Entry  Thursday, March 07, 2019, 12:20, chad fisher, South Hot-Cell, Repair, TM2, , Pre-polishing pictures 
Pictures of the water blocks before polishing can be found on docushare, collection 24400
Entry  Thursday, March 07, 2019, 13:59, chad fisher, South Hot-Cell, Repair, TM2, , Polishing 
Polishing of the water block sealing surfaces has commenced. First attempt was on block B with low nap brown polishing pad (the least aggressive pad
prepared) and isopropyl for 30 seconds. This cleaned a little but did not remove the "ring" which I believe is water scale. I will step up to
2000 grit wet sand paper and iso next.
Entry  Friday, March 08, 2019, 14:10, chad fisher, South Hot-Cell, Repair, TM2, , Water block polishing B_after_SB_(2).jpg
After trials with 2000 grid wet paper I have moved up to "red" scotch brite. This seems to have worked the best so far although it took two
minutes to remove the ring that the other materials could not remove (see picture).
I have moved to next circuit. Currently at 3 minutes and 30 seconds with scotch brite but significant ring remains.
Entry  Monday, March 11, 2019, 14:34, chad fisher, South Hot-Cell, Repair, TM2, , Water Block Polishing status 
Stage 1 polishing (water scale and at least 99% of visual indium removed) has been achieved on all 2 seal water blocks that will be used (Ground electrode
has not been polished). Process required 3-4 3minute cycles of the tool using scotch brite pads with the tool running at approximately 75 psi.
Entry  Tuesday, March 12, 2019, 09:13, chad fisher, South Hot-Cell, Repair, TM2, , Water Block Polishing status Blocks_Stage_1_Polish.jpg
Stage 1 polish has been achieved on all single seal water blocks using the single pad tool run at 75 psi, 2 3 minute cycles per block using red scotch
brite.
Entry  Thursday, March 14, 2019, 10:25, chad fisher, South Hot-Cell, Repair, TM2, , Water Block Polishing status Blocks_final_polished.jpg
Phase 2 (intermediate) and Phase 3 (Final) polishing is complete on all water blocks on TM2 (minus ground electrode circuit which has only had a cursory
cleaning). Phase 2 with 2000 grit wet sand paper and isopropynol for 1 minute with tool at 75 psi, Phase 3 with Veltex polishing cloth for 1 minute with
tool at 75 psi.
Entry  Friday, March 15, 2019, 08:51, Travis Cave, Conditioning Station, Standard Operation, TM2, no target, Module move 
 TM#2 has been moved from the south hot cell to the conditioning station.
Entry  Monday, March 18, 2019, 07:23, David Wang, Conditioning Station, Repair, TM2, , TM2 window line helium test 
New seals with a blank off cap are installed on TM2 window line water block.   The seals are checked at TCS with 70 psi helium for 5 minutes
with LD at 0.0xE-9atm/cc.sec. No response on LD during test. Seals are good. 
Entry  Wednesday, March 20, 2019, 11:19, Travis Cave, South Hot-Cell, Standard Operation, TM2, no target, Module move 
 TM#2 has been moved from the conditioning station to the south hot cell.
Entry  Thursday, March 21, 2019, 09:56, chad fisher, South Hot-Cell, Repair, TM2, , Tray insertion 20190321_091833.jpg20190321_094625.jpg
This morning new water block fasteners and gas line capture nut fasteners were inserted into the hot cell. Window waterline blank off was removed from
TM2, surfaces inspected and given a polish with Veltex (30 seconds, 70 psi) as there was a small bit of c seal residue. Transfer try with new source tray
has been latched to the module.
Entry  Monday, March 25, 2019, 10:11, Aaron Schmidt, South Hot-Cell, Repair, TM2, , LP-FEBIAD Test Target (empty)  TM2_-_FEBIAD_target_-_Electrical_Test.pdf
Link to previous target information: https://elog.triumf.ca/TIS/RH-ISAC/1039

Monday, March 25, 2019, 10:00: Target electrical checks (See Attachment 1)
Entry  Tuesday, March 26, 2019, 09:32, Travis Cave, Conditioning Station, Standard Operation, TM2, Dummy Target, Module move 
 TM#2 with a new source tray and the dummy target has been moved from the south hot cell to the conditioning station.
Entry  Tuesday, March 26, 2019, 11:10, Travis Cave, Conditioning Station, Standard Operation, TM2, Dummy Target, Electrical Check Electrical_Check_TM2_Dummy__Target_CS_Mar-26-2019.pdf
 Electrical Check of TM#2 with the dummy target attached.
Entry  Tuesday, March 26, 2019, 11:17, Travis Cave, South Hot-Cell, Standard Operation, TM2, no target, Electrical Checks of TM#2 during the source tray change. Elecrictal_Check_TM#2_Old_source_Tray_Jan_11_2019.pdfElectrical_Check_TM#2_No_Source_Tray_Feb_25_2019.pdfElectrical_Check_TM#_New_source_Tray_Mar_22_2019.pdfElectrical_Check_TM#2_new_source_tray_Mar_25_2019.pdf
 The four electrical check done on TM#2 during the source tray change.
Entry  Thursday, March 28, 2019, 10:27, David Wang, Conditioning Station, Repair, TM2, dummy febiad test target, TM2 new source tray helium pressure test at TCS. 
Helium pressure test on TM2 all water circuits is done. 70 psi helium , 10 minutes test time. Leak detector :base leak rate 0.0XE-9 atm.cc/sec, base
pressure 0.0Xe-4torr. No any response on LD during the test. All TM2 water circuit are leak free. 
    Reply  Thursday, March 28, 2019, 12:48, Anders Mjos, Conditioning Station, Repair, TM2, dummy febiad test target, TM2 new source tray helium pressure test at TCS. 


    
        
            David Wang wrote:
        
        
            
            Helium pressure test on TM2 all water circuits is done. 70 psi helium , 10 minutes test time. Leak detector
Entry  Thursday, May 16, 2019, 12:31, chad fisher, South Hot-Cell, Standard Operation, TM2, Ta#58, Ta #58 installed 
Ta #58 has been installed onto TM2. All new silver plated high current fasteners. All torqued to 130 in lbs.
Entry  Thursday, May 16, 2019, 14:35, Travis Cave, South Hot-Cell, Standard Operation, TM2, Ta#58, Electrical Check Ta#58_TM2_SHC_electrical_chk_May_16_2019.pdfElectrical_Chk_TM2_no_target_May_15_2019_SHC.pdf
 Results of the electrical check of TM#2 without target and with the new Ta#58 target.
Entry  Friday, May 17, 2019, 10:47, Travis Cave, ITE, Standard Operation, TM2, Ta#58, Module move 
 TM#2 with Ta#58 has been moved from the south hot cell to the east target station.
Entry  Tuesday, June 04, 2019, 08:46, David Wang, ITE, Standard Operation, TM2, , ITE water signal interlock check. 
ITE water signal interlock check is done. Everything is good. Coil 2   circuit no longer used in ITE . PQRU are looped as one circuit fro coil 1
circuit on Module since now. 