Monday, March 14, 2016, 15:22, David Wang, Conditioning Station, Standard Operation, TM2, , 2016 Winter Shut Down Target Hall Schedule 
|
update schedule according to change. See attachment 1,2
|
Wednesday, March 16, 2016, 09:20, Travis Cave, ITE, Standard Operation, TM2, SiC#32, module moved
|
TM#2 with SiC#32 has been moved from the west station to the south hot cell. |
Wednesday, March 16, 2016, 14:23, chad fisher, South Hot-Cell, Standard Operation, TM2, SiC#32, SiC#32 removal Target Module Inspection 
|
SiC#32 has been removed from TM2. Quick inspection shows some troubling discoloration on the water cooled connection blocks of C and D as well as the left target heater A.
As for the target, both legs are broken and is has the normal "charge up" marks on the 9 pin connector. |
Thursday, March 17, 2016, 14:57, David Wang, South Hot-Cell, Repair, TM2, , TM2 first round leak check in SHC
|
Chad and I finished the first round check on Tm2 water lines. The lines and spots checked are: Target oven + and - (front side braze joints) , Tube heater+and -(front side braze joints and water blocks), coil2 and coil 1(front side braze joints and area close to water blocks),. No leak has been found on all above of them. The last, we checked the GE which has the biggest leak so far. The leak detector base leak rate only can get to 4XE-9 atm.cc/sec. Chad sprayed helium very close to GE water block, and I got a quick response on leak detector. The leak rate climbed from 4Xe-9 atm.cc/sec to 1.4 atm.cc/sec. We confirmed the GE is leaking now. The exact location need to be pinpointed later once the containment box is out after the module is back to SHC. The module will be moved to TCS tomorrow morning and pressurized again there. Anders will use RGA to monitor the helium response during the check. |
Friday, March 18, 2016, 08:34, Travis Cave, Conditioning Station, Standard Operation, TM2, no target, module moved
|
TM#2 with no target has been moved to the conditioning station from the south hot cell. |
Friday, March 18, 2016, 09:34, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall schedule for beam schedule 130 (Apr- Sep) 
|
I would like to post the spreadsheet of target hall schedule for beam schedule 130(Apr to Sep) first. The MS project of TH schedule for beam schedule 130 is under construction, and will be posted later. |
Friday, March 18, 2016, 09:42, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 vacuum sysytem has been connected at TCS
|
TM2 vacuum system has been connected at TCS. Started roughing pump. Everything is good so far. |
Friday, March 18, 2016, 13:13, Travis Cave, Conditioning Station, Standard Operation, TM2, SiC#32, Electrical Check 
|
Electrical checks of the TM#2 with the old SiC#32 and without the target. See attached PDFs. |
Monday, March 21, 2016, 10:25, David Wang, Conditioning Station, Repair, TM2, , TM2 Helium pressure Test Result in TCS and ITW
|
TM2 has been helium pressure tested in ITW and TCS. They are both tested with 70psi helium, each circuit for 3minutes.
The leak detector base leak rate: 0.0X E-9 atm.cc/sec, base pressure 0.0 xE-4 torr for both ITW and TCS. The test results are:
circuit |
TCS Test Result (atm.cc/sec) 2016-03-021 |
ITW Test Result (atm.cc/sec) 2016-03-02 |
TCS Test Result (atm.cc/sec)
2116-11-24
|
Target Oven + |
5.2 X E-9 |
1.7 X E-8 |
2.0 X E-9 |
Target Oven - |
5.6 X E-9 |
8.7 X E-9 |
2.2 X E-8 |
Tube Heater + |
3.7 X E-8 |
1.7 X E-8 |
2.3 X E -8 |
Tube Heater - |
1.9 X E-8 |
1.5 X E-8 |
8.2 X E-8 |
Coil 2 (P-Q) |
7.2 X E-8 |
6.7 X E-8 |
5.4 X E-9 |
Coil 1 (R-U) |
1.4 X E-8 |
1.3 X E-8 |
2.4 X E-9 |
MSP |
2.3 X E-7, SECOND TIME 2.5 X E-7 |
4 X E-9 |
2.4 X E-7 |
HS |
NO TEST, LINE IS OPEN TO VACUUM. |
GOOD, NO RESPONSE ON LD |
Good, 0.0 X E-9 |
EE |
4.3 X E-9 |
GOOD, NO RESPONSE ON LD |
3.7 X E-8
|
window |
4.5 X E-9 |
GOOD, NO RESPONSE ON LD |
Good , 0.0 X E-9 |
GE |
NO TEST, CONFIRMED IN SHC |
MIDDLE OF E-6 RANGE |
No test. Blanked |
|
|
|
|
2016-11-24: Checked again and added result into this elog. No essential change has been found. MSP still has the biggest leak rate. David |
Monday, March 21, 2016, 11:30, David Wang, Conditioning Station, Repair, TM2, , TM2 and TCS vacuum pumps are stopped
|
I stopped TM2 and TCS vacuum pumps. It will be vented and disconnected this afternoon for tomorrow moving. |
Monday, March 21, 2016, 15:27, David Wang, Conditioning Station, Repair, TM2, , TM2 has been disconnected at TCS
|
TM2 vacuum system has been disconnected at TCS. Venting is in process now. |
Wednesday, March 23, 2016, 11:00, Travis Cave, South Hot-Cell, Standard Operation, TM2, no target, module moved
|
TM#2 was moved into the south hot cell by 08:30. |
Wednesday, March 23, 2016, 11:32, David Wang, South Hot-Cell, Repair, TM2, , TM2 Helium spray leak check on GE and MSP lines at SHC
|
Chad and I did the helium spray leak check on TM2 GE and MSP water lines at SHC this morning. We confirmed the GE leak on water blocks. We can not found the MSP leak by using the helium spray since its leak rate in TCS is much smaller than GE leak. The leak check process are as below:
Leak detector are calibrated before the check.
GE lines : Base leak rate 0.0 X E-9 atm.cc/sec, base pressure 0.0 XE-4 torr.
Chad sprayed 5 psi helium to GE lines soldering joints for 5 second, no response on leak detector.
Chad sprayed 5 psi helium to GE lines water blocks( between blocks seal surface) for 5 seconds, Leak detector response to 8 XE-9 atm.cc/sec right away.
Chad sprayed 5 psi helium to GE lines soldering joints for 5 seconds again, No response on leak detector.
Chad sprayed 5 psi helium around the source tray and to vacuum duct for 5 seconds more, No response on leak detector.
MSP lines: Base leak rate 0.0X E-9 atm.cc/sec, base pressure 0.0 X E-4 torr. Chad did same thing as he did on GE lines. no response on LD. Chad repeated the test and prolonged the spray time to 10 seconds, No response.
The conclusion: It is pretty clear we have a leak on GE line water blocks seal. MSP lines leak could not be found by helium spray in SHC since it is a small leak.
|
Wednesday, March 30, 2016, 15:49, David Wang, Assembly/Bench Test, Repair, TM2, , TM2 Helium spray leak check on solder stems inside service cap on the top of SW silo. 7x
|
On each water circuit in side the service cap, there are 4 soldering stems which two of them are inside blue nylon insulator and other two are connected to service tray. Each stem has two soldering spots. See attachment pictures for detail location. I sprayed 15 psi helium on each soldering spots on stems for 20second on each circuit. I sprayed tons of helium inside each blue nylon.No any leak has been found during the check. The leak detector base leak rate:0.0 XE-9 atm.cc/sec, base pressure:0.0X E-4 torr. The circuit which I checked are :TA+, Ta-, Tube+, Tube-, PQ (coil 2), RU( coil1), EE, MSP, GE. The HS and window circuit are opened at this moment so they can not be checked. |
Wednesday, April 13, 2016, 10:14, Travis Cave, Conditioning Station, Standard Operation, TM2, no target, module moved
|
TM#2 has been moved from the south west silo to the conditioning station. |
Wednesday, April 13, 2016, 10:46, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 and TCS vacuum system has been connected.
|
TCS is under roughing now. |
Wednesday, April 13, 2016, 10:46, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 and TCS vacuum system has been connected.
|
TCS is under roughing now.
2016-04-14, Started TCS and TM2 turbo-pumps yesterday afternoon. Overnight pumping down is fine. |
Thursday, April 14, 2016, 09:46, Anders Mjos, Conditioning Station, Standard Operation, TM2, , TM2 water leak test
|
Thursday, April 14, 2016, 07:50: RGA on
Friday, April 15, 2016, 08:09 : Ratio between water and air is higher than normal (indicating possible air leak). See attachment. 3.5 more H2O than N2. (Ratio in TM3 Nov 2015 was 82:1)
A leak was found on the o-ring between the module flange and TCS. This could be fixed by cleaning the o-ring and sealing surface. The Window line is not closed and was accidentally pressurized with He on April 25
Tuesday, April 26, 2016, 08:47: David started the water package.
Wednesday, April 27, 2016, 08:15: Switched off chiller / water cooling.
Wednesday, April 27, 2016, 14:41: Switched chiller / water cooling back on. |
Monday, April 18, 2016, 09:07, David Wang, Conditioning Station, Repair, TM2, , venting TCS with argon.
|
Anders reported a possible air leak on TM2 and TCS by watching RGA this morning. I found the quick connector on F terminal on the top of the module is leaking air. It is only used as "X" terminal for Febiad without water. So, it should be blind capped instead of installing a quick connector. It was installed with a blind cap before. I borrowed it for leak check on coil lines at SHC, but forgot to put it back right away. Instead, I put a quick connector on it later. This caused the problem. Anyway The TCS need to be vented , and a blind cap will be installed on the F terminal.
2014-04-18, 9:24AM, I changed the quick connector with a blind cap on F terminal. the rough pump is started now. |
Friday, April 22, 2016, 14:07, David Wang, Conditioning Station, Standard Operation, TM2, , 2016 Winter Shut Down Target Hall Schedule 
|
Weekly update.This is the last update on 2016 winter shut down schedule. The new TH schedule for beam130 will be posted weekly after this. All jobs in winter shut down schedule were finished on time.
|
|