2037
|
Thursday, December 12, 2019, 14:39 |
Isaac Earle | Safe Module Parking | Development | | | SMP assembly shifted 1.0" north | The SMP assembly was shifted approximately
1.0" north today by pushing it, braced
against the south wall, using a 100 Ton capacity |
|
|
2196
|
Thursday, March 04, 2021, 16:30 |
Isaac Earle | North Hot-Cell | Development | | | NHC gas delivery lines leak checked | The North Hot Cell gas delivery lines
(labeled 1, 2, and 3 on the hot and cold
side panels) were leak checked today. |
|
|
2200
|
Monday, March 15, 2021, 13:01 |
Isaac Earle | Crane | Development | | | Plate & pin lift assembly load testing (ITA6550) | In mid-2020 design analysis was completed
on the steel plate & pin assemblies (ITA6550)
used to connect the ISAC target hall crane |
11x |
|
68
|
Tuesday, January 10, 2012, 11:51 |
Grant Minor | Conditioning Station | Repair | | | IMC at Cond. Station is VENTED - DO NOT PUT MODULE IN | Hi Remote Handling,
The guage on the IMC circuit in the
Target Hall is reading atmosphere, and the |
|
|
129
|
Wednesday, June 20, 2012, 11:39 |
Grant Minor | South Hot-Cell | Development | TM3 | N/A | TM3 Planned Activites at South Hot Cell Jun 20 to 29 2012 |
Normal
0
false
false
false
|
|
|
148
|
Wednesday, July 18, 2012, 16:49 |
Grant Minor | South Hot-Cell | Development | | | South Hot Cell Ventilation Alarm Trip | Today (Wednesday July 18th) at around 4:15
pm I was taking a small tour group from
VECC into the Target Hall. In the process |
|
|
149
|
Wednesday, July 18, 2012, 16:49 |
Grant Minor | South Hot-Cell | Development | | | South Hot Cell Ventilation Alarm Trip | Today (Wednesday July 18th) at around 4:15
pm I was taking a small tour group from
VECC into the Target Hall. In the process |
|
|
218
|
Monday, December 03, 2012, 19:34 |
Grant Minor | ITE | Standard Operation | TM4 | LpUCx | Argon supply opened for ITE vent | Around 7pm tonight I opened the main valve
approximately 1.5 turns on the Argon bottle
used for venting ITE, located in the ISAC |
  |
|
222
|
Wednesday, December 05, 2012, 13:26 |
Grant Minor | South Hot-Cell | Standard Operation | TM4 | N/A | TM4 moved from SHC to South West Silo | TM4 was successfully moved from the South
Hot Cell to the South-West Silo remotely
by Grant Minor, with help from David Wang |
|
|
238
|
Friday, January 18, 2013, 16:56 |
Grant Minor | Conditioning Station | Standard Operation | TM4 | | VAT valve btwn roughing and nuc. vent. closed | Bevan attempted to start pumping down on
TM4 today remotely but there was an issue.
He will report on Monday. |
|
|
239
|
Friday, January 18, 2013, 17:01 |
Grant Minor | Conditioning Station | Development | TM4 | | Photos of the CS with TM4 (after the no-module HV test, only vacuum connected) | Attached are some photos of TM4 in the
Conditioning Station after the no-module
HV test completion. Only vacuum services |
   |
|
243
|
Friday, February 08, 2013, 11:42 |
Grant Minor | ITE | Maintenance | | | TAPC 477 resolved - ISAC elec. room gas cylinder | See attached TAPC 477 documentation. |
|
|
423
|
Wednesday, August 21, 2013, 20:36 |
Grant Minor | South Hot-Cell | Repair | TM3 | | TM3 module-side water block sealing surface inspection (post polishing) | The water block sealing surfaces on the
module-side of TM3 were polished this week
by Chad Fisher, using his air-ratchet controlled |
 |
|
424
|
Thursday, August 22, 2013, 19:38 |
Grant Minor | South Hot-Cell | Repair | TM3 | | TM3 Rev 3 source tray - water blocks connected and torqued | After a great struggle with the water block
jigs, the TM3 source tray was finally advanced
fully into the service tray and all water |
6x |
|
425
|
Friday, August 23, 2013, 18:32 |
Grant Minor | South Hot-Cell | Repair | TM3 | | TM3 Rev 3 - steerer wire broken from connector on module side | While continuing on the TM3 Rev 3 source
tray installation, Chad noticed today that
one of the steerer wires is broken and has |
    |
|
426
|
Monday, August 26, 2013, 18:22 |
Grant Minor | South Hot-Cell | Repair | TM3 | | TM3 Rev 3 - all connetions made except steerers, IMG, and entrance window | Today Chad finished making all connections
to the new source tray, except for:
- steerers - broken wire, must be |
8x |
|
427
|
Monday, August 26, 2013, 18:26 |
Grant Minor | Conditioning Station | Standard Operation | TM3 | | TM3 moved from Hot Cell to Conditioning Station | Target Module 3 with no target, and a partially-installed
Rev-3 source tray (no steerers connected,
no IMG connected, entrance window lines blanked |
|
|
431
|
Tuesday, August 27, 2013, 17:18 |
Grant Minor | Conditioning Station | Repair | TM3 | no target | TM3 Rev 3 source tray - prelminary leak check results at CS | David Wang started a helium leak check
on TM3 at the CS this morning.
David will create an e-log once his |
 |
|
437
|
Thursday, August 29, 2013, 12:03 |
Grant Minor | South Hot-Cell | Repair | TM3 | no target | Heat Shield Circuit Leak |
|
  |
|
442
|
Wednesday, September 04, 2013, 18:53 |
Grant Minor | South Hot-Cell | Repair | TM3 | | Maico's measurements of new c-seals and bench-tested c-seals | Today Maico measured the thickness of three
indium-plated inconel c-seals, presumably
Ultra-Seal P/N 50606. These seals had |
 |