ITW and the water resistivity remains > 8 MOhm cm, which should allow normal operation. However, the resin is suspected to be approaching end of life. Work is ongoing to get a new replacement resin tank.

Attachment 1: 2016-04-08_ISAC_High_Active_Water_Resistivity.png
2016-04-08_ISAC_High_Active_Water_Resistivity.png
  1199   Friday, April 08, 2016, 07:13 David WangITWStandard OperationTM1UCx15TM1 has been connected in ITW.

After ITW HV test is done, TM1 has been connected to ITW. Water signals are checked in electrical room. They are good.