  RH-ISAC, Page 59 of 138  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
  ID Date Author Category Type Module Target/Numberdown Subject Text Attachments
  1940   Wednesday, June 12, 2019, 08:56 Carla BabcockConditioning StationMaintenanceTM4No targetMore TM4 conditioning without source trayThe conditioning station was ramped down
overnight and David ramped it back up this
morning. Currently trying to get it to sit
  
  2296   Thursday, January 20, 2022, 08:18 David WangNorth Hot-CellStandard OperationTM4No targetTM4 was removed from NHC to S_W silo yesterday. TM4 was removed from NHC to S_W silo yesterday. 
The remove is smooth and successful. 
  
  2745   Thursday, January 09, 2025, 11:46 David WangSafe Module ParkingStandard OperationTM4No targetSMP is under vacuum for TM4 storage during shut down.  SMP:MP1 is started with SMP BV1 is
opened. SMP is under vacuum for TM4 storage
during shut down.
  
  2750   Thursday, January 16, 2025, 14:21 David WangConditioning StationStandard OperationTM3No targetTM3 electrical check at TCS under good vacuum A
complete TM3 electrical check at TCS under
good vacuum has been done. Pin 14 to 60KV
 TM3_electrical_check_@TCS_page_1.pdfTM3_electrical_check_@TCS_page_2.pdf 
  2755   Tuesday, January 28, 2025, 11:47 David WangConditioning StationStandard OperationTM3No targetTm3 has been moved from TCS to silo.Tm3 has been moved  from TCS to silo.
The move is successful.
  
  350   Wednesday, May 15, 2013, 18:12 Bevan MossConditioning StationStandard OperationTM3No source trayHV test repeat After discussion with Friedhelm it
was decided to continue trying to condition
the module today before moving it tomorrow.
 15052013_TM3_HV_test_repeat.xlsx 
  398   Friday, July 05, 2013, 10:02 Bevan MossConditioning StationStandard OperationTM3No source trayTM3 module move to TCSTM3 has been moved from the south hot cell
to the conditioning station. David and I
completed the move. All went well.
  
  85   Monday, April 16, 2012, 16:17 Bevan MossConditioning StationStandard OperationTM1No TargetHigh Voltage Test A high voltage test was completed
on a target free TM1 in the conditioning
station. Only the turbo pumps on the target
  
  1952   Monday, July 22, 2019, 14:51 Adam NewsomeSouth Hot-CellStandard OperationTM4No TargetTM4 MoveTM4 has been moved from the South West
silo to the South Hot Cell. New source tray,
no target.
  
  1957   Wednesday, July 31, 2019, 08:57 Adam NewsomeSouth Hot-CellStandard OperationTM4No TargetTM4 MoveTM4 has been moved from the Conditioning
Station to the South Hot Cell. No target.
  
  339   Friday, May 10, 2013, 11:28 Bevan MossConditioning StationStandard OperationTM3No Source TrayRoughing Started Roughing on TM3 was started at 11:26am
today
  
  340   Friday, May 10, 2013, 14:05 Bevan MossConditioning StationStandard OperationTM3No Source TrayTurbo Pumps OnThe turbo pumps are on. TP1 and TP2 once
again timed out and had to be restarted before
they would stay on.
  
  344   Wednesday, May 15, 2013, 10:17 Bevan MossConditioning StationStandard OperationTM3No Source TrayPreliminary Results from HV testing Testing on TM3 without a source tray
was completed on 13/05.2013. All items were
tied to common and the water blocks were
 module_hv_test_0KV.rgaMODULE_hv_test_42kv.rgaTM3_13052013_no_source_tray.xlsx 
  348   Wednesday, May 15, 2013, 16:51 Bevan MossConditioning StationStandard OperationTM3No Source TrayRepeat of HV Test The HV test completed on Monday was
repeated today over a much longer time period.
By taking longer there was slightly less
 150502013_TM3_No_Source_Tray.xlsx 
  354   Tuesday, May 21, 2013, 11:52 Bevan MossConditioning StationStandard OperationTM3No Source TrayMay 16th Long HV conditioningOn May 16th 2013 the module was HV conditioned
all day. As a result the maximum stable voltage
has been increased to about 47kV (~4kV more
 16052013_TM3_long_HV_conditioning.xlsx 
  404   Monday, July 22, 2013, 15:52 Bevan MossConditioning StationStandard OperationTM3No Source TrayHV testing update   I have fallen behind on the
HV testing that has been completed on TM3.
Data can be found on docushare in the TM3
  
  464   Wednesday, September 25, 2013, 10:00 Travis CaveSouth Hot-CellStandard OperationTM3NiO#2module moveTM#3 with NiO#2 has been moved from the
south hot cell to the conditioning station.
  
  465   Wednesday, September 25, 2013, 11:08 Travis CaveSouth Hot-CellStandard OperationTM3NiO#2Electrical checkThe module was checked electrically this
morning before the module move. See the attached
PDF for details.
 TM#3_elec_chk_NiO#2_SHC.PDF 
  466   Wednesday, September 25, 2013, 13:48 Travis CaveConditioning StationStandard OperationTM3NiO#2Electrical checkElectrical check of TM#3 in the conditioning
station under vacuum see attached PDF for
details.
 TM#3_elec_chk_NiO#2_CS.PDF 
  468   Thursday, September 26, 2013, 14:31 Bevan MossSouth Hot-CellRepairTM3NiO#2Activities September 24 - 25September 24
 After the manipulator repair
Maico installed the NiO#2 onto the target
 elec_check.pdf 