1016
|
Monday, July 27, 2015, 15:34 |
David Wang | ITE | Standard Operation | TM4 | | Leak check on TM4 HS water line with new UCX target. at SHC |
Chad and I leak checked the HS line at SHC after UCX target installation. On first round helium spray, one of VCR fitting has a leak to E-6 atm.cc/sec range. Chad tightened the fitting, and solved the problem. We leak checked both VCR fittings twice. No leak. The line will be helium pressured at CS tomorrow. |
1017
|
Monday, July 27, 2015, 15:46 |
David Wang | South Hot-Cell | Standard Operation | | | The yellow steel plug is put on SHC in TH |
The yellow steel plug is put on SHC in TH. The spent target is inside the SHC.The field around the SHC area in TH is so high that we have put it on. It will be moved out on this Thursday just before the spent target move. |
1018
|
Monday, July 27, 2015, 17:03 |
David Wang | Conditioning Station | Standard Operation | TM4 | UCx 13 | UCx13 and TM4 under vacuum at CS. |
I connected the CS vacuum system to TM4. The CS and TM4 turbo pumps are started. Everything is good so far. The HS line will be pressured with helium tomorrow for leak checking. The CS and TM4 will be vented with Argon on Wednesday morning as planned before moved to ITE. |
1019
|
Tuesday, July 28, 2015, 10:12 |
David Wang | Conditioning Station | Standard Operation | TM4 | UCx 13 | Helium pressure test on TM4 HS line at CS |
I did the helium pressure test on TM4 HS line at CS. Applied 70 psi helium 2 minutes. base leak rate0.0x E-9 atm.cc/sec. No response during the test. No leak. |
1020
|
Tuesday, July 28, 2015, 10:17 |
David Wang | ITE | Repair | | | ITE TP4 has been replaced |
Tony and I replaced the ITE TP4 turbo pump today. The pumping time on controller has been reset to 0. The replaced broken pump is bagged and stored at west end of TH. |
1024
|
Wednesday, July 29, 2015, 06:24 |
David Wang | Conditioning Station | Standard Operation | TM4 | UCx 13 | Stopped the CS and TM4 pumps and vent with argon. |
Dan and I stopped the CS and TM4 pumps. We are venting the CS with argon for UCX13 target. |
1026
|
Wednesday, July 29, 2015, 10:14 |
David Wang | ITE | Standard Operation | TM4 | | TM4 has been connected in ITE |
Dan and I connected TM4 in ITE. We checked all water signals on ITE cooling circuits. Everything is good. |
1028
|
Friday, July 31, 2015, 09:47 |
David Wang | ITE | Standard Operation | | | Target Hall Scheduled Activities April 07 - August 019 2015 |
Weekly update of Target Hall schedule after so many jobs have been finished in this week. See attachment 1, 2 |
1031
|
Friday, August 07, 2015, 10:01 |
David Wang | ITE | Standard Operation | | | Target Hall Scheduled Activities April 07 - August 19 2015 |
Weekly update target hall schedule and activities. See attachment 1,2
Update and extend Target Hall schedule to Sep 08. See attachment 3,4 |
1037
|
Thursday, August 13, 2015, 17:17 |
David Wang | Conditioning Station | Repair | TM2 | Dummy target | TM2 at CS |
TM2 has been moved to CS. All turbo-pumps have been started. The pumping down is good so far. I connected the leak detector to service cap, and finished the leak check today. The LD base LR:0.0Xe-9atm.cc/sec. 80psi helium were applied to coil1, coil 2. HS and window circuits, each for 2minutes. No any response has been found on LD. So all water lines are leak tight now. I also sprayed helium to top service cap checking all air to vacuum seals. They are all good either. But, The new installed PGN1 does not work. Other thing need to mention is The TP2 is running at 2.45A which is 1A higher comparing to TP1. It need to be monitored to see if we have to replace it or not. The high current cables and water lines will be connected tomorrow morning. |
1038
|
Friday, August 14, 2015, 10:00 |
David Wang | Conditioning Station | Repair | TM2 | | Started CS water package for TM2 |
I finished the rest TM2 connections to CS, and started CS cooling package. Everything works fine so far. |
1040
|
Wednesday, August 19, 2015, 14:52 |
David Wang | Conditioning Station | Repair | TM2 | | TM2 at CS |
During the TM2 HV test at CS, It failed. In order to confirm there is no any water leak inside the module after the heaters and beam extraction test, I disconnected all the water lines on the TM2, and purged the water lines with pressure air. Leak detector was reconnected back to the TM2 service cap, and all water lines are pressurized with 80psi helium again each for 2 minutes.No any leak had been found during the test. All the water lines are still perfectly sealed. Also, I checked all the vacuum to air seals on the top of the module.They are good either. Anders used the RGA tracking the helium during the test. No leak. |
1041
|
Thursday, August 20, 2015, 09:38 |
David Wang | Conditioning Station | Repair | TM2 | | TM2 was disconnected at CS |
TM2 was disconnected at CS. Travis and I did electrical check before the venting. After,The module was vented and moved to SHC. The moving is smooth. |
1044
|
Thursday, August 20, 2015, 13:48 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Target Hall Scheduled Activities April 07 - Sep 08 2015 |
Weekly update target hall schedule.See attachment 1,2
Spring and summer run is close to the end. This will be the last update on this old schedule. See attachment3,4. A new schedule for TH activities after mini shut down will be posted next time. |
1051
|
Wednesday, August 26, 2015, 14:28 |
David Wang | Conditioning Station | Standard Operation | TM2 | ZrC | Leak check on TM2 HS and windowwater line with new ZrC target at SHC |
Chad and I leak checked TM2 HS and window circuit VCR joints with ZrC target and containment box installed at SHC. No leak has been found. They will be helium pressurized at CS later. |
1052
|
Wednesday, August 26, 2015, 14:30 |
David Wang | Conditioning Station | Standard Operation | TM2 | ZrC | TM2 and Cs vacuum sysyem has been connected at CS. |
Turbo-pumps are started . The pumping down is good so far. |
1053
|
Wednesday, August 26, 2015, 14:52 |
David Wang | Conditioning Station | Standard Operation | TM2 | ZrC | Helium pressure test on TM2 HS and window lines at CS |
LD base LR 0.0xE-9 atm.cc/sec , 80 psi helium 2 minutes on HS and window circuits. No leak. Also, the reinstalled(after rewiring job) TP2 and PNG1(steers) side panel have been leak checked. No leak. |
1056
|
Tuesday, September 01, 2015, 06:25 |
David Wang | Conditioning Station | Standard Operation | TM2 | ZrC | Argon venting TM2 at CS |
Argon venting TM2 at CS. |
1058
|
Tuesday, September 01, 2015, 10:38 |
David Wang | ITW | Maintenance | TM2 | | ITW top tank flange clean up and r-ring replacement. |
During last run, ITW dump circuit had a water leak on an adaptor below the pressure gauge. The top tank flange, slot, and O-ring were water contaminated by the leak. I removed the old o- ring, cleaned up the flange and o-ring slot, and put a new o-ring into the flange. Some pictures will be attached in this mail later. |
1059
|
Tuesday, September 01, 2015, 14:54 |
David Wang | ITW | Standard Operation | TM2 | | TM2 has been connectec in ITW. |
TM2 has been connected in ITW. During the connection, Anders and I found the TM2 high current cables used in ITE and CS are short in ITW. Anders and Grant found the original TM2 ITE high current cables in target hall. We replaced them. They works fine. But, a little bit longer on cable length would be easy to connect them. All other connections and HV cover in ITW work for the TM2 so far. |