  1902   Thursday, March 28, 2019, 12:48 Anders MjosConditioning StationRepairTM2dummy febiad test targetTM2 new source tray helium pressure test at TCS.

David Wang wrote:

Helium pressure test on TM2 all water circuits is done. 70 psi helium , 10 minutes test time. Leak detector :base leak rate 0.0XE-9 atm.cc/sec, base pressure 0.0Xe-4torr. No any response on LD during the test. All TM2 water circuit are leak free.

 Thursday, March 28, 2019, 12:40: Found valve to expansion tank TCS:TK2 to be closed. Opened valve. This allow air to escape out of the system and the water system is running as expected again


Friday, March 29, 2019, 11:15: Changed EE to conditioning mode

Friday, March 29, 2019, 11:35: BIAS / EZL 20 / 10 kV

Friday, March 29, 2019, 13:47: BIAS / EZL: 25 / 12.5 kV

Friday, March 29, 2019, 16:09: BIAS / EZL: 30  / 15 kV

Friday, March 29, 2019, 17:23: No sparks for >60 min

Friday, March 29, 2019, 17:26: BIAS / EZL off


Monday, April 01, 2019, 08:13: BIAS / EZL: 30  / 15 kV

Monday, April 01, 2019, 08:33 BIAS / EZL: 35  / 17.5 kV

Monday, April 01, 2019, 09:00: Sparking at about 37.5 kV BIAS. Lowered below 20 kV to stop. Now sparking at around 20 kV

Monday, April 01, 2019, 10:00: BIAS/EZL 22 / 20 kV. Occasional sparking on BIAS as voltage is increased.

Monday, April 01, 2019, 10:05: Change of strategy. Will heat target to bake out the vacuum before continuing with HV conditioning.

Monday, April 01, 2019, 10:43:

BIAS / EZL / EE: 15 / 7.5 / 1.5 kV
COIL / ANODE: 10 A / 200 V
Ramping TGHT / TBHT at 1 A/min. Good/bad vacuum (IG2): 1E-6 / 2E-6 Torr

Monday, April 01, 2019, 19:16: TGHT / TBHT: 500 / 270 A. Vacuum increasing. IG1/2 1.2E-7 / 1.4E-6 Torr


Monday, April 08, 2019, 09:28: BIAS / EZL: 20 / 10 kV (some periods of multiple sparks)

Monday, April 08, 2019, 10:28: BIAS / EZL: 30 / 15 kV (some periods of multiple sparks)

Monday, April 08, 2019, 11:24: 3 sparks for the last 60 min

Monday, April 08, 2019, 14:43: BIAS / EZ: 40 / 20 kV (after two periods of sparking around 39 kV requiring voltage to be reduced below 30 kV to recover)

Monday, April 08, 2019, 15:57: Two sparks in 70 min


Tuesday, April 09, 2019, 12:40: BIAS / EZL 40 / 20 kV with >90 min without sparking

Tuesday, April 09, 2019, 16:00: BIAS / EZL 48 / 24 kV

Tuesday, April 09, 2019, 16:07: Sparking tripped TPs and IG1S, then power supplies.


Tuesday, April 16, 2019, 16:41: BIAS / EZL 50 / 25 kV for 1 hour without sparking.


Wednesday, April 17, 2019, 15:23 : Continued without problems to 50 kV earlier, but sparks tripped off vacuum just above 50kV. Continue later.

  1922   Thursday, May 16, 2019, 12:31 chad fisherSouth Hot-CellStandard OperationTM2Ta#58Ta #58 installed

Ta #58 has been installed onto TM2. All new silver plated high current fasteners. All torqued to 130 in lbs.

  1923   Thursday, May 16, 2019, 14:35 Travis CaveSouth Hot-CellStandard OperationTM2Ta#58Electrical Check

 Results of the electrical check of TM#2 without target and with the new Ta#58 target.

Attachment 1: Ta#58_TM2_SHC_electrical_chk_May_16_2019.pdf
Ta#58_TM2_SHC_electrical_chk_May_16_2019.pdf
Attachment 2: Electrical_Chk_TM2_no_target_May_15_2019_SHC.pdf
Electrical_Chk_TM2_no_target_May_15_2019_SHC.pdf
  1924   Friday, May 17, 2019, 10:47 Travis CaveITEStandard OperationTM2Ta#58Module move

 TM#2 with Ta#58 has been moved from the south hot cell to the east target station.

  1932   Tuesday, June 04, 2019, 08:46 David WangITEStandard OperationTM2 ITE water signal interlock check.

ITE water signal interlock check is done. Everything is good. Coil 2   circuit no longer used in ITE . PQRU are looped as one circuit fro coil 1 circuit on Module since now.

  1943   Friday, June 14, 2019, 08:15 David WangITEStandard OperationTM2 5 shielding blocks are moved to ITE.

ITE is configured to take proton beam.

  1959   Thursday, August 08, 2019, 09:33 Carla BabcockITEDevelopmentTM2Ta#58TM2 HV conditioning with protons, round 1

Starting HV tests on TM2 with 50uA of protons.

Tuesday, August 06, 2019, 03:37 : Ramping up 500V every 2mins or so, couple of sparks, then consistent sparks at 34kV. No vacuum response on IG1 for any sparks, even though the current spikes from around 40uA to 1300uA. Brought it down to 28kV to stop sparking. See a response on the EZL frequently.

Tuesday, August 06, 2019, 05:24 : Going above 30kV proves very difficult, lots of up and down, frequent sparks, still no vacuum response. Still seeing an EZL response.

Tuesday, August 06, 2019, 05:58 : Up to 31.5kV on bias, 1046V on EE and 15kV on EZL.

Tuesday, August 06, 2019, 06:50 : Controls are being sticky - not responding well.

Tuesday, August 06, 2019, 07:25 : Sat at 32 kV > 20mins with 2 sparks

Tuesday, August 06, 2019, 08:03 : lots of sparking at 36kV, went back down to 35kV. Current draw is 50uA.

Tuesday, August 06, 2019, 08:10 : lots of sparking after 9 mins at 35kV, had to turn it down to 34kV

Tuesday, August 06, 2019, 08:11 : Still sparking at 34, down to 33

Tuesday, August 06, 2019, 08:31 : At 33kV, sparked twice in 20mins and was going for another when the protons went off.

With protons off, the bias current dropped quickly from 66uA to 40uA and raising the bias to 40kV was not difficult.  Later bias up to 50kV. Still no conclusion on if the sparking was inside or outside of the vacuum. No vacuum response seems to indicate outside, however the influence of protons would indicate inside. To be investigated visually when TM2 comes to the HC.

  1960   Tuesday, August 13, 2019, 09:49 Adam NewsomeSouth Hot-CellStandard OperationTM2Ta 58TM2 Move

TM2 was moved from ITE to South Hot Cell. Tantalum 58 target.

  1961   Wednesday, August 14, 2019, 08:55 David WangITEStandard OperationTM2 TM2 has been disconnected in ITE.

TM2 has been disconnected in ITE. The bias jumper between U and T was burned out during the last beam time.

  1962   Wednesday, August 14, 2019, 11:43 Travis CaveSouth Hot-CellStandard OperationTM2Ta#58 and no target.Results of electrical checks post beam at the south hot cell.

 Here are the results of the electrical done at the south hot cell post beam of with the Ta#58 target attached and with just the module no target attached.

Attachment 1: TM2_elec_chk_Ta58_post_beam_shc.pdf
TM2_elec_chk_Ta58_post_beam_shc.pdf
Attachment 2: TM2_Elec_chk_no_tgt_shc_Aug-14-2019.pdf
TM2_Elec_chk_no_tgt_shc_Aug-14-2019.pdf
  1963   Thursday, August 15, 2019, 09:36 Adam NewsomeITEStandard OperationTM2ZrC #8TM2 Move

TM2 was moved from South Hot Cell to ITE. ZrC #8 target.

  1964   Thursday, August 15, 2019, 09:45 Travis CaveSouth Hot-CellStandard OperationTM2ZrC#8Electrical Check

 Electrical of TM#2 with ZrC#8 at the south hot cell. See attached for details.

Attachment 1: TM2_elec_chk_with_ZrC8_at_SHC_Aug_17_2019.pdf
TM2_elec_chk_with_ZrC8_at_SHC_Aug_17_2019.pdf
  1968   Friday, August 16, 2019, 14:23 Carla BabcockITERepairTM2ZrC#8TM2 electrical checks in ITE

Ramped voltage on TM2 up to 30kV with no problems. Bias current is at 29uA, same as original TM2 bias current (see archiver for ITE June 15th, before protons) and similar to 31uA right after protons went off on Aug. 6.

TGHT=0A

TBHT=0A

BIAS V=30kV

BIAS current = 29uA

EZL V= 15kV

EZL current= 51uA

EE V= 1kV

EE current= 0.952mA

IG1= 8.6e-7

protons=0

This seems ok despite poor electrical checks showing 300 MOhm resistance between HV and ground. These values indicate a resistance of 1 GOhm. Let's see what happens when protons are on.

For future (optimistic) reference when testing protons:

BIAS=35kV, 35uA

EZL-17.5kV, 60uA

BIAS=38kV, 37uA

EZL=18.5kV, 63uA

  1986   Tuesday, September 17, 2019, 07:37 Carla BabcockITEDevelopmentTM2ZrC#8end of run HV investigations

Ramping up HV to ~30kV, encountered problems and had to drop back to 28kV. No response on IG1 or anything else during sparks. Lots of charging-type behaviour on the bias current. Protons at 55uA

Tuesday, September 17, 2019, 02:02 : 15 mins with only 1 spark at 30kV so increased the bias

Tuesday, September 17, 2019, 02:31 : 32kV. Current unstable

Tuesday, September 17, 2019, 02:41 : Current continues extremely unstable but not much sparking....

Tuesday, September 17, 2019, 02:53 : Proton beam trip initially settled the bias current down, but then current began climbing pretty steeply with protons still off

Tuesday, September 17, 2019, 03:28 : Protons dropped to 40uA from 55uA, Bias current is much more stable and no sparks for 25mins

Tuesday, September 17, 2019, 03:36 : Raising voltage easy to about 33.5kV then instability and sparking similar to around 31kV at 55uA p+

Tuesday, September 17, 2019, 04:45 : Lowered protons to 25uA and no sparks though the current is not stable

More things but forgot to write them down. Spreadsheet attached.

Attachment 1: HVtests_TM2_Sept172019.xlsx
  1991   Monday, September 30, 2019, 11:36 Travis CaveSouth Hot-CellStandard OperationTM2ZrC#8Module move

 TM#2 with ZrC#8 has been moved from the east station to the south hot cell.

  1992   Monday, September 30, 2019, 14:05 Travis CaveSouth Hot-CellStandard OperationTM2ZrC#8Electrical Check

 Results of the electrical check on TM#2 with ZrC#8 post beam.

Attachment 1: TM2_elec_chk_ZrC8_post_beam_SHC_09-30-2019.pdf
TM2_elec_chk_ZrC8_post_beam_SHC_09-30-2019.pdf
  1993   Tuesday, October 01, 2019, 09:23 Don JacksonITEMaintenanceTM2ZrC #860KV Common Connections

1 Jumpers between 60KV common and FEBIAD lines were connected in an unusual way.  This should of had no impact on the ZrC run but would have to be corrected for any future FEBIAD runs.

2 Feedthrough U was mislabeled (label has been removed)

 

Attachment 1: TM2_Wiring.jpg
TM2_Wiring.jpg
  1994   Tuesday, October 01, 2019, 10:22 chad fisherSouth Hot-CellStandard OperationTM2ZrC#8ZrC#8 Removed Ta#59 installed

ZrC#8 has been removed from TM2. Upon removal of the high current tube heater bolts it was noticed that the tube was broken. Also the 9 pin connector has an arc mark (see pictures attached).

Ta#59 has been installed with new fasteners. High current fasteners torqued to 130 in lbs.

Attachment 1: 20190930_140918[1].jpg
20190930_140918[1].jpg
  1995   Tuesday, October 01, 2019, 14:38 Travis CaveSouth Hot-CellStandard OperationTM2Ta#59Electrical Check

 The results of the electrical check on TM#2 with the Ta#59 target and without before the target was mounted on the module.

Attachment 1: TM2_no_target_SHC_elec_chk_Oct-1-2019.pdf
TM2_no_target_SHC_elec_chk_Oct-1-2019.pdf
Attachment 2: TM2_Ta59_SHC_elec_chk_Oct-1-2019.pdf
TM2_Ta59_SHC_elec_chk_Oct-1-2019.pdf
  1996   Tuesday, October 01, 2019, 16:30 Anders MjosConditioning StationStandard OperationTM2Ta#58Conditioning of Ta#58

Tuesday, October 01, 2019, 15:15: Started roughing.

Tuesday, October 01, 2019, 16:30: Started TPs

Tuesday, October 01, 2019, 16:34: All TPs at speed


Conditioning completed over the weekend by RIB operations. The shutter was left closed on the module, so no beam could be seen on the FC. Conditioning otherwise OK.