1233
|
Monday, May 16, 2016, 10:48 |
Anders Mjos | Conditioning Station | Maintenance | | | Topped up water in TCS:TK2 | Filled from 15 to 25 in |
|
|
1232
|
Friday, May 13, 2016, 10:12 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 water lines, heaters, EE, and EL are connected at TCS. | The HV cover is installed on to TM2
after the connections. The HV key is returned
back to B2 level. The TCS Faraday cage is |
|
|
1231
|
Friday, May 13, 2016, 10:08 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Helium pressure test on TM2 HS and window line at CS with new Lp Ta target | These two lines are passed helium pressure
test this morning. The LD base leak rate
0.0 X E-9 atm.cc/sec. The base pressure 0.0 |
|
|
1230
|
Wednesday, May 11, 2016, 13:16 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 and TCS vacuum system has been connected. | TM2 and TCS vacuum system has been connected.
I started all turbo pumps. Everything is
good so far. |
|
|
1229
|
Wednesday, May 11, 2016, 13:15 |
David Wang | Conditioning Station | Maintenance | TM2 | | TCS tank top flange seal is changed this morning | I changed TCS tank top flange seal(o-ring
42.00"ID X 0.275" DIA) this morning
before TM2 was moved to TCS. |
|
|
1228
|
Wednesday, May 11, 2016, 09:44 |
Travis Cave | Conditioning Station | Standard Operation | TM2 | Ta#48 | module moved | TM#2 with Ta#48 has been moved from the
south hot cell to the conditioning station. |
|
|
1227
|
Tuesday, May 10, 2016, 14:27 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | Ta#48 | Electrical Check | Electrical check of TM#2 with Ta#48 attached.
See the attached PDF for details. |
|
|
1226
|
Tuesday, May 10, 2016, 13:54 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | SHC, TM2 leak check on window line and HS line. | Chad and I leak checked the TM2 HS and
window lines after new target installation.
The window line was very easy pumped down |
|
|
1225
|
Tuesday, May 10, 2016, 13:37 |
chad fisher | South Hot-Cell | Standard Operation | TM2 | Ta#48 | Ta#48 Installation | Ta#48 has been installed onto TM2. Also
new window gaskets were installed.
High current fasteners were torqued |
|
|
1224
|
Monday, May 09, 2016, 10:13 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | no target | module moved | TM#3 was moved from the conditioning station
to the NE Silo. TM#2 was moved from the SW
Silo to the South hot cell. |
|
|
1223
|
Monday, May 09, 2016, 08:43 |
David Wang | Conditioning Station | Repair | TM3 | | I reinstalled all the side panel on TM3 service cap. | They were moved for TM3 inspection job
last week. All the bolts on the panel are
hand tight only now since they will be removed |
|
|
1222
|
Wednesday, May 04, 2016, 12:01 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule for beam schedule 130 (Apr- Sep) | Update schedule weekly. See attachment
1,2,3. |
|
|
1221
|
Wednesday, May 04, 2016, 11:14 |
Isaac Earle | North Hot-Cell | Development | | | North Hot Cell Scope Decision | A meeting was held on May 4, 2016 to determine
the scope of the North Hot Cell project.
The following was agreed upon by those |
|
|
1220
|
Monday, May 02, 2016, 11:33 |
Travis Cave | Conditioning Station | Standard Operation | TM2 | no target | module moved | TM#2 was moved to the SW Silo from the
Conditioning Station. TM#3 was from from
the NW Silo to the Conditioning Station. |
|
|
1219
|
Friday, April 29, 2016, 10:06 |
David Wang | Conditioning Station | Standard Operation | TM2 | | I switched off TCS and TM2 vacuum pumps. | I switched off TCS and TM2 vacuum
pumps. The TM2 will be disconnected at TCS
today and moved to silo on next Monday. |
|
|
1218
|
Friday, April 29, 2016, 08:01 |
David Wang | Conditioning Station | Maintenance | TM2 | | TM2 leak check at TCS, helium pressure test | Anders and I finished the most part of
TM2 water lines helium pressure test yesterday.I
list the system parameters and test result |
|
|
1217
|
Thursday, April 28, 2016, 06:28 |
David Wang | Conditioning Station | Maintenance | TM2 | | TCS water system are turned off. | TCS water system worked fine overnight.
I turned off TCS water system at 6:16 AM
this morning. Start of purging TM2 water |
|
|
1216
|
Tuesday, April 26, 2016, 10:47 |
David Wang | Conditioning Station | Repair | TM2 | | TM2 leak check at TCS, water test. | The following water circuits in TM2 are
connected at TCS and running with water
now : target oven+ - ( one circuit), tube |
|
|
1215
|
Monday, April 25, 2016, 12:18 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule for beam schedule 130 (Apr- Sep) | Post MS project and Excel
target hall schedule for beam schedule 130
see attachments 1,2 |
7x |
|
1214
|
Friday, April 22, 2016, 14:07 |
David Wang | Conditioning Station | Standard Operation | TM2 | | 2016 Winter Shut Down Target Hall Schedule | Weekly update.This is the last update on
2016 winter shut down schedule. The new TH
schedule for beam130 will be posted |
|