Entry  Wednesday, August 26, 2015, 14:28, David Wang, Conditioning Station, Standard Operation, TM2, ZrC, Leak check on TM2 HS and windowwater line with new ZrC target at SHC 
Chad and I leak checked TM2 HS and window circuit VCR joints with ZrC target and containment box installed at SHC. No leak has been found. They will
  be helium pressurized  at CS later.
Entry  Wednesday, August 26, 2015, 14:30, David Wang, Conditioning Station, Standard Operation, TM2, ZrC, TM2 and Cs vacuum sysyem has been connected at CS. 
Turbo-pumps are started . The pumping down is good so far.
Entry  Wednesday, August 26, 2015, 14:52, David Wang, Conditioning Station, Standard Operation, TM2, ZrC, Helium pressure test on TM2 HS and window lines at CS 
LD base LR 0.0xE-9 atm.cc/sec , 80 psi helium 2 minutes on HS and window circuits. No leak. Also, the reinstalled(after rewiring job) TP2 and PNG1(steers)
side panel have been leak checked. No leak.
Entry  Thursday, August 27, 2015, 08:43, Travis Cave, Conditioning Station, Standard Operation, TM2, ZrC #7, Electrical Check TM2_elec_chk_ZrC7_CS.PDF
Electrical check of TM#2 at the conditioning station under vacuum. The resistance value of the target to 60kV common is a bit lower then what it was
at the south hot cell.
Entry  Thursday, August 27, 2015, 10:10, Anders Mjos, Conditioning Station, Standard Operation, TM2, ZrC#7, Conditioning new Source Tray 2015-08-31_Service_Cap_Sparking_on_Rubber_Plug.pdfTM2_Source_Tray_with_ZrC#7.docxVacuum_gague_calibration.xlsx
Thursday, August 27, 2015, 10:10: Started water system. TK2 level reduced from 24.9 to 23.5 in. 
IG2 not working. Force is ON.

EE in conditioning mode.
Entry  Tuesday, September 01, 2015, 06:25, David Wang, Conditioning Station, Standard Operation, TM2, ZrC, Argon venting TM2 at CS 
Argon venting TM2 at CS.
Entry  Tuesday, September 01, 2015, 10:32, Travis Cave, ITW, Standard Operation, TM2, ZrC #7, Module moved 
TM#2 with ZrC#7 has been moved from the conditioning station  to the west target station.
Entry  Tuesday, September 01, 2015, 10:38, David Wang, ITW, Maintenance, TM2, , ITW top tank flange clean up and r-ring replacement. ITW_o-ring_replacement_2015-09-01_008.JPGITW_o-ring_replacement_2015-09-01_007.JPGITW_o-ring_replacement_2015-09-01_006.JPG
During last run, ITW dump circuit had a water leak on an adaptor below the pressure gauge. The top tank flange, slot, and O-ring were water contaminated
by the leak. I removed the old o- ring, cleaned up the flange and o-ring slot, and put a new o-ring into the flange. Some  pictures will be attached
in this mail later.
Entry  Tuesday, September 01, 2015, 14:54, David Wang, ITW, Standard Operation, TM2, , TM2 has been connectec in ITW. 
TM2 has been connected in ITW. During the connection, Anders and I  found the TM2  high current cables used in ITE and CS are short in ITW. 
Anders and Grant found the original TM2 ITE high current cables in target hall. We replaced them. They works fine. But, a little bit longer on cable length
would be easy to connect them. All other connections and HV cover in ITW work for the TM2 so far.
Entry  Tuesday, September 01, 2015, 16:03, Grant Minor, ITW, Standard Operation, TM2, ZrC #7, Photos of TM2 Connection Procedure on Docushare 1Sept2015 
https://documents.triumf.ca/docushare/dsweb/View/Collection-15323
Entry  Tuesday, September 08, 2015, 10:11, David Wang, ITW, Standard Operation, TM2, ZrC, 5 Shielding blocks have been transferred from ITE to ITW. 
Maico and Dan moved 5 shielding blocks from ITE to ITW. The ITW is configured to take proton beam.
Entry  Friday, September 11, 2015, 14:31, Anders Mjos, Conditioning Station, Maintenance, TM2, ZrC#7, Vacuum gauge and EPICS read back calibration 
The corelation betwenn the local value on the gauge controllers and the read back valiues in EPICS was compared. Data can be found in a previous  e-log
Entry  Wednesday, October 14, 2015, 12:42, David Wang, ITW, Standard Operation, TM2, ZrC#7, TM2 has been disconnected in ITW  
Dan and I disconnected TM2 in ITW this morning.
Entry  Wednesday, October 14, 2015, 12:44, David Wang, ITW, Standard Operation, TM2, ZrC#7, TM2 has been moved from ITW to SHC 
Bill and I remotely removed TM2 from ITW to SHC. The move is smooth.
Entry  Wednesday, October 14, 2015, 12:48, David Wang, South Hot-Cell, Standard Operation, TM2, ZrC#7, TM2 ZrC#7 after run electrical check at SHC. ZrC_#7_after_run_electrical_check.pdf
I did an electrical check on TM2 with ZrC #7 on it. The EE is short to 60KV bias. See attachment
Entry  Wednesday, October 14, 2015, 14:03, chad fisher, South Hot-Cell, Standard Operation, TM2, ZrC#7, ZrC#7 removed 20151014_134022.jpg20151014_135127.jpg
ZrC#7 has been removed from TM2. Everything looks good.
Entry  Wednesday, October 14, 2015, 14:49, David Wang, South Hot-Cell, Standard Operation, TM2, , Install new high current cables to TM2 TM2_Febiad_High_current_cables_047.JPGTM2_Febiad_High_current_cables_048.JPGTM2_Febiad_High_current_cables_049.JPG
I installed a set of new high current cables for TM2 Febiad run. The top of TM2  is configured to Febiad mode. See attachments
Entry  Thursday, October 15, 2015, 08:07, David Wang, South Hot-Cell, Standard Operation, TM2, no target, TM2 no target electrical check at SHC. TM2_electrical_check_2015-10-16_no_target.pdf
I did a TM2 no target electrical check at SHC this morning. A to RU at 500v  is 250K which is low.   anode- x pin is dead short to 60kv
bias. RU is dead short to 60kv bias( as before).   see attachment
Entry  Thursday, October 15, 2015, 14:17, chad fisher, South Hot-Cell, Repair, TM2, , Anode Connector Install and adjustment 20151015_085914.jpg
The TM2 containment box was removed this morning for installation of the 9 pin connector...connection.
The 9 pin connector copper tube connection was made and Anders advised on routing of the cable to the banana plug water block connection.
Short was diagnosed (short disappeared when water block was pushed slightly towards center of module) and thicker Ultem spacer installed and tested
Entry  Monday, October 19, 2015, 11:53, chad fisher, South Hot-Cell, Standard Operation, TM2, SiC#32, SiC#32 installed on TM2 
SiC#32 has been installed on TM2. High current fasteners torqued to 130 in lbs.