Monday, March 14, 2016, 15:22, David Wang, Conditioning Station, Standard Operation, TM2, , 2016 Winter Shut Down Target Hall Schedule 
|
update schedule according to change. See attachment 1,2
|
Wednesday, March 16, 2016, 09:20, Travis Cave, ITE, Standard Operation, TM2, SiC#32, module moved
|
TM#2 with SiC#32 has been moved from the west station to the south hot cell. |
Wednesday, March 16, 2016, 14:23, chad fisher, South Hot-Cell, Standard Operation, TM2, SiC#32, SiC#32 removal Target Module Inspection 
|
SiC#32 has been removed from TM2. Quick inspection shows some troubling discoloration on the water cooled connection blocks of C and D as well as the
left target heater A.
As for the target, both legs are broken and is has the normal "charge up" marks on the 9 pin connector. |
Thursday, March 17, 2016, 14:57, David Wang, South Hot-Cell, Repair, TM2, , TM2 first round leak check in SHC
|
Chad and I finished the first round check on Tm2 water lines. The lines and spots checked are: Target oven + and - (front side braze joints) , Tube
heater+and -(front side braze joints and water blocks), coil2 and coil 1(front side braze joints and area close to water blocks),. No leak has been found
on all above of them. The last, we checked the GE which has the biggest leak so far. The leak detector base leak rate only can get |
Friday, March 18, 2016, 08:34, Travis Cave, Conditioning Station, Standard Operation, TM2, no target, module moved
|
TM#2 with no target has been moved to the conditioning station from the south hot cell. |
Friday, March 18, 2016, 09:34, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall schedule for beam schedule 130 (Apr- Sep) 
|
I would like to post the spreadsheet of target hall schedule for beam schedule 130(Apr to Sep) first. The MS project of TH schedule for beam schedule
130 is under construction, and will be posted later. |
Friday, March 18, 2016, 09:42, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 vacuum sysytem has been connected at TCS
|
TM2 vacuum system has been connected at TCS. Started roughing pump. Everything is good so far. |
Friday, March 18, 2016, 13:13, Travis Cave, Conditioning Station, Standard Operation, TM2, SiC#32, Electrical Check 
|
Electrical checks of the TM#2 with the old SiC#32 and without the target. See attached PDFs. |
Monday, March 21, 2016, 10:25, David Wang, Conditioning Station, Repair, TM2, , TM2 Helium pressure Test Result in TCS and ITW
|
TM2 has been helium pressure tested in ITW and TCS. They are both tested with 70psi helium, each circuit for 3minutes.
The leak detector base leak rate: 0.0X E-9 atm.cc/sec, base pressure 0.0 xE-4 torr for both ITW and TCS. The test results are:
|
Monday, March 21, 2016, 11:30, David Wang, Conditioning Station, Repair, TM2, , TM2 and TCS vacuum pumps are stopped
|
I stopped TM2 and TCS vacuum pumps. It will be vented and disconnected this afternoon for tomorrow moving. |
Monday, March 21, 2016, 15:27, David Wang, Conditioning Station, Repair, TM2, , TM2 has been disconnected at TCS
|
TM2 vacuum system has been disconnected at TCS. Venting is in process now. |
Wednesday, March 23, 2016, 11:00, Travis Cave, South Hot-Cell, Standard Operation, TM2, no target, module moved
|
TM#2 was moved into the south hot cell by 08:30. |
Wednesday, March 23, 2016, 11:32, David Wang, South Hot-Cell, Repair, TM2, , TM2 Helium spray leak check on GE and MSP lines at SHC
|
Chad and I did the helium spray leak check on TM2 GE and MSP water lines at SHC this morning. We confirmed the GE leak on water blocks. We can
not found the MSP leak by using the helium spray since its leak rate in TCS is much smaller than GE leak. The leak check process are as below:
|
Wednesday, March 30, 2016, 15:49, David Wang, Assembly/Bench Test, Repair, TM2, , TM2 Helium spray leak check on solder stems inside service cap on the top of SW silo. 7x
|
On each water circuit in side the service cap, there are 4 soldering stems which two of them are inside blue nylon insulator and other two are connected
to service tray. Each stem has two soldering spots. See attachment pictures for detail location. I sprayed 15 psi helium on each soldering spots on stems
for 20second on each circuit. I sprayed tons of helium inside each blue nylon.No any leak has been found during the check. The leak detector base leak |
Wednesday, April 13, 2016, 10:14, Travis Cave, Conditioning Station, Standard Operation, TM2, no target, module moved
|
TM#2 has been moved from the south west silo to the conditioning station. |
Wednesday, April 13, 2016, 10:46, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 and TCS vacuum system has been connected.
|
TCS is under roughing now. |
Wednesday, April 13, 2016, 10:46, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 and TCS vacuum system has been connected.
|
TCS is under roughing now.
2016-04-14, Started TCS and TM2 turbo-pumps yesterday afternoon. Overnight pumping down is fine. |
Thursday, April 14, 2016, 09:46, Anders Mjos, Conditioning Station, Standard Operation, TM2, , TM2 water leak test
|
Thursday, April 14, 2016, 07:50: RGA on
Friday, April 15, 2016, 08:09 : Ratio between water and air is higher than normal (indicating possible air leak). See attachment. 3.5 more
H2O than N2. (Ratio in TM3 Nov 2015 was 82:1) |
Monday, April 18, 2016, 09:07, David Wang, Conditioning Station, Repair, TM2, , venting TCS with argon.
|
Anders reported a possible air leak on TM2 and TCS by watching RGA this morning. I found the quick connector on F terminal on the top of the module
is leaking air. It is only used as "X" terminal for Febiad without water. So, it should be blind capped instead of installing a quick connector.
It was installed with a blind cap before. I borrowed it for leak check on coil lines at SHC, but forgot to put it back right away. Instead, I put |
Friday, April 22, 2016, 14:07, David Wang, Conditioning Station, Standard Operation, TM2, , 2016 Winter Shut Down Target Hall Schedule 
|
Weekly update.This is the last update on 2016 winter shut down schedule. The new TH schedule for beam130 will be posted weekly after this. All
jobs in winter shut down schedule were finished on time.
|
|