Thursday, August 25, 2016, 08:36, David Wang, Conditioning Station, Standard Operation, TM2, , Helium pressure test on TM2 HS water lline
|
I did a helium pressure test on TM2 HS water line at TCS. Leak detector base leak rate only could get to 1.8x e-8 atm.cc/sec at this moment. Applied 5 minutes 70psi helium on it. No leak has been found at this level. I connected water to this circuit after the test for weekend TM2 conditioning at TCS.
I will do another helium pressure test after the conditioning. The LD base leak rate should be 0.0Xe-9 atm.cc/sec at that time.
2016-08-29: LD Base leak rate 0.0xe-9atm.cc/sec.TM2 HS line helium pressure check again after conditioning. 70psi helium 5minutes. no response on LD. HS line is perfectly sealed. |
Wednesday, August 24, 2016, 14:42, Anders Mjos, Conditioning Station, Standard Operation, TM2, Ta#49, Conditioning
|
Wednesday, August 24, 2016, 14:42: RGA on
Wednesday, August 24, 2016, 20:27: IG2 and IG1S on. Checked on water system.
Conditioning by ISAC operations. Water flow tripped power supplies after a few hours of conditioning at 580 / 230 A and 30 kV. See operations e-log for details. |
Wednesday, August 24, 2016, 14:37, Anders Mjos, South Hot-Cell, Standard Operation, , SiC#33, PIE
|
The target was inspected by Anders and Chad. The target was in good condition as can be seen on the photos on DocuShare. Only minor accumulation of material on the EE. |
Wednesday, August 24, 2016, 11:06, Travis Cave, South Hot-Cell, Standard Operation, TM2, Ta#49, module moved and electrical check
|
TM#2 with Ta#49 has had its electrical check and was moved to the conditioning station. see the attached pdf for the electrical check details.
The electrical check has been edited to reflect that well the original has been just not the PDF. |
Wednesday, August 24, 2016, 10:45, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 vacuum system has been connected at TCS
|
Start of roughing now. |
Wednesday, August 24, 2016, 10:44, David Wang, South Hot-Cell, Standard Operation, TM2, , SHC, TM2 leak check on HS line.
|
Chad and I leak checked Tm2 Hs line with new target installed. Base LR 0.0Xe-9 atm.cc/sec. No leak has been found. This line will be helium pressured at TCS later. |
Wednesday, August 24, 2016, 10:41, David Wang, ITW, Standard Operation, TM2, , TM2 was disconnected in ITW yesterday.
|
TM2 was disconnected in ITW yesterday and moved to SHC. |
Wednesday, August 24, 2016, 09:19, chad fisher, South Hot-Cell, Maintenance, , , Anteroom Clean -up paint prep
|
Remaining items from anteroom have been bagged and removed (save the boot boxes, 1 garbage can and 1 coverall garbage can).
Room is ready to be surveyed so it can be deemed a non-boot box area for painting. |
Wednesday, August 24, 2016, 09:17, chad fisher, South Hot-Cell, Standard Operation, TM2, , Ta#49
|
Ta#49 has been installed on TM2 and tested. All high current fasteners torqued to 130 in lbs. |
Tuesday, August 23, 2016, 13:31, chad fisher, South Hot-Cell, Standard Operation, TM2, SiC#33, SiC#33 Removed
|
SiC#33 has been removed from TM2. |
Tuesday, August 23, 2016, 10:39, Travis Cave, South Hot-Cell, Standard Operation, TM2, SiC#33, module moved
|
TM#3 with SiC#33 has been moved from the west station to the south hot cell. |
Tuesday, August 23, 2016, 08:05, chad fisher, South Hot-Cell, Maintenance, , , Post Hot Cell Entry Clean-up
|
Plastic has been removed from the floor and any known active items in the hot cell moved to the south east corner in an attempt to shield the anteroom. Fields at the aluminum panel were reduced from 66 uSv/h to 58.8uSv\h. No contamination found on walls, floor, tacky mats, or standard aluminum cover. The aluminum cover with breathable air line hole did have 400 counts on 44-2, 1200 on ludlum.
|
Thursday, August 18, 2016, 14:19, Travis Cave, Conditioning Station, Standard Operation, TM3, no target, module moved
|
TM#3 is now back in the the north east silo. |
Thursday, August 18, 2016, 13:57, chad fisher, South Hot-Cell, Maintenance, , , Manipulator maitenance
|
South hot cell was entered to check to replace cable if needed. Wrist cable showed no signs of fraying or broken strands.
A tong with new cable pre-installed is now in the hot cell for next time this job needs to be done. There is also another spare tong cable not installed in a tong located in the box of manipulator repair equipment located inside the hot cell.
Both manipulator slave ends were lubricated whilst inside. |
Friday, July 08, 2016, 16:56, Anders Mjos, Conditioning Station, Repair, , , VFD21 OL1 fault on Chiller
|
Plant Services group (Tony) will contact a service tech on Monday.
Water system will be switched off over the weekend. |
Thursday, July 14, 2016, 13:25, Anders Mjos, Conditioning Station, Repair, , , VFD21 OL1 fault on Chiller
|
Anders Mjos wrote: |
Plant Services group (Tony) will contact a service tech on Monday.
Water system will be switched off over the weekend.
|
Thursday, July 14, 2016, 13:24: Claus from Daikin is on site to troubleshoot.
The VFD driven fan motor has failed. Temporarily blocked air-flow through failed fan to improve air-flow to radiator. A new motor will be ordered (Curtis).
Thursday, July 14, 2016, 15:39: Stopped cooling system for the day
Friday, July 15, 2016, 08:16: Cooling system started
Friday, July 15, 2016, 15:00; Cooling system stopped. |
Thursday, August 18, 2016, 10:35, Anders Mjos, Conditioning Station, Repair, , , VFD21 OL1 fault on Chiller
|
Anders Mjos wrote: |
Anders Mjos wrote: |
Plant Services group (Tony) will contact a service tech on Monday.
Water system will be switched off over the weekend.
|
Thursday, July 14, 2016, 13:24: Claus from Daikin is on site to troubleshoot.
The VFD driven fan motor has failed. Temporarily blocked air-flow through failed fan to improve air-flow to radiator. A new motor will be ordered (Curtis).
Thursday, July 14, 2016, 15:39: Stopped cooling system for the day
Friday, July 15, 2016, 08:16: Cooling system started
Friday, July 15, 2016, 15:00; Cooling system stopped.
|
Thursday, August 18, 2016, 10:34: The motor was replaced today by Claus from Daikin. System is running normally again. |
Tuesday, August 16, 2016, 12:35, David Wang, Conditioning Station, Repair, TM3, , CS vacuum pumps have been stopped
|
The TCS is venting now. The TM3 blue insulator replacement job will be started soon. |
Tuesday, August 16, 2016, 11:27, chad fisher, South Hot-Cell, Maintenance, , , South Cell Field Readings
|
Field readings have been taken at the south hot cell in preparation for entry into the cell to fix manipulator.
Field on contact at aluminum cover is 66 uSv/h, and a pole monitor into the cell through the tool port read 297 uSv/h. |
Monday, August 15, 2016, 10:15, David Wang, Conditioning Station, Standard Operation, TM4, , Target Hall schedule for beam schedule 130 (Apr- Oct, 2016)
|
Weekly update target hall schedule. Everything on schedule are finished on time. See attachment. |
Monday, August 15, 2016, 10:08, David Wang, ITE, Standard Operation, TM4, UC#17, 5 Shielding blocks have been transferred from ITW to ITE.
|
Dan and I transferred 5 shielding blocks from ITW to ITE. The ITE is configured to take proton beam. |
Friday, August 12, 2016, 10:59, Anders Mjos, Conditioning Station, Development, TM3, , HV Test with Service Chase Panel removed
|
Water cooling is performed manually with CP1. RGA is ON since yesterday. EE is not connected and in conditioning mode.
Friday, August 12, 2016, 10:43: BIAS at 10 kV, EL at 0.5 kV. IG1 at 1.8E-6 T
Friday, August 12, 2016, 11:04: BIAS at 20 kV
Friday, August 12, 2016, 11:10: Sparking at 21 kV
Friday, August 12, 2016, 11:29: BIAS at 22 kV. Many small sparks/current excursions.
Friday, August 12, 2016, 11:32 : BIAS at 23 kV
Friday, August 12, 2016, 11:37: BIAS at 24 kV
Friday, August 12, 2016, 11:43: BIAS at 25 kV. Heavy sparking. Lowered to 24 kV to reduce spark rate.
Friday, August 12, 2016, 11:52: Increased sparking rate. Lowered to 23 kV.
Friday, August 12, 2016, 12:05: Lowered to 20 kV
Friday, August 12, 2016, 12:21: Back to 23 kV
Friday, August 12, 2016, 12:28: Heavy sparking between 23 and 24 kV. Lowered to 22 kV
Friday, August 12, 2016, 12:29: More sparking. Lowered to 21 kV.
Friday, August 12, 2016, 13:02: Increased back up to ~25 kV while Aurelia was listening for sparks in the Target Hall.
Friday, August 12, 2016, 13:03: EL to 10 kV
Friday, August 12, 2016, 13:06: BIAS / EL to 23 / 12.5 kV
Friday, August 12, 2016, 13:34: Repeated sparking at 24.5 kV. Ramping down
Friday, August 12, 2016, 15:33: Stopped water package. RGA off |
|