ID Date Author Category Type Moduledown Target/Number Subject Text Attachments
  1173   Friday, March 18, 2016, 13:13 Travis CaveConditioning StationStandard OperationTM2SiC#32Electrical CheckElectrical checks of the TM#2 with the
old SiC#32 and without the target. See attached
PDFs.
 TM2_SiC32_postbeam.PDFTM2_elec_chk_notgt_CS.PDF 
  1174   Monday, March 21, 2016, 10:25 David WangConditioning StationRepairTM2 TM2 Helium pressure Test Result in TCS and ITWTM2 has been helium pressure tested in
ITW and TCS. They are both tested with 70psi
helium, each circuit for 3minutes. 
  
  1175   Monday, March 21, 2016, 11:30 David WangConditioning StationRepairTM2 TM2 and TCS vacuum pumps are stoppedI stopped TM2 and TCS vacuum pumps. It
will be vented and disconnected this afternoon
for tomorrow  moving.   
  
  1176   Monday, March 21, 2016, 15:27 David WangConditioning StationRepairTM2 TM2 has been disconnected at TCSTM2 vacuum system has been disconnected
at TCS. Venting is in process now.
  
  1178   Wednesday, March 23, 2016, 11:00 Travis CaveSouth Hot-CellStandard OperationTM2no targetmodule movedTM#2 was moved into the south hot cell
by 08:30.
  
  1179   Wednesday, March 23, 2016, 11:32 David WangSouth Hot-CellRepairTM2 TM2 Helium spray leak check on GE and MSP lines at SHC  Chad and I did the helium spray
leak check on TM2 GE and MSP  water lines
at SHC this morning. We confirmed the GE
  
  1185   Wednesday, March 30, 2016, 15:49 David WangAssembly/Bench TestRepairTM2  TM2 Helium spray leak check on solder stems inside service cap on the top of SW silo.On each water circuit in side the service
cap, there are 4 soldering stems which two
of them are inside blue nylon insulator and
 7x 
  1208   Wednesday, April 13, 2016, 10:14 Travis CaveConditioning StationStandard OperationTM2no targetmodule movedTM#2 has been moved from the south west
silo to the conditioning station.
  
  1209   Wednesday, April 13, 2016, 10:46 David WangConditioning StationStandard OperationTM2 TM2 and TCS vacuum system has been connected. TCS is under roughing now.   
  1210   Wednesday, April 13, 2016, 10:46 David WangConditioning StationStandard OperationTM2 TM2 and TCS vacuum system has been connected. TCS is under roughing now.
2016-04-14, Started TCS and TM2 turbo-pumps
yesterday afternoon. Overnight pumping down
  
  1211   Thursday, April 14, 2016, 09:46 Anders MjosConditioning StationStandard OperationTM2 TM2 water leak test Thursday, April 14, 2016, 07:50:
RGA on

Friday, April 15, 2016, 08:09
 2016-04-15_RGA.png 
  1213   Monday, April 18, 2016, 09:07 David WangConditioning StationRepairTM2 venting TCS with argon.Anders reported a possible air leak on
TM2 and TCS by watching RGA  this morning.
I found the quick connector on F terminal
  
  1214   Friday, April 22, 2016, 14:07 David WangConditioning StationStandard OperationTM2 2016 Winter Shut Down Target Hall ScheduleWeekly update.This is the last update on
2016 winter shut down schedule. The new TH
schedule for beam130  will be posted
 2016_winter_shut_down__target_hall_schedule.pdf2016_winter_shut_down__target_hall_schedule.mpp 
  1216   Tuesday, April 26, 2016, 10:47 David WangConditioning StationRepairTM2 TM2 leak check at TCS, water test.The following water circuits in TM2 are
connected at TCS and  running with water
now : target oven+ - ( one circuit), tube
  
  1217   Thursday, April 28, 2016, 06:28 David WangConditioning StationMaintenanceTM2 TCS water system are turned off. TCS water system worked fine overnight.
I turned off TCS water system at 6:16 AM
this morning. Start of purging TM2 water
  
  1218   Friday, April 29, 2016, 08:01 David WangConditioning StationMaintenanceTM2 TM2 leak check at TCS, helium pressure testAnders and I finished the most part of
TM2 water lines helium pressure test yesterday.I
list the system parameters and test result
  
  1219   Friday, April 29, 2016, 10:06 David WangConditioning StationStandard OperationTM2 I switched off TCS and TM2 vacuum pumps.  I switched off TCS and TM2 vacuum
pumps. The TM2 will be disconnected at TCS
today and moved to silo on next Monday.
  
  1220   Monday, May 02, 2016, 11:33 Travis CaveConditioning StationStandard OperationTM2no targetmodule movedTM#2 was moved to the SW Silo from the
Conditioning Station. TM#3 was from from
the NW Silo to the Conditioning Station.
  
  1224   Monday, May 09, 2016, 10:13 Travis CaveSouth Hot-CellStandard OperationTM2no targetmodule movedTM#3 was moved from the conditioning station
to the NE Silo. TM#2 was moved from the SW
Silo to the South hot cell.
  
  1225   Tuesday, May 10, 2016, 13:37 chad fisherSouth Hot-CellStandard OperationTM2Ta#48Ta#48 InstallationTa#48 has been installed onto TM2. Also
new window gaskets were installed.
High current fasteners were torqued
  