ID Date Author Category Type Module Target/Number Subject
  1408   Tuesday, November 29, 2016, 06:27 David WangConditioning StationStandard OperationTM2 TCS water pumps are stopped

Argon venting on TCS and TM2 is processing

  1407   Friday, November 25, 2016, 09:04 Travis CaveSpent Target VaultStandard Operation SiC#35Spent Target move

On November 24th 2016 the spent SiC#35 was moved from the south hot cell to the spent target vault. see attached pdf for details.

Attachment 1: Vault_Storage_November_24_2016.pdf
Vault_Storage_November_24_2016.pdf Vault_Storage_November_24_2016.pdf Vault_Storage_November_24_2016.pdf Vault_Storage_November_24_2016.pdf
  1406   Thursday, November 24, 2016, 10:30 David WangConditioning StationStandard OperationTM2 HV cover is installed on TM2 at TCS

Interlock key  are returned back to B2 level.TM2 is ready for HV conditioning and heating up at TCS.

  1405   Thursday, November 24, 2016, 09:33 Anders MjosConditioning StationStandard OperationTM2UC#18Conditioning UC#18

Thursday, November 24, 2016, 09:33: Water package on

Thursday, November 24, 2016, 09:43: TCS:WPV1 shows only 12% open. A visual inspection confirms the valve is fully opened. Controls will be contacted to troubleshoot

 

  1404   Wednesday, November 23, 2016, 16:21 David WangConditioning StationStandard OperationTM2 TM2 and TCS vacuum system has been connected.

All vacuum pumps have been started. Air ballast 50seconds on roughing pump. Everything is good  so far.

  1403   Wednesday, November 23, 2016, 16:10 David WangSouth Hot-CellStandard OperationTM2 SHC, TM2 leak check on HS line.

Chad and I leak checked TM2 HS line with new UCx target installed. Helium spray  2 seconds on each joint and 10seconds flushing around target in SHC. LD base LR: 0.0XE-9atm.cc/sec, base pressure:0.0XE-4 torr. No response has been found on LD during check. The line is leak free.

  1402   Wednesday, November 23, 2016, 14:25 Travis CaveSouth Hot-CellStandard OperationTM2UC#18Electrical Check

Results of TM#2 with UC#18 electrical at the south hot cell. See attached PDF for details.

Attachment 1: TM2_elechk_UC18_SHC.PDF
TM2_elechk_UC18_SHC.PDF
  1401   Wednesday, November 23, 2016, 14:21 Travis CaveConditioning StationStandard OperationTM2UC#18module moved

TM#2 with UC#18 has been moved from the south hot cell to the conditioning station.

  1400   Tuesday, November 22, 2016, 14:26 David WangConditioning StationStandard Operation  TCS vacuum pumps are switched off

TCS will be vented tomorrow morning for TM2 moving.

  1399   Tuesday, November 22, 2016, 11:56 Travis CaveSouth Hot-CellStandard OperationTM2SiC#35Electrical Check

Electrical check of TM#2 with the SiC#35  post beam run. See attached PDF for details.

Attachment 1: TM2_elechk_SiC35_postbeam.PDF
TM2_elechk_SiC35_postbeam.PDF
  1398   Tuesday, November 22, 2016, 10:45 Travis CaveSouth Hot-CellStandard OperationTM2SiC#35module moved

TM#2 with the old SiC #35 has been moved from ITW to the south hot cell.

  1397   Tuesday, November 15, 2016, 07:53 David WangConditioning StationStandard OperationTM4 Target Hall schedule for beam schedule 131(Sep-Dec, 2016)

Update TH schedules . See attachments

Attachment 1: Target_Hall_shedule_131_Sep_to_Dec.pdf
Target_Hall_shedule_131_Sep_to_Dec.pdf
Attachment 2: Target_Hall_shedule_131_Sep_to_Dec.mpp
Attachment 3: Target_Hall_shedule_131__Sep_to_Dec_2016.pdf
Target_Hall_shedule_131__Sep_to_Dec_2016.pdf
  1396   Tuesday, November 08, 2016, 14:45 David WangITEMaintenanceTM4 TM4 has been moved to ITE and connected there.

All ITE and TM4  turbo pumps are started. The east station pumping down is good so far.

  1395   Tuesday, November 08, 2016, 14:04 Isaac EarleNorth Hot-CellDevelopment  Interference check with TCS turbo pump and proposed NHC duct routing

David Wang and I accessed the NHC today to check if the proposed duct routing (IRH1618) will interfere with servicing or replacement of the TCS turbo pump.  A piece of plywood was placed in the future position of the NHC/TCS partition wall (IRH1609), and a ducting elbow was placed at the approximate position of the nearest elbow to the turbo pump.

David concluded that the ducting in the proposed location will not have any significant effect on replacement of the turbo pump, and he does not expect replacement will be difficult to perform after installation of the wall and NHC ducting.  Standing at floor level towards the east side of the TCS space and reaching upwards seemed to be the best way to reach the turbo pump flange bolts.  It was also noted that there was sufficient room in the TCS space for two workers to be in the area.

 

IMG_7577.JPG

 

IMG_7583.JPG

 

IMG_7582.JPG

  1394   Tuesday, November 08, 2016, 10:23 Travis CaveITEStandard OperationTM4Ta#50module moved

TM#4 with Ta#50 has been moved to the east target station.

  1393   Tuesday, November 08, 2016, 07:47 David WangConditioning StationStandard OperationTM4 TCS water and vacuum pumps are switched off

TCS is vented. TM4 is disconnected and TCS.

  1392   Monday, November 07, 2016, 10:35 Travis CaveSpent Target VaultStandard Operation SiC#34Spent Target move

Spent SiC#34 was moved on the 3rd of November and  placed in the spent target vault. See attached pdf for details.

Attachment 1: Vault_Storage_November_3_2016.pdf
Vault_Storage_November_3_2016.pdf Vault_Storage_November_3_2016.pdf Vault_Storage_November_3_2016.pdf Vault_Storage_November_3_2016.pdf
  1391   Thursday, November 03, 2016, 09:01 David WangConditioning StationStandard OperationTM4 TCS water system has been started for TM4.

The system works fine. All water signals to TM4 at TCS are normal. HV cover is installed on to TM4 at TCS.

  1390   Thursday, November 03, 2016, 08:57 David WangConditioning StationStandard OperationTM4 Helium pressure test on TM4 HS line at TCS

70 psi helium ,2minutes to  TM4 HS line. LD base leak rate 0.0xE-9 atm.cc/sec. No leak.

  1389   Wednesday, November 02, 2016, 13:41 David WangConditioning StationStandard OperationTM4 TM4 has been connected at TCS.

All turbo-pumps are started. The pumping down is good so far.