149
|
Wednesday, July 18, 2012, 16:49 |
Grant Minor | South Hot-Cell | Development | | | South Hot Cell Ventilation Alarm Trip | Today (Wednesday July 18th) at around 4:15
pm I was taking a small tour group from
VECC into the Target Hall. In the process |
|
150
|
Thursday, July 26, 2012, 08:33 |
David Wang | ITE | Standard Operation | TM4 | | I moved 5 shielding blocks from ITW to ITE thisTuesday morning . | All water interlock checks for ITE
had been done. The ITE water signals strength
and frequency(Espcially on MSP circuit) had |
|
159
|
Tuesday, August 07, 2012, 14:06 |
David Wang | ITW | Repair | | | ITW TP4S has been replaced |
Normal
0
|
|
163
|
Monday, August 20, 2012, 12:28 |
David Wang | ITW | Standard Operation | TM1 | | I moved 5 shielding blocks from ITE to ITW, | I moved 5 shielding blocks from ITE
to ITW.ITW is configured to take proton beam
now. |
|
164
|
Thursday, August 23, 2012, 07:34 |
David Wang | ITW | Repair | | | Replaced broken air lines on ITW HARP5B cylinder. | Prob guys replaced broken air lines on
ITW HARP 5B Cylinder.Several shielding blocks
had been moved out to make the cylinder accessible. |
|
165
|
Thursday, August 30, 2012, 13:57 |
David Wang | ITE | Standard Operation | TM4 | | Disconnected TM4 in ITE. | I disconnected TM 4 in ITE on AUG 29th
morning.The vacuum lines stay untouched and
they will be disconnected on SEP 04th. |
|
166
|
Friday, August 31, 2012, 12:10 |
chad fisher | South Hot-Cell | Maintenance | | | Hot Cell Maitenance | Entered south hot cell Wednesday and replaced
the pre-filter air filter as well as the
front two light bulbs. Also removed two bags |
|
189
|
Thursday, September 27, 2012, 09:13 |
David Wang | ITE | Repair | TM4 | | ITE MSP water circuit flow wheel had been replaced | ITE MSP water circuit flow wheel was replaced
yesterday due to poor performance. |
|
191
|
Thursday, October 04, 2012, 11:06 |
David Wang | Conditioning Station | Repair | | | Replace conditioning station scroll pump in target hall | Grant and I replaced the conditioning station
broken srcoll pump with a refurbished
scroll pump which is supplied by vacuum group. |
|
199
|
Wednesday, October 31, 2012, 11:24 |
David Wang | ITE | Standard Operation | TM4 | | Transfer five shielding blocks from ITW to ITE. | Bevan and I transferred five shielding
blocks from ITW to ITE. ITE is ready for
taking proton beam. |
|
200
|
Friday, November 02, 2012, 08:45 |
maicodallavalle | Spent Target Vault | Maintenance | | | F-308 | The F-308 have been cleaned and serviced.
There were three F-308's that came back with
some contamination.#13, #15 and #19 were |
|
201
|
Friday, November 02, 2012, 13:18 |
Travis Cave | Spent Target Vault | Standard Operation | | | spent target assay | This week six targets and the two source
trays were assayed and surveyed from the
storage vault. see attached PDF for details. |
|
203
|
Tuesday, November 06, 2012, 11:34 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | | Nb#7 Removal | Attached are pre-removal pictures of NB#7
and the inside face of the containment box
cover before cleaning. |
![IMG_0797[1].JPG IMG_0797[1].JPG](attachment.png) ![IMG_0798[1].JPG IMG_0798[1].JPG](attachment.png) |
214
|
Wednesday, November 14, 2012, 10:57 |
David Wang | ITW | Standard Operation | TM1 | | TM1connected in ITW | I connected TM1 in ITW yesterday. Everything
is good so far. Travis was with me when i
did the job. |
|
215
|
Wednesday, November 14, 2012, 11:04 |
David Wang | ITE | Repair | TM4 | | Change ITE dump water circiut flow wheel | I changed ITE dump water circuit flow wheel
due to its poor performance. The new flow
wheel works fine. The signal on electrical |
|
216
|
Wednesday, November 14, 2012, 11:51 |
Travis Cave | Spent Target Vault | Standard Operation | | | Moving the spent targets to mini storage. | Five spent targets have been moved from
the storage vault to the mini storage vault.
The five targets are as follows: SiC #25, |
 |
217
|
Wednesday, November 21, 2012, 09:36 |
Travis Cave | Spent Target Vault | Standard Operation | | | Spent target move | On Nov 20th the 5 targets in mini storage
have been moved to the F-308s, those F-308s
have since been moved to the hot cell ante |
|
225
|
Wednesday, January 02, 2013, 12:11 |
David Wang | ITW | Standard Operation | TM1 | | I moved 5 shielding blocks from ITW to block storage area | I moved 5 shielding blocks from ITW
to block storage area for preparing the TM1
disconnection. Air sampled and swiped blocks |
|
226
|
Thursday, January 03, 2013, 10:05 |
David Wang | ITW | Standard Operation | TM1 | | Disconnected TM1 in ITW. | TM1 has been disconnected in ITW. All
water lines had been purged. Travis was with
me during the job. |
|
229
|
Thursday, January 10, 2013, 10:40 |
David Wang | ITW | Maintenance | | | Replaced all high active water system magnetic pedal wheels in ITW and ITE. | I replaced all high active water system
magnetic pedal wheels in ITW and ITE. This
is a preventive maintenance job we planned |
|