  RH-ISAC, Page 63 of 138  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
  ID Date Author Categorydown Type Module Target/Number Subject Text Attachments
  92   Tuesday, April 24, 2012, 10:02 Travis CaveITWStandard OperationTM1Nb#6module moveTM#1 with Nb#6 from the conditioning station
to the west target station, move was uneventful.
Mike LaRoss was there today for move in place
  
  97   Wednesday, May 02, 2012, 11:27 David WangITWStandard OperationTM1  ITW is ready for taking proton beam. I moved 5 shielding blocks from ITE
to ITW .  I checked  all ITW water
signals strength and frequency in electrical
  
  116   Tuesday, June 05, 2012, 15:06 Bevan MossITWStandard OperationTM1Nb#6Module move from ITW to SHC TM1 has been moved from ITW to the
SHC. The move did encounter some issues,
one of the railings for preventing people
  
  117   Wednesday, June 06, 2012, 08:21 David WangITWStandard OperationTM1 TM1 disconnected in ITWI disconnected TM1 in ITW yesterday morning.The
general radioactive level in ITW over the
TM top (300mm) is about 350 usv/hr. contacting
  
  127   Tuesday, June 19, 2012, 10:35 Travis CaveITWStandard OperationTM1Ta#38module moveTM#1 with Ta#38 moved from the conditioning
station to the west target station. Move
went well.
  
  128   Tuesday, June 19, 2012, 16:18 David WangITWStandard OperationTM1Ta38TM1connected in ITW
 

 Normal
  0

 
   
  
  134   Monday, June 25, 2012, 14:39 David WangITWStandard Operation  I moved 5 shielding blocks from ITE to ITW,and set up ventilation for ITW. ITW is
ready for taking proton beam now. All water
interlock checks for ITW are done. The ITW
  
  151   Tuesday, July 31, 2012, 09:52 David WangITWStandard OperationTM1Ta38TM1 disconnected in ITWI disconnected TM1 in ITW.  Heat shield
line has been purged .
  
  159   Tuesday, August 07, 2012, 14:06 David WangITWRepair  ITW TP4S has been replaced
 

 Normal
  0

 
   
  
  160   Tuesday, August 14, 2012, 11:16 Travis CaveITWStandard OperationTM1UCx#4module moveTM#1 with UCx#4 has been moved from the
conditioning station to the west target station
move went well.
  
  161   Tuesday, August 14, 2012, 11:16 Travis CaveITWStandard OperationTM1UCx#4module moveTM#1 with UCx#4 moved from the conditioning
to the west target station move went well.
  
  162   Tuesday, August 14, 2012, 14:27 David WangITWStandard OperationTM1UCxTM1connection in ITWConnected TM1 in ITW,started 6 turbo pumps,
and finished TM1 water interlock check .
Every thing is good so far.
  
  163   Monday, August 20, 2012, 12:28 David WangITWStandard OperationTM1 I moved 5 shielding blocks from ITE to ITW,I moved 5 shielding blocks from ITE 
to ITW.ITW is configured to take proton beam
now.
  
  164   Thursday, August 23, 2012, 07:34 David WangITWRepair  Replaced broken air lines on ITW HARP5B cylinder.Prob guys replaced broken air lines on
ITW HARP 5B Cylinder.Several shielding blocks
had been moved out to make the cylinder accessible.
  
  176   Wednesday, September 12, 2012, 11:59 David WangITWStandard OperationTM1UCxTM1 disconnected in ITWI removed 5 shielding blocks from ITW to
block storage area, and disconnected TM1
in ITW. After UCx run,  the radioactive
  
  187   Tuesday, September 25, 2012, 10:34 Travis CaveITWStandard OperationTM1Nb#7module moveTM#1 with Nb#7 moved from the conditioning
station to the west target station. Move
went well.
  
  188   Tuesday, September 25, 2012, 14:33 David WangITWStandard OperationTM1Nb#7TM1connected in ITWTM 1 is in ITW now. All connections are
done. The turbo pumps had been started  this
afternoon. The vacuum looks good so far.
  
  190   Tuesday, October 02, 2012, 11:47 David WangITWStandard OperationTM1Nb#7I moved 5 shielding blocks from ITE to ITW.5 shielding blocks have been moved from
ITE to ITW. ITW is configured to take proton
beam now.
  
  202   Tuesday, November 06, 2012, 11:06 Travis CaveITWStandard OperationTM1Nb#7module moveTM#1 with Nb#7 has been moved from the
west target station to the south hot cell
move went well.
  
  204   Tuesday, November 06, 2012, 12:08 David WangITWStandard OperationTM1Nb#7TM1 disconnected in ITWBevan and I disconnected TM1 in ITW this
morning. The TM1 was moved to south hot cell
later.   
  