ID Date Author Category Type Moduledown Target/Number Subject Text Attachments
  1001   Friday, July 17, 2015, 13:51 chad fisherSouth Hot-CellRepairTM2 TM2 StatusGas lines extensions installed yesterday
were too long and gas lines touched top inside
of containment box. They have been removed
 20150717_134123.jpg 
  1002   Monday, July 20, 2015, 14:12 chad fisherSouth Hot-CellRepairTM2 TM2 StatusUltem high voltage spacer installed and
9 pin banana plug plugged in. Target has
been inserted into the hot cell and will
 20150720_134819.jpg20150720_135747.jpg20150720_140100.jpg 
  1003   Monday, July 20, 2015, 17:11 Grant MinorSouth Hot-CellRepairTM2 TM2 New Source Tray - additional photos 20 July 2015A few additional higher-resolution photos
of the TM2 source tray with new spacer ITA6270,
and bent copper ground line clip.
 3-8ths_gap_check_15July2015.JPGTM2_New_Source_Tray_20July2015.JPGTM2_Spacer_ITA6270_and_copper_ground_clip_detail_20July2015.JPG 
  1004   Tuesday, July 21, 2015, 09:21 Travis CaveSouth Hot-CellStandard OperationTM2no targetElectrical Check FailedTM#2 has failed the electrical check see
attached pdf for details.
 TM#2_elec_chk_source_tray_no_tgt.PDF 
  1005   Tuesday, July 21, 2015, 10:40 Grant MinorAssembly/Bench TestRepairTM2 TM2 - bench inspection photos from 6-June-2015   TM2_Source_Tray_Bench_Inspection_6-June-2015_04.JPGTM2_Source_Tray_Bench_Inspection_6-June-2015_13.JPGTM2_Source_Tray_Bench_Inspection_6-June-2015_11.JPG 
  1008   Wednesday, July 22, 2015, 11:31 Travis CaveSouth Hot-CellStandard OperationTM2no targetElectrical CheckElectrical check done on TM#2 around the
25th of June 2015, this was before the coil
line leak was found.
 TM#2elecchksourcetraynotgt62515.PDF 
  1009   Wednesday, July 22, 2015, 12:13 chad fisherSouth Hot-CellRepairTM2 TM2 Short FindingsPin X was unplugged, short remained, however
any slight pressure on the block towards
the source tray makes the short go away.
 TM2_Short_July_22.jpg 
  1012   Friday, July 24, 2015, 14:41 Travis CaveSouth Hot-CellStandard OperationTM2no targetModule movedTM#2 has been moved from the south hot
cell to north east silo.
  
  1030   Thursday, August 06, 2015, 11:40 Travis CaveSouth Hot-CellStandard OperationTM2no targetModule movedTM#2 is now in the south hot cell   
  1032   Monday, August 10, 2015, 14:07 Isaac EarleSouth Hot-CellRepairTM2 TM2 Containment Box RemovedThe containment box was taken off TM2 in
preparation for installation of a new coil
line isolator.
  
  1033   Thursday, August 13, 2015, 09:17 chad fisherSouth Hot-CellRepairTM2 TM2 statusTuesday, August 11,  insulator ITA6272
was installed onto the "pin x"
line (unused plasma electrode) and tested;
 20150811_132709.jpg20150813_083255.jpg20150813_090814.jpg 
  1034   Thursday, August 13, 2015, 11:34 Travis CaveSouth Hot-CellStandard OperationTM2Dummy TargetElectrical CheckElectrical check of TM2 without target
after that widget has installed, electrical
check with the shunts on, electrical check
 TM2_elechknotgtafterwidget.PDFTM2_elechknotgtshunt.PDFTM2_elecchkdummytgt.PDF 
  1035   Thursday, August 13, 2015, 13:46 chad fisherSouth Hot-CellRepairTM2 TM2 StatusAs previously mentioned, dump target installed
with new mounting and high current fasteners.
Leak Check complete and ready to
  
  1036   Thursday, August 13, 2015, 14:36 Travis CaveConditioning StationStandard OperationTM2Dummy TargetModule movedTM#2 with the dummy target has been moved
to the conditioning station.
  
  1037   Thursday, August 13, 2015, 17:17 David WangConditioning StationRepairTM2Dummy targetTM2 at CSTM2 has been moved to CS. All turbo-pumps
have been started. The pumping down is good
so far.  I connected the leak detector
  
  1038   Friday, August 14, 2015, 10:00 David WangConditioning StationRepairTM2 Started CS water package for TM2 I finished the rest TM2 connections to
CS, and started CS cooling package. Everything
works fine so far.
  
  1039   Monday, August 17, 2015, 10:44 Anders MjosConditioning StationDevelopmentTM2LP-FEBIAD Test Target (empty)Conditioning TM2 Source Tray with FEBIAD test targetTGHT, TBHT, ANODE and COIL power tested
(some amps/volts)
Monday, August 17, 2015, 10:43: BIAS/EL/EE
 FirstBeamTM2SourceTray2015-08-17.pngTM2_Source_Tray_with_FEBIAD_test_target.docx 
  1040   Wednesday, August 19, 2015, 14:52 David WangConditioning StationRepairTM2 TM2 at CSDuring the TM2 HV test at CS, It failed.
In order to confirm there is no any water
leak inside the module after the heaters
  
  1041   Thursday, August 20, 2015, 09:38 David WangConditioning StationRepairTM2 TM2 was disconnected at CSTM2 was disconnected at CS. Travis and
I did  electrical check before the venting.
After,The module was vented and moved to
  
  1042   Thursday, August 20, 2015, 10:15 Travis CaveSouth Hot-CellStandard OperationTM2Dummy TargetModule movedTM#2 is now in the south hot cell.   