Entry  Monday, March 14, 2016, 15:22, David Wang, Conditioning Station, Standard Operation, TM2, , 2016 Winter Shut Down Target Hall Schedule 2016_winter_shut_down__target_hall_schedule.pdf2016_winter_shut_down__target_hall_schedule.mpp
update schedule according to change. See attachment 1,2
 
Entry  Wednesday, March 16, 2016, 09:20, Travis Cave, ITE, Standard Operation, TM2, SiC#32, module moved 
TM#2 with SiC#32 has been moved from the west station to the south hot cell.
Entry  Wednesday, March 16, 2016, 14:23, chad fisher, South Hot-Cell, Standard Operation, TM2, SiC#32, SiC#32 removal Target Module Inspection 20160316_141127.jpg20160316_141146.jpg
SiC#32 has been removed from TM2. Quick inspection shows some troubling discoloration on the water cooled connection blocks of C and D as well as the
left target heater A.
As for the target, both legs are broken and is has the normal "charge up" marks on the 9 pin connector.
Entry  Thursday, March 17, 2016, 14:57, David Wang, South Hot-Cell, Repair, TM2, , TM2 first round leak check in SHC 
Chad and I finished the first round check on Tm2 water lines.  The lines and spots checked are: Target oven + and - (front side braze  joints) , Tube
heater+and -(front side braze joints and water blocks),  coil2 and coil 1(front side braze joints and area close to water  blocks),. No leak has been found
on all above of them.  The last, we  checked   the GE which has the biggest leak so far. The leak detector  base leak rate only can get
Entry  Friday, March 18, 2016, 08:34, Travis Cave, Conditioning Station, Standard Operation, TM2, no target, module moved 
TM#2 with no target has been moved to the conditioning station from the south hot cell.
Entry  Friday, March 18, 2016, 09:34, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall schedule for beam schedule 130 (Apr- Sep) Target_Hall_shedule_130_Apr_to_Sep_2016.xlsxTarget_Hall_shedule_130_Apr_to_Sep_2016.pdf
I would like to post the spreadsheet of target hall schedule for beam schedule 130(Apr to Sep) first. The MS project of TH schedule for  beam schedule
130 is under construction, and will be posted later.
Entry  Friday, March 18, 2016, 09:42, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 vacuum sysytem has been connected at TCS 
TM2 vacuum system has been connected at TCS. Started roughing pump. Everything is good so far.
Entry  Friday, March 18, 2016, 13:13, Travis Cave, Conditioning Station, Standard Operation, TM2, SiC#32, Electrical Check TM2_SiC32_postbeam.PDFTM2_elec_chk_notgt_CS.PDF
Electrical checks of the TM#2 with the old SiC#32 and without the target. See attached PDFs.
Entry  Monday, March 21, 2016, 10:25, David Wang, Conditioning Station, Repair, TM2, , TM2 Helium pressure Test Result in TCS and ITW 
TM2 has been helium pressure tested in ITW and TCS. They are both tested with 70psi helium, each circuit for 3minutes. 
The leak detector base leak rate: 0.0X E-9 atm.cc/sec, base pressure 0.0 xE-4 torr  for both ITW and TCS. The test results are:
 
Entry  Monday, March 21, 2016, 11:30, David Wang, Conditioning Station, Repair, TM2, , TM2 and TCS vacuum pumps are stopped 
I stopped TM2 and TCS vacuum pumps. It will be vented and disconnected this afternoon for tomorrow  moving.   
Entry  Monday, March 21, 2016, 15:27, David Wang, Conditioning Station, Repair, TM2, , TM2 has been disconnected at TCS 
TM2 vacuum system has been disconnected at TCS. Venting is in process now.
Entry  Wednesday, March 23, 2016, 11:00, Travis Cave, South Hot-Cell, Standard Operation, TM2, no target, module moved 
TM#2 was moved into the south hot cell by 08:30.
Entry  Wednesday, March 23, 2016, 11:32, David Wang, South Hot-Cell, Repair, TM2, , TM2 Helium spray leak check on GE and MSP lines at SHC 
  Chad and I did the helium spray leak check on TM2 GE and MSP  water lines at SHC this morning. We confirmed the GE leak on water  blocks. We can
not found the MSP leak by using the helium spray since  its leak rate in TCS is much smaller than GE leak.  The leak check  process are as below:
Entry  Wednesday, March 30, 2016, 15:49, David Wang, Assembly/Bench Test, Repair, TM2, , TM2 Helium spray leak check on solder stems inside service cap on the top of SW silo. 7x
On each water circuit in side the service cap, there are 4 soldering stems which two of them are inside blue nylon insulator and other two are connected
to service tray. Each stem has two soldering spots. See attachment pictures for detail location. I sprayed 15 psi helium on each soldering spots on stems 
for 20second on each circuit. I sprayed tons of helium inside each blue nylon.No any leak has been found during the check. The leak detector base leak
Entry  Wednesday, April 13, 2016, 10:14, Travis Cave, Conditioning Station, Standard Operation, TM2, no target, module moved 
TM#2 has been moved from the south west silo to the conditioning station.
Entry  Wednesday, April 13, 2016, 10:46, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 and TCS vacuum system has been connected.  
TCS is under roughing now.
Entry  Wednesday, April 13, 2016, 10:46, David Wang, Conditioning Station, Standard Operation, TM2, , TM2 and TCS vacuum system has been connected.  
TCS is under roughing now.
2016-04-14, Started TCS and TM2 turbo-pumps yesterday afternoon. Overnight pumping down is fine.
Entry  Thursday, April 14, 2016, 09:46, Anders Mjos, Conditioning Station, Standard Operation, TM2, , TM2 water leak test 2016-04-15_RGA.png
 Thursday, April 14, 2016, 07:50: RGA on

Friday, April 15, 2016, 08:09 : Ratio between water and air is higher than normal (indicating possible air leak). See attachment. 3.5 more
H2O than N2.  (Ratio in TM3 Nov 2015 was 82:1)
Entry  Monday, April 18, 2016, 09:07, David Wang, Conditioning Station, Repair, TM2, , venting TCS with argon. 
Anders reported a possible air leak on TM2 and TCS by watching RGA  this morning. I found the quick connector on F terminal on the top of the module
is leaking air. It is only used as "X" terminal for Febiad without  water. So, it should be blind capped instead of installing a quick connector.
It was installed with a  blind cap before. I borrowed it for leak check on coil lines at SHC, but forgot to put it back right away. Instead, I put
Entry  Friday, April 22, 2016, 14:07, David Wang, Conditioning Station, Standard Operation, TM2, , 2016 Winter Shut Down Target Hall Schedule 2016_winter_shut_down__target_hall_schedule.pdf2016_winter_shut_down__target_hall_schedule.mpp
Weekly update.This is the last update on 2016 winter shut down schedule. The new TH schedule for beam130  will be posted weekly after this. All
jobs in winter shut down schedule were finished on time.
 